United States Fidelity & Guaranty Co. v. G-K Construction Company, Inc., and Cross-Plaintiff-Appellant, Henderson County, Tennessee, and Cross-Defendant-Appellee

767 F.2d 922, 1985 U.S. App. LEXIS 14338
CourtCourt of Appeals for the Sixth Circuit
DecidedJune 10, 1985
Docket83-5418
StatusUnpublished

This text of 767 F.2d 922 (United States Fidelity & Guaranty Co. v. G-K Construction Company, Inc., and Cross-Plaintiff-Appellant, Henderson County, Tennessee, and Cross-Defendant-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. G-K Construction Company, Inc., and Cross-Plaintiff-Appellant, Henderson County, Tennessee, and Cross-Defendant-Appellee, 767 F.2d 922, 1985 U.S. App. LEXIS 14338 (6th Cir. 1985).

Opinion

767 F.2d 922

Unpublished Disposition
NOTICE: Sixth Circuit Rule 24(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Sixth Circuit.
UNITED STATES FIDELITY & GUARANTY CO., PLAINTIFF,
v.
G-K CONSTRUCTION COMPANY, INC., DEFENDANT AND
CROSS-PLAINTIFF-APPELLANT,
HENDERSON COUNTY, TENNESSEE, DEFENDANT AND CROSS-DEFENDANT-APPELLEE.

NO. 83-5418

United States Court of Appeals, Sixth Circuit.

6/10/85

W.D.Tenn.

VACATED AND REMANDED

On Appeal from the United States District Court for the Western District of Tennessee, Eastern Division

Before: KENNEDY and CONTIE, Circuit Judges; and EDWARDS, Senior Circuit Judge.

PER CURIAM.

G-K Construction Company, Inc. appeals from the District Court's judgment, following a bench trial, in favor of cross-defendant Henderson County in this construction contract dispute. Because the District Court's findings are not sufficient to dispose of all of G-K's claims against Henderson County, we must remand to the District Court for additional findings.

In December 1978 G-K contracted to build a county health department building for Henderson County. The contract price, after certain deletions from the original specifications, was $222,777. Construction was to begin in December 1978, but the start was delayed until April. As the construction progressed, considerable friction developed between G-K and its president, Gerald Kirksey, and the county and its architect, Howell Taylor. On February 13, 1985, the architect notified G-K of ten deficiencies in the building, and on that same date the county informed G-K that the contract would be terminated unless the deficiencies were corrected in ten days. On February 27, 1980, the county terminated the contract.

As of the termination date the county had already paid G-K $174,713, and had withheld $20,632 in retainage. G-K had an additional outstanding application for payment of $10,978 for work already done. The county eventually completed the building through another contractor for an additional cost of $39,873.

The county filed a claim against G-K's bonding agent, U.S.F. & G., which then filed this declaratory judgment action against G-K and Henderson County. G-K and Henderson County each filed cross-complaints, claiming that the other party had committed various contract breaches. After a bench trial, the District Court found that 'the work performed by G-K, or under its direction, contained many instances of improper workmanship, some of which [are] quite serious and not feasibly subject to correction,' and that the county 'was justified in terminating the contract.' Judgment was entered directing the county to pay G-K the outstanding $10,978 application for payment1, allowing the county to keep the withheld retainage, dismissing G-K's claims for breach of contract and the county's claims for liquidated damages, and absolving U.S.F. & G. from liability.

G-K now appeals the dismissal of its cross-claims against the county. Henderson County filed no cross-appeal. The District Court's judgment on Henderson County's cross-claim for liquidated damages is therefore final. No separate judgment was entered for the county on its claim for diminution of the value of the building due to poor workmanship. Nor was any finding made as to the diminution in value. The District Court's opinion permitted the county to keep the $20,632 it still held as a retainage 'as an offset to the diminution in value for the faulty workmanship performed by G-K or under its supervision' and entered judgment for Henderson County, but not in any dollar amount. G-K complains that the District Court erred in awarding the offset. We agree, although not for the reasons urged by G-K. The District Court made no finding as to the amount of the diminution in value because of faulty workmanship. If it intended to find that it was $20,632 there is no basis in the record for that particular sum. On remand the District Court should make specific findings as to what diminution value, if any, the county has proved.

We turn then to whether the District Court properly dismissed G-K's breach of contract claims. We are not able to determine whether the dismissal was proper because of the absence of sufficient findings. In cases tried to the court the District Court must set forth its findings of fact and conclusions of law. Fed. R. Civ. P. 52(a). Without specific factual findings concerning the alleged breaches in this case, we are left without an adequate basis for appellate review. Rule 52(a) requires the trial court to state factual findings 'with sufficient detail to indicate the factual basis for its ultimate conclusions of law. Otherwise, appellate review is rendered practically impossible, and we are usually left with no alternative but to vacate the judgment and remand the case for further findings.' Ionmar Compania Naviera, S.A., v. Olin Corp., 666 F.2d 897, 903 (5th Cir. 1982).

G-K has alleged a number of different contract breaches on the part of the county. We will first consider G-K's claim that the county's termination of the project was wrongful. The contract provided that if the contractor:

is guilty of a substantial violation of a provision of the Contract Documents, then the Owner, upon certification by the Architect that sufficient cause exists to justify such action, may, without prejudice to any right or remedy and after giving the Contractor and his surety, if any, seven days' written notice, terminate the employment of the Contractor . . ..

G-K contends that the termination was wrongful for five reasons: (1) the termination was not made for a permissible reason; (2) G-K's workmanship did not justify termination; (3) by making partial payments, the county waived any defects in workmanship covered by those payments; (4) the architect did not certify that there was cause for termination; and (5) the county was not entitled to terminate the contract because it was itself in breach of the contract.

The first three of these contentions are without merit. G-K argues that the contract was terminated not for contractual reasons, but because of G-K's 'lack of cooperation,' quoting the county's termination letter. However, it is clear that the lack of cooperation referred to in that letter is the failure to correct the deficiencies so as to conform substantially to the plans and specifications. The District Court's factual finding that the work performed by G-K did not substantially conform to the plans and specifications is supported by the testimony of two architects, cited by the District Court, and is not clearly erroneous. G-K's theory that partial payments constitute waiver of defects in the work is belied by the fact that the contract allows the county to keep retainage in order to offset possible defects. In J.R. Hale & Sons v. R.C. Stone Engineering Co., 14 Tenn. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. R. Hale & Sons v. R. C. Stone Engineering Co.
14 Tenn. App. 461 (Court of Appeals of Tennessee, 1932)
R. Lee Tolley Co. v. Marr
12 Tenn. App. 505 (Court of Appeals of Tennessee, 1931)
Ionmar Compania Naviera, S.A. v. Olin Corp.
666 F.2d 897 (Fifth Circuit, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
767 F.2d 922, 1985 U.S. App. LEXIS 14338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-g-k-construction-company-inc-ca6-1985.