Airline Construction, Inc. v. Barr

807 S.W.2d 247, 1990 Tenn. App. LEXIS 847
CourtCourt of Appeals of Tennessee
DecidedDecember 11, 1990
StatusPublished
Cited by158 cases

This text of 807 S.W.2d 247 (Airline Construction, Inc. v. Barr) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Airline Construction, Inc. v. Barr, 807 S.W.2d 247, 1990 Tenn. App. LEXIS 847 (Tenn. Ct. App. 1990).

Opinion

FARMER, Judge.

This is an appeal from a judgment in favor of the defendants/appellees, William J. and Joyce A. Barr (hereinafter “Barr") against plaintiff/appellant, Airline Construction, Inc. (hereinafter “Airline”), for breach of a construction contract.

This litigation concerns construction which occurred on Barr’s real estate (Old English Inn) located in Jackson, Tennessee. Barr engaged the architectural firm of Brannon/Cutliff to add an addition to the Old English Inn. Brannon/Cutliff solicited bids from four construction companies and accepted the proposal from Airline. On August 26, 1986, the parties entered into a construction contract for this addition to the Inn. The construction contract called for 68 new guest rooms (the “rental unit”) and a commercial building consisting of 1490 square feet.

Airline instituted this suit to recover contract balances allegedly owed from Barr in the amount of $118,198. 1 By later amendment to the complaint, Airline also sought to recover additional damages for an increase in the scope of work, extended duration of time, and amounts they were required to expend for an umbrella liability policy.

Barr filed a counterclaim claiming Airline breached the parties’ construction contract. Separate suits were filed by subcontractors (Tri-State Sprinkler Corporation, J & A Mechanical, Inc., and Brock Electric Company) to enforce mechanics’ liens to recover for labor, materials and equipment which they furnished for the project. Airline filed counterclaims against J & A Mechanical and Brock Electric for alleged damages due to delays and deficient and incomplete work. The subcontractors’ cases were consolidated in this action for trial.

A final judgment was entered by the Chancellor on September 22, 1989 in favor of the Barrs and provides in part as follows:

IT IS, THEREFORE, HEREBY ORDERED, ADJUDGED AND DECREED AS FOLLOWS:
(a) The Barrs shall have and recover of Airline and Ohio Casualty the aggregate sum of $309,319.45 determined as follows:
[[Image here]]
*253 (b) The Barrs shall also have and recover of Airline and Ohio Casualty the sum of $75,000.00 for attorneys’ fees.
(c) The Barrs shall also have and recover of Airline only the additional sum of $69,028.40.
As set forth by the appellant, the issues on appeal are: 2
I Whether the trial court erred in awarding the Barrs $210,940.00 for diminution of value of the project.
II Whether the trial court erred in awarding the Barrs lost rental as delay damages.
III Whether the trial court erred in awarding the Barrs liquidated damages.
IV Whether the trial court erred in awarding the Barrs damages for other items for correction, completion or security.
V Whether the trial court erred in awarding the Barrs $75,000.00 for attorney’s fees.
VI Whether the trial court erred in refusing to award Airline $77,186.00 in damages for the extended project duration.
VII Whether the trial court erred in refusing to award Airline the cost of the additional insurance coverage required and the cost of installing the underground sprinkler system.
VIII Whether the trial court erred in finding that Item 8 of Exhibit C to the Contract provided for Room 221 to be the standard for all purposes for the new rooms.
IX Whether the trial court erred in unilaterally and without proof reducing items requested by Airline.
X Whether the trial court erred in refusing to award Airline damages regarding the many consultants on the job.
XIWhether the trial court erred in denying Airline damages for additional amounts expended in performing work beyond the scope of its contract.

The Standard Of Review

The Tennessee Rules of Appellate Procedure Rule 13(d) provides that:

Unless otherwise required by statute, review of findings of fact by the trial court in civil actions shall be de novo upon the record of the trial court, accompanied by a presumption of the correctness of the finding, unless the preponderance of the evidence is otherwise.

