City of Bristol v. Bostwick

146 Tenn. 205
CourtTennessee Supreme Court
DecidedSeptember 15, 1921
StatusPublished
Cited by38 cases

This text of 146 Tenn. 205 (City of Bristol v. Bostwick) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Bristol v. Bostwick, 146 Tenn. 205 (Tenn. 1921).

Opinion

Mr. Justice Bachman

delivered the opinion of the Court.

[209]*209This cause was before the court upon the bill, demurrer thereto, and cross-bills of creditors at the September term at Knoxville, 1917, and the action of the court thereon is reported in 139 Tenn., 304 et seq., 202 S. W., 61. Upon remand extensive proof was taken, upon which an advisory reference to a special master was ordered by the chancellor. The master reported that the contractor, Bostwick, was in default at the time the building commission took over the contract, and that he was entitled to no recovery thereon save for extra work in the sum of $160.90. It was further reported that Bostwick was liable to complainants under contractual provision for delay $4,125, as liquidated damages, leaving a balance of $1,959.35 due the city, it having in its possession $2,165.65 belonging to Bostwick. The identity of creditors was fixed, and the aggregate of their claims was found to be $21,271.87, for which the surety was held proportionately liable to the extent of $20,000, the amount of its bond. The master found that the surety was not released from its undertaking because of the payment of certain estimates, after notice, to the contractor and his assignees, but that it was liable for the claims of the creditors for labor and material, as well as for the costs and expenses of the suit, together with attorneys’- fees, fixed at $2,500. By the report the surety was held not liable for the city’s claim for liquidated damages on account of delay, no notice thereof having been given it, as provided under the indemnity phase of its bond.

Exceptions to the import were taken by both parties, all of which were overruled, with the exception of the reduction of the city’s claim for liquidated damages to the sum of $2,000; the report was in all things confirmed by the chancellor, and a decree in conformity thereto was entered.

[210]*210The case is before us upon appeals by both parties, and numerous errors are assigned, in support of which counsel present exhaustive briefs.

In the case of the Kingsport Improvement Corporation v. W. H. Bostwick and United States Fidelity & Guaranty Co. et al., a number of the questions here made have been adjudicated, and any discussion other than their enumeration is deemed unnecessary. The refusal of the chancellor to stay proceedings on account of military service of the defendant Bostwick, the payment of earned estimates to Bostwick, and his assignees, as well as the authority of the chancellor to order an advisory reference, upon questions of law and fact, and the authority to fix compensation for the special master, were passed upon, and need not here be further considered. Also the decision of this court upon the former appeal in this case is the law applicable, and is conclusive of certain other questions here made. That the defendant Bostwick Avas in default upon his contract and the city warranted in giving notice and subsequently assuming charge of the work is clearly shown in the proof. The dual obligation of the surety has been heretofore determined, and the record does not disclose any proof warranting the conclusion that, in the execution of the bond, the surety was in any wise deceived or misled; certainly to one engaged in the business of professional suretyship the insistence of the building commission that the bond be made to comply with the statutory requirements and the citation of authority for the necessity therefor was an unambiguous request, the effect of compliance with which could not have been misunderstood.

The allegations of the bill as to the delay and default of the contractor in the performance of his contract are fully [211]*211sustained by the proof, and the city was warranted in giving the required notice and assuming charge of the work. The contract entered into April 14, 1916, called for the completion of the main school building in October following, and the auditorium in January. In February there after neither of the buildings were finished, the contractor was insolvent, and it was apparent that he was wholly unable to complete his undertaking. While it may be admitted that conditions with reference to labor and construction material prevailing during the period within which the work was to be done were such as to impede the progress of the work, yet the delay, as shown by the record, is not attributable to causes exculpating the contractor, but rather to his personal inability to further the con-, struetion, as agreed upon. The contractor contends that he should not be held liable in any amount upon the provision in the contract stipulating an agreed per diem payment for delay, for the reason that the same is to be considered a penalty, and solely for the purpose of enforcing the completion of the contract, and for the further reason that the delay Avas the result of conditions over which he had no control. Considering the nature of the contract, the purpose for which the building was to be used, the public detriment to be contemplated by delay, with the difficulty of approximating the damage thereon, we think the stipulation complained of is a reasonable pre-ascertainment by the parties of the liquidated damages and is not to be regarded as a penalty. Vaulx v. Buntin, 127 Tenn., 118, 153 S. W., 481; Wise v. United States, 249 U. S., 361, 39 Sup. Ct., 303, 63 L. Ed., 647.

