Harrison v. Knafle

128 Tenn. 329
CourtTennessee Supreme Court
DecidedSeptember 15, 1913
StatusPublished
Cited by1 cases

This text of 128 Tenn. 329 (Harrison v. Knafle) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harrison v. Knafle, 128 Tenn. 329 (Tenn. 1913).

Opinion

Mr. Justice Lansden

delivered the opinion of the Court.

Harrison is the trustee in bankruptcy of the S. M.. Beaumont Company and filed this bill in the chancery court for the purpose of contesting with the General Fire Extinguisher Company, the Tennessee Mill & Mining Supply Company, and the Alex A. Scott Brick Company the claims'of the latter to a furnisher’s lien in certain fund paid into court by Knafle and wife tO‘ represent the value of two certain houses constructed for them by S. M. Beaumont Company, the complainant’s bankrupt.

The question here is whether the lien claimants are entitled to priority in the fund representing the real estate over the general creditors of the bankrupt.

The Alex A. Scott Brick Company and the Tennessee Mill & Mining Supply Company furnished the ma[331]*331terial used in the construction of the buildings, and the Fire Extinguisher Company installed an automatic fire extinguishing plant in the two buildings. It is not claimed that the Brick Company or the Supply Company have given thirty days’ notice from the last date of materials furnished by them. It is claimed by them, however, that their notice was given within thirty days after the completion of the buildings, and this is likewise the claim of the Fire Extinguisher Company. Whether or not this is true depends upon the effect to be given to certain work done upon the sprinkler system December 26th, 27th, and 28th. The notice of each of the claimants was given within thirty days from those dates, but, if the work done upon the dates referred to does not fall within the contemplation of the building contract, notices are not within time.

This makes it necessary to state the contract between S. M. Beaumont Company, the principal contractor, and Knafle and wife, as the owners for the construction of the two buildings. The buildings .were adjoining each other and were to be built on lots of a frontage of fifty feet each and according to plans and specifications prepared by certain architects and revised and approved by the contractor. These drawings and specifications were made parts of the contract. The original contract provided that “no payment made under this contract except the final payment shall be conclusive evidence of the performance of this contract, either wholly or in. part, and no pay[332]*332ment shall be construed as an acceptance of defective work or improper material.”

Soon after the execution of this contract, and before any material part of the work in the construction of the buildings was done, the parties agreed in parol to enlarge the terms of the original contract by providing that one of the buildings should have an adddi-tional story above the basement, and a complete automatic water sprinkler system should-be put in both buildings, but as one system, by the contractor. The water sprinkler system was to be continuous through both buildings with one pressure tank and one supply pipe for the system. The contractor, after this enlargement of his contract with the owner, entered into a written contract with the Fire Extinguisher Company by which that company agreed to install the sprinkler system in accordance with a contract between the contractor and the owner. This contract provided that the material should be of standard quality and the work done in a thorough and workmanlike manner and in conformity with plans to be approved by the Tennessee Inspection Bure'au. The specifications provided, after designating the number of automatic sprinklers, pipes, fittings, hangers, and the like, that it shall be installed “in a thorough and workmanlike manner, and in strict conformity with the rules and requirements of the within-named insurance interests.”

It is also provided in the contract “that it is the intention of this contract to cover a complete equipment in every respect and install in a manner that will [333]*333meet with the approval of the within-named insurance interests and Beaumont Bros., architects.”

The evidence shows that one of these buildings was completed so that a tenant was placed in it August 1, 1912, and the other was completed and occupied by tenant November 6, 1912. The sprinkler system was installed in the two buildings in such manner that the foreman of the Fire Extinguisher Company believed it to be in compliance with the contract between that company and the principal contractor some time in October, and certainly in November, 1912. The sprinkler system was inspected by an inspector of the Tennessee Inspection Bureau, in October, and water was turned into the system November 6, 1912. Insurance was effected on the buildings November 6th, and the sprinkler system was believed by the insurance agent to be complete, judging alone, however, from its general appearance.

One of the buildings was used as a factory for the manufacture of overalls, pants, and the like, and, in the course of manufacturing these articles, it is necessary to use large tables upon which the garments are cut. These tables were installed after the building was leased to this tenant, and it became necessary to add a number of sprinkler heads under these tables because the tables cut off the protection to the floor which would be afforded by the sprinkler heads located in the ceiling over the tables. This work was done December 26, 27, and 28, 1912, and there is no claim by the lien claimants that this additional work [334]*334would fall within the contract between the parties so as to extend the time of their lien. The claim made by the lienors is that the contract for the construction of the sprinkler system required that the system be approved by the Tennessee Inspection Bureau before it was complete or would be accepted by the owner, and that the system as first installed was inspected by that bureau and disapproved until certain other things were done about it, and that this work was not done until the dates last named. The inspector reported the system equipment to be good in general, the piping well installed, and the heads arranged both staggered and in regular order; that the water supply was good; and that the equipment should control any ordinary fire originating in the building. The inspector also recommended that a sprinkler head located against a steam pipe be moved eight inches, and that a hanger should be placed on the end of the line; that certain crooked sprinklers should be straightened up, and all high heads should be lowered, so that the deflectors would be at least three inches below the bottom of the beams in the basement; that the alarm should be placed in proper working order and plugs inserted in drain valves. He also recommended that an additional head should be placed over the deck of the stairs on the second floor.

Under the authority of Voightman v. Railroad, 123 Tenn., 463, 131 S. W., 982, Ann. Cas., 1912C, 211, if the improvements suggested by the inspector were provided for by the contract for the installation of the [335]*335sprinkler system, and a material part of it, and this work was not properly done by the subcontractor, the building could not be considered as completed until after the improvements were made in December. If, however, it was merely an unimportant or an inconsiderable thing not of the essence of the contract, or. if it was merely to supply defective material or to repair defective work, it would not extend the time for the furnisher’s lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
128 Tenn. 329, Counsel Stack Legal Research, https://law.counselstack.com/opinion/harrison-v-knafle-tenn-1913.