US FOR USE AND BENEFIT OF SHANKLE-CLAIRDAY v. Crow

414 F. Supp. 160, 20 U.C.C. Rep. Serv. (West) 47, 1976 U.S. Dist. LEXIS 17263
CourtDistrict Court, M.D. Tennessee
DecidedJanuary 9, 1976
Docket75-68-NA-CV
StatusPublished

This text of 414 F. Supp. 160 (US FOR USE AND BENEFIT OF SHANKLE-CLAIRDAY v. Crow) is published on Counsel Stack Legal Research, covering District Court, M.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
US FOR USE AND BENEFIT OF SHANKLE-CLAIRDAY v. Crow, 414 F. Supp. 160, 20 U.C.C. Rep. Serv. (West) 47, 1976 U.S. Dist. LEXIS 17263 (M.D. Tenn. 1976).

Opinion

MEMORANDUM

MORTON, District Judge.

Plaintiff Shankle-Clairday, Inc. brings suit pursuant to the provisions of the Miller Act, 40 U.S.C. § 270a et seq. to recover for material furnished to defendant J. Harvey Crow, a contractor. United States Fidelity & Guaranty Company is sued as surety for defendant Crow. Crow seeks recovery from plaintiff of damages allegedly resulting from the latter’s failure to timely perform its contract. This surety seeks judgment against Crow for any amounts it is required to pay by virtue of its bond.

On October 2, 1973, J. Harvey Crow contracted with the United States of America to make certain improvements on the seventh floor of the Federal Building in Nashville, Tennessee. Notice for J. Harvey Crow to proceed upon the performance of this contract was issued by the General Services Administration on October 12, 1973. The completion of the contract was required by January 15, 1974. The contract contained a provision requiring the contractor to pay liquidated damages to the United States of America in the amount of $15.00 per day for each day completion of the contract exceeded January 15, 1974.

*162 On October 8, 1973, United States Fidelity and Guaranty Company as surety executed a payment bond for J. Harvey Crow as principal whereby it agreed to be answerable for payment to all persons supplying labor and material in the prosecution of the work.

A portion of the contract provided for the installation of acoustical ceiling tile on the seventh floor of the Federal Building in Nashville, Tennessee.

Prior to November 29, 1973, J. Harvey Crow contacted Mr. Bruce Shankle, an officer of Shankle-Clairday, Inc. by telephone from his office in Brecksville, Ohio to inquire as to the availability of and to receive a price quotation for the acoustical ceiling tile specified in the government contract. During this telephone conversation, Bruce Shankle was informed that the contract was with the United States Government and included a provision requiring payment by the contractor of liquidated damages in the amount of $15.00 per day for each day completion of the contract exceeded the completion date. Shankle advised that acoustical ceiling tile was available, and could be supplied by Shankle-Clairday, Inc. between December 1, 1973, and December 15,1973, at a cost of $469.44. Thereupon, J. Harvey Crow orally placed an order for acoustical ceiling tile with Shankle-Clairday, Inc. and confirmed the purchase by written purchase order No. 666 dated November 29, 1973.

The tile was not delivered at the agreed time. Several conversations ensued between Shankle and Crow. Various delivery dates were projected by Shankle with the delivery being made on February 20, 1974. At no time did Crow terminate his contract with the plaintiff. Neither did he attempt to obtain the tile from other suppliers who had the product available.

As a direct result of the plaintiff’s failure to deliver on the date specified in the contract, the defendant completed performance on March 15, 1974, and was. assessed liquidated damages in the amount of $885.00. The plaintiff, through its officer Shankle, knew of the contract penalty provision and was generally familiar with Such provisions in government contracts.

By reason of the return of a portion of the tile, Crow is entitled to a credit of $24.00 on the sales price. Thus, the amount to be recovered by plaintiff, if successful, is the contract price ($469.44), less his credit, or $445.44. The court rejects the testimony of the witness Shankle as to the sales price of the tile.

