E Solutions For Buildings, LLC v. Knestrick Contractor, Inc.

CourtCourt of Appeals of Tennessee
DecidedOctober 30, 2019
DocketM2018-02028-COA-R3-CV
StatusPublished

This text of E Solutions For Buildings, LLC v. Knestrick Contractor, Inc. (E Solutions For Buildings, LLC v. Knestrick Contractor, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E Solutions For Buildings, LLC v. Knestrick Contractor, Inc., (Tenn. Ct. App. 2019).

Opinion

10/30/2019 IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE August 13, 2019 Session

E SOLUTIONS FOR BUILDINGS, LLC v. KNESTRICK CONTRACTOR, INC., ET AL.

Appeal from the Chancery Court for Davidson County No. 15-62-IV Russell T. Perkins, Chancellor ___________________________________

No. M2018-02028-COA-R3-CV ___________________________________

This appeal involves payment disputes arising out of a public construction project. Among other things, the case involves claims made by an equipment supplier against a subcontractor, the project’s general contractor, and the general contractor’s bonding company, and claims made by the same subcontractor against the general contractor. Following a trial, the trial court granted the supplier a judgment against the subcontractor and granted the subcontractor a judgment against the general contractor. The supplier’s claim against the general contractor and its bonding company was denied. The propriety of these rulings and numerous other issues are now before this Court. Having reviewed the record transmitted to us on appeal, we affirm in part, affirm in part as modified, reverse in part, and remand the case for such further proceedings as are necessary and consistent with this Opinion.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed in Part; Modified in Part; Reversed in Part and Remanded

ARNOLD B. GOLDIN, J., delivered the opinion of the Court, in which J. STEVEN STAFFORD, P.J., W.S., and CARMA DENNIS MCGEE, J., joined.

Paul T. Housch, Nashville, Tennessee, for the appellant, Air Comfort Heating and Cooling, LLC.

Timothy H. Nichols, Nashville, Tennessee, for the appellee, E Solutions for Buildings, LLC.

Adam G. LaFevor, Nashville, Tennessee, for the appellees, Knestrick Contractor, Inc., and Berkley Regional Insurance Company. OPINION

BACKGROUND AND PROCEDURAL HISTORY

This case stems from the construction of the Centennial Sportsplex Indoor Fitness Expansion Building by the Metropolitan Government of Nashville and Davidson County (“Metro”). In April 2013, Metro entered into a contract with Knestrick Contractor Inc. (“Knestrick”), pursuant to which Knestrick agreed to construct the Centennial Sportsplex expansion. Under the contract, Knestrick was obligated to accomplish substantial completion of the project by December 2, 2013,1 and if it failed to do so, Metro was entitled to assess “the sum of $1,000.00 for each calendar day of delay until the Project is Substantially Complete.” Knestrick, as principal, and Berkley Regional Insurance Company (“Berkley”), as surety, provided a payment bond in connection with the project.

Following its agreement to serve as a general contractor for the Centennial Sportsplex expansion, Knestrick entered into a subcontract with Air Comfort Heating & Cooling, LLC (“Air Comfort”) with respect to the HVAC work required for the project. This subcontract, which was entered into in July 2013, specifically provided that the work must be performed on or before November 27, 2013. Moreover, similar to the prime contract between Metro and Knestrick, the subcontract involving Air Comfort provided that $1,000.00 in liquidated damages could be assessed “for each day that the work remains uncompleted beyond the specified date period.”

In furtherance of its required work under the subcontract, Air Comfort sought to purchase certain HVAC equipment. To this end, Air Comfort engaged in negotiations with E Solutions for Buildings, LLC (“E Solutions”). E Solutions sent Air Comfort a proposal regarding the needed HVAC equipment on November 11, 2013, and on November 13, 2013, Air Comfort submitted a purchase order for the equipment. The purchase order recited December 13, 2013 as the delivery date, but in the terms and conditions attached to the purchase order, the following was provided: “Shipment dates are estimates only. No valid contract may be made to ship within or at a specified time unless in writing, signed by an authorized signatory of Seller.” There was no liquidated damages provision provided for in the contract between Air Comfort and E Solutions, and the attached terms and conditions further stated that the seller, E Solutions, would “IN NO EVENT . . . BE LIABLE FOR ANY INCIDENTAL, CONSEQUENTIAL, OR PUNITIVE DAMAGES.” Moreover, the terms and conditions provided that E Solutions’ duty to perform was subject to, among other things, the “inability to procure

1 Per an email sent in May 2013, a representative with Metro communicated that a revised construction schedule, establishing a substantial completion date of December 6, 2013, was appropriate based on the time it took Metro to process Knestrick’s final contract. -2- materials from the usual sources of supply” and other causes beyond its “reasonable control.”

