Central Towers Apartments, Inc. v. Martin

453 S.W.2d 789, 61 Tenn. App. 244, 1969 Tenn. App. LEXIS 288
CourtCourt of Appeals of Tennessee
DecidedDecember 5, 1969
StatusPublished
Cited by19 cases

This text of 453 S.W.2d 789 (Central Towers Apartments, Inc. v. Martin) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Towers Apartments, Inc. v. Martin, 453 S.W.2d 789, 61 Tenn. App. 244, 1969 Tenn. App. LEXIS 288 (Tenn. Ct. App. 1969).

Opinion

MATHERNE, J.

This appeal challenges a decree of the Chancellor which awarded to a surety on a contractor’s performance bond tire sum of $15,109.20 as attorney’s fees and litigation expenses incurred by the surety *248 in the defense of a suit brought by the owner against the contractor, the surety and others for damages due to the breach of the construction contract.

The contractor I. W. McGuire, Jr., d/b/a McGuire Construction Company, brings Writ of Error to this Court and assigns six errors. With exceptions herein noted, these Assignments of Error raise the one determinative issue of whether the Chancellor erred in awarding the surety its attorney’s fees and iltigation expenses.

Central Towers Apartments, Inc., the owner, entered into a contract with McGuire for the construction of an apartment building in Memphis, Tennessee. Royal Indemnity Company executed the contractor’s performance bond in the amount of the contract price and received its regular premium therefor. In order to obtain this bond McGuire, the contractor, executed an indemnity agreement to Royal Indemnity the surety wherein McGuire agreed to hold the surety harmless for any amount paid by the surety as an obligation under the contractor’s bond.

The apartment building was to be permanently financed by the Federal Housing Administration and "all plans, specifications, the construction, payments and the final acceptance of the building were subject to the approval of that Agency.

The construction contract is dated February 24, 1961. This contract is a “cost plus” contract wherein the owner agreed to pay the costs of labor and material expended plus 6.75 percent, with a top side limitation of $2,074-, 394.00. The contractor was to commence construction within thirty days and complete the work within twenty-four months from date of contract. This contract had the *249 customary retainage clause to the effect that each month when the contractor submitted a monthly estimate of the labor expended and material in place he would receive 90% of that sum and 10% would be withheld by the owner as a retainage to insure complete performance by the contractor. The final contract price was $2,103,013.94, and 10% thereof was subject to retention until the contract was completed.

The building was completed and accepted by the owner on December 12, 1962. This acceptance was subject to the correction of certain deficiencies noted at that date. The sum of $26,900.00 was set up in an escrow account to insure correction of the deficiencies noted. This acceptance was made with the approval of the owner, the architect, the contractor and the Federal Housing Administration, subject to the correction of listed discrepancies, and subject to a nine month and twelve month inspection and approval of construction by the Federal Housing Administration. The instruments signed on that occasion by the contractor clearly provided that the contractor remained liable on construction contract warranties.

Bather extensive leaks developed in the heating and airconditioning units. The Chancellor found that sometime in January 1963 there had developed about 300 such leaks and the owner at that time knew of this deficiency. The heating and airconditioning sub-contractor repaired numerous leaks at no charge to the owner. It developed that to attempt a repair of the units would not correct the deficiency. The manufacturer of the units, thereupon, at its cost, replaced throughout the building these defective units. This leakage caused some water damage to the building, and the owner alleged it caused him exten *250 sive rent loss and other damage. It is to be noted the $26,900 escrow deposit of December 12,1962 did not specifically cover the defective airconditioning nnits as they were not listed as defective and apparently were not known to be defective at that time.