Defendant Crow refused to pay the purchase price of the tile and asserted a set off claim against plaintiff for $885.00, Crow’s liquidated damages under the government contract. The defendant surety, on receiving notice of the dispute. and the claim against it as surety, demanded that Crow furnish it a defense. Crow refused to do so. Thereafter, the surety company employed an attorney who defended it against liability, filed an answer, a cross-claim against Crow, and participated in the trial of the cause. When the complaint was originally filed, another claimant, Norvell & Wallace, Inc. was seeking a judgment. Crow paid this claim immediately prior to the trial date.

As before stated, on March 17, 1975, United States Fidelity & Guaranty Company employed Ed R. Davies, an attorney of Nashville, Tennessee, to protect its interest in this cause. Davies will charge United States Fidelity & Guaranty Company a total of $970.00 for professional services rendered in this litigation, which amount the latter asserts is recoverable from the defendant Crow because of his refusal to provide the surety a defense.

The Miller Act is silent on the question of whether attorney’s fees are recoverable in actions brought under it. At least with respect to the rights of a successful plaintiff suing the principal and his surety under the Act, the Supreme Court has made it clear that the recovery of attorney’s fees is to be determined not by state law, as the defendant surety suggests, but by federal law, and that in federal courts the so-called “American Rule” governs. F. D. Rich Co. v. Industrial Lumber Co., 417 U.S. 116, 94 S.Ct. 2157, 40 L.Ed.2d 703 (1974). The *163 “American Rule” provides that attorney’s fees “are not ordinarily recoverable in the absence of a statute or enforceable contract providing therefor.” Id. at 126, 94 S.Ct. at 2163, 40 L.Ed.2d at 712. The absence of any such statutory or contractual provisions in the instant case is manifest and will be discussed in detail below. Thus, under the rationale of Rich, the surety’s claim for attorney’s fees from its principal might similarly be rejected. But since the issue in Rich was whether a successful plaintiff could recover attorney’s fees from the defendants, the question of whether an unsuccessful surety is similarly limited, is arguably outside the scope of that decision. Even if the defendant surety’s rights in the instant case were to be determined according .to state law (in this case, Tennessee law), however, the discussion below will demonstrate that the surety would be in no better position.

While there appear to be no Tennessee cases squarely on point, the relevant case law strongly suggests that a compensated surety (as opposed to an accommodation surety), in the absence of an indemnity agreement or a controlling statute, may not recover from its principal expenses which it incurs in defending a suit brought by an obligee against the principal and surety as codefendants, unless it has first satisfied some portion of the principal’s obligation.

This principle is not a novel one. In the 1869 case of Overton v. Hardin, 46 Tenn. (6 Coldwell) 375 (1869), the Tennessee Supreme Court ruled that an indorser (alternately referred to by the court as a surety) on a note “has no remedy against the maker, [i.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fleischmann Distilling Corp. v. Maier Brewing Co.
386 U.S. 714 (Supreme Court, 1967)
Transamerica Insurance Company v. Harry Bloomfield
401 F.2d 357 (Sixth Circuit, 1968)
Anderson-Gregory Co. v. Lea
370 S.W.2d 934 (Court of Appeals of Tennessee, 1963)
Gilson v. Gillia
321 S.W.2d 855 (Court of Appeals of Tennessee, 1958)
Central Towers Apartments, Inc. v. Martin
453 S.W.2d 789 (Court of Appeals of Tennessee, 1969)
Friedman v. Georgia Showcase Co.
183 S.W.2d 9 (Court of Appeals of Tennessee, 1944)
Petway v. Loew's Nashville Knoxville Corporation
117 S.W.2d 975 (Court of Appeals of Tennessee, 1938)
Gibson County Bank v. Shatz
12 Tenn. App. 281 (Court of Appeals of Tennessee, 1930)
Southern v. Beeler, Atty.-Gen.
195 S.W.2d 857 (Tennessee Supreme Court, 1946)
City of Bristol v. Bostwick
146 Tenn. 205 (Tennessee Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
414 F. Supp. 160, 20 U.C.C. Rep. Serv. (West) 47, 1976 U.S. Dist. LEXIS 17263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-for-use-and-benefit-of-shankle-clairday-v-crow-tnmd-1976.