It was the opinion of the learned chancellor that notice given within thirty days after abandonment by the prin[212]*212cipal contractor, or within thirty days after the completion of the contract by the city, or at any time after the debts became due, and within thirty days after the completion of the work to be done under the contract, was a sufficient compliance with the provision of the statute. With due respect to the holding of the chancellor, for whose opinion we entertain the highest regard, it is manifest that he misconstrued -the' holding of this court on the former appeal as to when effective notice must be given by claimants to secure the benefits of chapter 182 of the Acts of 1899, in cases of default, as here shown. The court there held that, to avail laborers or furnishers of material, notice of claims must be given within thirty days after the time the contract was abandoned by the original contractor. By the terms of the statute (section 4) the completion of the contract is the beginning of the period in which liability may be fixed by notice, and the contract contemplated is necessarily, that of the principal, whose faithful performance of his obligation is under-written, and with whom dealings have been had, and by whom the debts of claimants are owed. The language of the section referred to is plain, unambiguous, and, in our opinion, alone susceptible to the construction heretofore placed thereon; the definition of the word “within” is properly found by the chancellor as denoting “before the expiration of,” “in advance of,” “before,” “not beyond or more than;” but it is to be noted that the period of action is prospective and limited to a time subsequent by the immediate use of the word “after.” The performance of an act “within thirty days after” a given event must take place before the limitation of the time succeeding the event. The pronouncement on the former appeal is the law of the case, and must determine [213]*213the validity of the claims presented.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SH Nashville, LLC v. FWREF Nashville Airport, LLC
Court of Appeals of Tennessee, 2024
In Re Market Center East Retail Property, Inc.
433 B.R. 335 (D. New Mexico, 2010)
Lopez v. Taylor
195 S.W.3d 627 (Court of Appeals of Tennessee, 2005)
Safeco Insurance Co. of America v. City of White House
133 F. Supp. 2d 621 (M.D. Tennessee, 2000)
Guiliano v. Cleo, Inc.
995 S.W.2d 88 (Tennessee Supreme Court, 1999)
Guliano v. Cleo
Tennessee Supreme Court, 1999
Vanderbilt University v. DiNardo
974 F. Supp. 638 (M.D. Tennessee, 1997)
State v. Carter
970 S.W.2d 509 (Court of Criminal Appeals of Tennessee, 1997)
Kimbrough & Co. v. Schmitt
939 S.W.2d 105 (Court of Appeals of Tennessee, 1996)
Kendrick v. Alexander
844 S.W.2d 187 (Court of Appeals of Tennessee, 1992)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
Figlio v. Shelley Ford, Inc.
804 S.W.2d 84 (Court of Appeals of Tennessee, 1990)
Montcastle v. Baird
723 S.W.2d 119 (Court of Appeals of Tennessee, 1986)
V. L. Nicholson Co. v. Transcon Investment & Financial Ltd.
27 Cont. Cas. Fed. 80,250 (Tennessee Supreme Court, 1980)
Travelers Insurance Co. v. Williams
541 S.W.2d 587 (Tennessee Supreme Court, 1976)
US FOR USE AND BENEFIT OF SHANKLE-CLAIRDAY v. Crow
414 F. Supp. 160 (M.D. Tennessee, 1976)
Knoxville Poultry & Egg Co. v. Robinson
477 S.W.2d 515 (Tennessee Supreme Court, 1972)
Harpeth Valley Utilities District of Davidson v. Due
465 S.W.2d 353 (Tennessee Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
146 Tenn. 205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-bristol-v-bostwick-tenn-1921.