The owner filed suit in the Chancery Court of Shelby County, Tennessee on November 5, 1963 for $350,000.00 as damages due to breach of contract. This suit named as defendants the contractor, surety, architect, heating and airconditioning subcontractor, heating and aircondi-tioning equipment manufacturer, and the plumbing and plastering sub-contractors. After prolonged pleading, cross-bills and amendments to pleadings and cross-bills, and the taking of various depositions the case was set for trial on oral testimony before the Chancellor without a jury on May 8, 1968. On that date the claim of the owner, Central Towers Apartments, Inc. was settled by payment to it of the sum of $28,000.00. The record establishes that after allowance for various set-offs and claims by the parties one against the other, the substance of the settlement was that most of this amount was paid by the heating and airconditioning equipment manufacturer. The surety on the contractor’s bond did not pay any amount, and apparently contributed little if any effort toward the settlement. In fact there is competent evidence that the surety was uncooperative toward the efforts to settle.

In the pleadings the contractor brought a cross action against the heating and airconditioning sub-contractor and the manufacturer of that equipment. The surety sought judgment over against the contractor for any amount it might be held liable to pay and also sought judgment for its attorney’s fees and litigation expenses *251 as against the contractor. After the matter had been settled as to all parties the Chancellor heard the issue on the surety’s cross action against the contractor for its attorney’s fees and expenses incurred, and rendered judgment in its favor as heretofore noted.

Based upon the December 12,1962 acceptance the owned paid the contractor the amount due under the contract as follows: As of December 15, 1962 the owner had paid $1,769,500.00; on January 17, 1963 the owner paid $175,000.00 cash, claimed a credit of $5,503.59 for construction costs paid by it and deposited the $26,900.00 in escrow for correction of deficiencies noted on December 12, 1962, leaving a balance due of $126,110.35; on February 25, 1963 the owner paid $106,110.35 cash and executed its note in the amount of $20,000. The foregoing payments,, escrow deposit, claim for credit and note total the contract price of $2,103,013.94, The owner did not withhold the 10% retainage.

Another matter concerning acts between the owner and the contractor must be here noted. The facts establish that to enable the owner corporation to enter info the project the contractor agreed to- lend to the owner a sum of between $50,000.00 and $100,000.00 to be used in construction of the building. As consideration and inducement to the contractor to make this loan the owner gave to the contractor an option to purchase 50% of its common stock at the price of $1.00 per share. The Chancellor found that $98,610.50 was advanced by the contractor to the owner under this agreement. At some point of time thereafter one F. Allen Brown sought to purchase the owner corporation, and in consideration of the contractor assigning to him- the option to purchase 50% of the stock *252

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gulf Insurance v. AMSCO, Inc.
889 A.2d 1040 (Supreme Court of New Hampshire, 2005)
Sentinel Trust Co. v. Universal Bonding Insurance
316 F.3d 213 (Third Circuit, 2003)
Gulf Insurance Co. v. Construx, Inc.
Court of Appeals of Tennessee, 2001
Old Republic Surety Co. v. Morris Eshaghpour
Court of Appeals of Tennessee, 2000
Fallon Electric Co. v. Cincinnati Insurance
121 F.3d 125 (Third Circuit, 1997)
James Constructors, Inc. v. Salt Lake City Corp.
888 P.2d 665 (Court of Appeals of Utah, 1994)
Perkins v. Thompson
551 So. 2d 204 (Mississippi Supreme Court, 1989)
Wilson & Co. v. Walsenburg Sand & Gravel Co.
779 P.2d 1386 (Colorado Court of Appeals, 1989)
Jackson v. Hollowell
685 F.2d 961 (Fifth Circuit, 1982)
Sentry Insurance v. Davison Fuel & Dock Co.
396 N.E.2d 1071 (Ohio Court of Appeals, 1978)
Perry v. Lockert
414 F. Supp. 169 (M.D. Tennessee, 1976)
US FOR USE AND BENEFIT OF SHANKLE-CLAIRDAY v. Crow
414 F. Supp. 160 (M.D. Tennessee, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
453 S.W.2d 789, 61 Tenn. App. 244, 1969 Tenn. App. LEXIS 288, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-towers-apartments-inc-v-martin-tennctapp-1969.