Airline contends that this “presumption of correctness” as provided for in T.R.A.P. 13(d) should not accompany the Chancellor’s findings of fact in this case. At the Chancellor’s request the parties in this case submitted proposed findings of fact. The Chancellor adopted verbatim the proposed findings submitted by the defendant as the court’s opinion. The Chancellor stated that Barr’s findings, “best represent the opinion of the Court.”

Airline contends that since the Chancellor only stated that these findings “best represented” his opinion without stating which factual findings actually represented the court’s opinion, the review of this appellate court should be de novo and the customary presumption of correctness as set out hereinabove should be disregarded.

The Tennessee Supreme Court held in Delevan-Delta Corp. v. Roberts, that:

the preparation of findings and conclusions is a high judicial function. We are committed to the requirement that the trial court’s findings and conclusions be its own. However, we are also aware that the thorough preparation of suggested findings and conclusions by able counsel can be of great assistance to the trial court. In an effort to strike a balance between these two considerations, we hold that although it is improper for the trial court to require counsel to prepare findings it is permissible and indeed *254 sometimes desirable for the trial court to permit counsel for any party to submit proposed findings and conclusions. Findings prepared by the trial judge which represent his independent labor are preferable, however we do not disapprove of party-prepared findings.

611 S.W.2d 51, 52-53 (Tenn.1981); Strouth v. State, 755 S.W.2d 819 (Tenn.Cr.App.1986).

Although we do not feel the Chancellor’s procedure should be encouraged, Airline has failed to show us that these party-prepared findings are not in accordance with the Chancellor’s own views. Additionally, if Airline were dissatisfied with these findings, then Airline could have moved the court pursuant to Tennessee Rules of Civil Procedure 52.02 to “amend [its findings] or make additional findings_” The plaintiff made no such motion here. See Delevan-Delta Corp., 611 S.W.2d at 53.

Therefore, we conclude that the adoption of the party-prepared findings is neither reversible error nor justification for disregarding the prescribed “presumption of correctness.”

I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vanessa Faddoul v. Edward James Beyer
Court of Appeals of Tennessee, 2025
Howard Levy v. James Franks
Court of Appeals of Tennessee, 2024
Kyuhwan Hwang v. Sania Holt
Court of Appeals of Tennessee, 2024
Sarah Edge Woodward v. Geoffrey Hamilton Woodward
Court of Appeals of Tennessee, 2023
Bandy v. Roberts
E.D. Tennessee, 2022
Sheryl Haynes v. Terry Haynes
Court of Appeals of Tennessee, 2022
Rex Allen Moore v. Silvia Hill
Court of Appeals of Tennessee, 2020
ECIMOS, LLC v. Carrier Corp.
Sixth Circuit, 2020
Shelby K. Marsh v. Angela D. Lowe
Court of Appeals of Tennessee, 2020
In Re Gracie H. Y.
Court of Appeals of Tennessee, 2020
Mary Beth Harcrow v. Clyde Johnson Harcrow, III
Court of Appeals of Tennessee, 2019
PSC Metals, Inc. v. S. Recycling, LLC
371 F. Supp. 3d 443 (M.D. Tennessee, 2019)
Robert Sawyers, Sr. v. E & R Auto Sales, Inc.
Court of Appeals of Tennessee, 2018
Little Hurricane Properties, LLC v. Ralph Cafaro
Court of Appeals of Tennessee, 2018
Sandra Jo Robbins v. Robert Scholze Robbins
Court of Appeals of Tennessee, 2018
In Re Joshua E.
Court of Appeals of Tennessee, 2018

Cite This Page — Counsel Stack

Bluebook (online)
807 S.W.2d 247, 1990 Tenn. App. LEXIS 847, Counsel Stack Legal Research, https://law.counselstack.com/opinion/airline-construction-inc-v-barr-tennctapp-1990.