When the original deadline for completion of the project proved untenable, Metro and Knestrick entered into an amendment whereby the substantial completion date was extended to January 26, 2014. Although no corresponding amendment was formally made regarding the completion date of Air Comfort’s work under its subcontract with Knestrick, a Knestrick officer testified that an extension was also passed on to subcontractors. Nonetheless, the ultimate delay accompanying the project’s completion has engendered substantial controversy among the parties concerning their respective claims for payment. The project was eventually certified as substantially complete on May 8, 2014.

Litigation subsequently ensued as a result of the construction project. The initiating complaint in this matter, which was filed by E Solutions in the Davidson County Chancery Court (“the trial court”) on January 15, 2015, alleged that E Solutions had not been paid for the materials, equipment, and services it provided on the project. In addition to asserting a bond claim against Knestrick and Berkley, E Solutions sued Air Comfort for breach of contract. Further, E Solutions pled an unjust enrichment/quantum meruit claim against Air Comfort and Knestrick.

On February 20, 2015, Air Comfort filed an answer to E Solutions’ complaint and also asserted a counterclaim and cross-claim. In its defense to E Solutions’ action, Air Comfort asserted, among other things, that E Solutions had materially breached the purchase order with Air Comfort by delaying delivery of the specified HVAC equipment. Air Comfort claimed that it had been damaged by E Solutions’ alleged failure to timely deliver the ordered equipment, and it asserted several theories of liability in its cross- claim against Knestrick. Air Comfort alleged that Knestrick was liable for breach of contract by failing to pay it sums owed under the subcontract, and according to Air Comfort, Knestrick should also be held liable for conversion and in violation of the Prompt Pay Act. A bond claim, a claim for unjust enrichment/quantum meruit, and a claim for contribution were also asserted against Knestrick.2

On February 24, 2015, Knestrick and Berkley filed an answer to E Solutions’ complaint, wherein they prayed that the claims against them be dismissed, and within the same filing, Knestrick separately asserted a cross-claim against Air Comfort. In the cross-claim, Knestrick averred it was entitled to recover $72,000.00 in liquidated damages and alleged that it was entitled to indemnification regarding the action filed against it by E Solutions. Answers to the cross-claims and counterclaim were thereafter filed, and a bench trial was held in the fall of 2016.

2 The bond claim was asserted against Knestrick and Berkley. -3- On March 17, 2017, the trial court entered its “Memorandum and Final Judgment,” wherein it determined that Air Comfort was entitled to a judgment for breach of contract against Knestrick in the amount of $15,000.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
Boyd v. Comdata Network, Inc.
88 S.W.3d 203 (Court of Appeals of Tennessee, 2002)
Scholz v. S.B. International, Inc.
40 S.W.3d 78 (Court of Appeals of Tennessee, 2000)
Stalsworth v. Grummons
36 S.W.3d 832 (Court of Appeals of Tennessee, 2000)
State Ex Rel. Vaughn v. Kaatrude
21 S.W.3d 244 (Court of Appeals of Tennessee, 2000)
Sanders v. Gray
989 S.W.2d 343 (Court of Appeals of Tennessee, 1998)
Story v. Lanier
166 S.W.3d 167 (Court of Appeals of Tennessee, 2004)
Performance Systems, Inc. v. First American National Bank
554 S.W.2d 616 (Tennessee Supreme Court, 1977)
Uhlhorn v. Keltner
723 S.W.2d 131 (Court of Appeals of Tennessee, 1986)
V. L. Nicholson Co. v. Transcon Investment & Financial Ltd.
27 Cont. Cas. Fed. 80,250 (Tennessee Supreme Court, 1980)
Killingsworth v. Ted Russell Ford, Inc.
104 S.W.3d 530 (Court of Appeals of Tennessee, 2003)
Massachusetts Mutual Life Insurance Co. v. Jefferson
104 S.W.3d 13 (Court of Appeals of Tennessee, 2002)
Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
Schoen v. J.C. Bradford & Co.
667 S.W.2d 97 (Court of Appeals of Tennessee, 1984)
Johnson v. Tennessee Farmers Mutual Insurance Co.
556 S.W.2d 750 (Tennessee Supreme Court, 1977)
Owens v. Owens
241 S.W.3d 478 (Court of Appeals of Tennessee, 2007)
Trinity Industries, Inc. v. McKinnon Bridge Co.
77 S.W.3d 159 (Court of Appeals of Tennessee, 2001)
Glassman Const. Co., Inc. v. Maryland City Plaza, Inc.
371 F. Supp. 1154 (D. Maryland, 1974)
Carpenter v. Klepper
205 S.W.3d 474 (Court of Appeals of Tennessee, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
E Solutions For Buildings, LLC v. Knestrick Contractor, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-solutions-for-buildings-llc-v-knestrick-contractor-inc-tennctapp-2019.