Wrinkle v. Larue

9 Tenn. App. 161, 1927 Tenn. App. LEXIS 225
Court of Appeals of Tennessee·Decided September 24, 1927·Published·Cited by 6 cases

Opinion

SNODGRASS, J.

The bill in this cause was filed against the defendants to collect an alleged balance of one thousand twenty-six dollars and eighty-four cents, stated in figures to be $1226.84, for installing a sprinkling system, in a building located at the northeast corner of Gay and Union streets in the City of Knoxville, and bearing No. 411 S. Gay street and being approximately 30x150' feet in dimension, consisting, it was alleged of three stories and a basement. A lien was claimed on the building, but apparently abandoned, as no *162 proof was offered to entitle the party to elaim same as against the owner. Regarding said account the bill represented the matter as follows:

“That the complainant, who operates the Knoxville Sprinkler Company, of which he is sole owner, was engaged by said J. F. Larue & Son to install a sprinkling system in said building, and to furnish pipes and other material requisite and necessary to the installation of said sprinkling system. Under his said contract complainant in.stalled a sprinkling system in said building, in first class shape. Complainant files herewith an itemized account for all the material by him furnished and all of the work by him done under said contract with the defendants J. F. Larue & Son, which account is correct, just and true and owing to the complainant, and amounts to the sum of one thousand twenty-six ($1226.84) dollars and eighty-four cents, all of Avhich is due from the said J. F. Larue & Son and wholly unpaid.”

After setting forth grounds of attachment and describing the property, it sought a decree for the full amount of the indebtedness alleged, and that the property be subjected to its payment.

Answers were filed by all defendants denying lien liability, especially by Larue & Son, a partnership composed of J. F. and C. R. Larue, who while admitting that complainant was employed by them to do certain work, averred that complainant had been fully paid for said work, and it was denied that anything was due him. Regarding complainant’s claim the answer set forth the contentions of defendants Larue & Son, as follows:

“These respondents first employed the complainant to install a sprinkling system upon the mezzanine floor and show windows of said building, and to move a certain tank which was upon the third floor of said building to another location upon the third floor. It is customary in the trade in which complainant and these defendants are engaged for contractors to make an estimate of certain work which they propose to do and to agree that the specified work shall cost no more than the sum mentioned, and that they will endeavor to do the'work and to purchase the material at such cost as will, if possible, save the contractor something; that is, will cost him less than the sum mentioned. So it was that the complainant made an estimate that the work hereinbefore referred to would cost $1065 or less.”

It was, however, averred that thereafter additional work was done by complainant, as follows:

“Minor changes around stairway; installing alarm valves; subbasement work; the installing of a new underground pipe from the street to a certain valve. After this additional work was completed complainant estimated that the cost thereof was $750.

It was thereupon maintained by the answer that the reasonable cost of doing all the work was $1815, whereas it is insisted that complainant was endeavoring to charge respondents therefor the sum of *163 $3223.14. It was averred that respondents had paid complainant the sum of $1999.64 for doing said work and furnishing said material, which is claimed was more than a reasonable charge for said work and more than respondents agreed to pay therefor, and it was accordingly denied that complainant was owed anything for said work. It was claimed that complainant was seeking to charge respondents with an excessive profit, both for labor and material, for which it would be inequitable and unjust to require defendants to pay; and further, that the work and materials had actually cost complainant more than it should 'have cost by reason of the manner in which he did the work, making it necessary for him to tear out and rebuild portions of the same. It was denied that respondents were responsible for additional costs which was put on the work by complainant by reason of his improper manner of doing it.

Taking the attitude of a cross-complainant, it was alleged that, as before stated, cross-complainants had paid original complainant $1999.64, whereas the proper amount that should have been paid him was $1815. It was further alleged that the work done by complainant was not done in a workmanlike manner, in that the tank removed and installed by complainant did not work satisfactorily; that it was defectively installed, as a result of which it would not hold water, and that cross-complainants had gone to considerable expense in having the defects corrected; that already cross-complainants have expended the sum of $58.60, and have incurred other liabilities for Which they had not received bills. Accordingly it was averred that complainant was indebted to cross-complainants in the sum of $100 growing out of the defective installation of the tank, in addition to the sum of $184.60, being the excessive amount paid to complainant, for which judgment was asked.

Free access — add to your briefcase to read the full text and ask questions with AI

Wrinkle v. Larue, 9 Tenn. App. 161, 1927 Tenn. App. LEXIS 225 (Tenn. Ct. App. 1927).

9 Tenn. App. 161 (Wrinkle v. Larue) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Crye-Leike, Inc. v. Sarah A. Carver
415 S.W.3d 808 (Court of Appeals of Tennessee, 2011)
Crye Leike, Inc. v. Richard Scott Over
Court of Appeals of Tennessee, 2004
CPB Management., Inc. v. Everly
939 S.W.2d 78 (Court of Appeals of Tennessee, 1996)
Castelli v. Lien
910 S.W.2d 420 (Court of Appeals of Tennessee, 1995)