Foster & Creighton Co. v. Wilson Contracting Co.

579 S.W.2d 422, 1978 Tenn. App. LEXIS 339
CourtCourt of Appeals of Tennessee
DecidedOctober 27, 1978
StatusPublished
Cited by34 cases

This text of 579 S.W.2d 422 (Foster & Creighton Co. v. Wilson Contracting Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foster & Creighton Co. v. Wilson Contracting Co., 579 S.W.2d 422, 1978 Tenn. App. LEXIS 339 (Tenn. Ct. App. 1978).

Opinion

OPINION

TODD, Judge.

The plaintiff, Foster & Creighton Company, a subcontractor, sued its general contractors, R. B. Tyler Company, Inc. (now known as Wilson Contracting Company) and Tyler-Hyde Company, a joint venture, for damages representing extra expenses incurred by delay of and interference with plaintiff in completing its subcontract. Defendants filed a third party action against United States Fidelity and Guaranty Company, surety on the contract of another subcontractor, T. F. Scholes, asserting that plaintiff’s damages, if any, were due to the default or delinquency of Scholes and that defendants should have judgment over against United States Fidelity and Guaranty Company for the amount of any judgment recovered by plaintiff against defendants.

The Chancellor awarded plaintiff judgment against defendants in the amount of $26,712.66 and dismissed defendants’ third party action against United States Fidelity and Guaranty Company.

Plaintiff has appealed because of dissatisfaction with the amount of the judgment. Defendants have appealed from the award of judgment to plaintiff and from the dis *424 missal of defendants’ third party action against United States Fidelity and Guaranty Company.

Early in 1957, defendants contracted with the United States Army Corps of Engineers to construct certain improvements at Key Field, Meridian, Mississippi, including resurfacing certain existing runways and grading and paving certain new runways.

On March 11,1957, defendants contracted with T. F. Scholes to perform the necessary earth moving and grading in preparation for the new paving. The contract provided that Scholes should complete the required work by January 2, 1958.

On March 22,1957, defendants contracted with plaintiff to perform all paving, including the resurfacing of existing runways and the paving of new runways by January 2, 1958.

It was possible for plaintiff to perform the resurfacing without waiting for completion of the work of any other subcontractor, but it was impossible for plaintiff to pave any new runway area until it had first been graded by Scholes.

For this reason, the provisions of both sub-contracts requiring complete performance by the same date, January 2, 1958, created a possible situation in which Scholes might complete his grading on time, yet leave no time for plaintiff to complete its paving after grading by Scholes.

During April and May, 1957, representatives of plaintiff and defendants discussed when plaintiff should begin its work which required the “setting up” of a large concrete mixing plant and accessory machinery. Plaintiff desired to delay operations until progress in grading by Scholes was such as to assure completion of grading in time to allow plaintiff to pave without delay. Defendants disagreed and insisted that plaintiff begin operations by July 1. Plaintiff objected to beginning on July 1 because Scholes was having difficulties in grading and his progress did not indicate that he could complete grading to accommodate plaintiff’s paving if begun on July 1.

Defendants’ supervisor, a Mr. White, told plaintiff’s representative that plaintiff must begin repaving existing runways on July 1, and said:

“You can- start on the asphalt (resurfacing) and when you get through with that, we’ll have the rest of the job where you can proceed along. So come on in.”

Early in June, plaintiff began assembling its mixing machinery and, on June 25, 1957, began laying concrete over the existing asphalt runways.

On July 5, 1957, plaintiff notified defendants that it would complete the “asphalt overlay” (resurfacing) within a few days and would not be able to proceed with new paving until some of the grading had been completed. Defendants’ representative assured plaintiff that defendants would “do everything they could to get the grade straightened out so we could pave.”

On July 19, 1957, plaintiff ceased operations because all of the resurfacing had been completed and none of the grading had been completed for new paving. At this time, plaintiff notified defendants that delay in proceeding with paving would result in extra expense of $6,000.00 per week. Defendants again promised to “get the grade straightened out” for paving, and plaintiff retained its equipment and crew on the job-site without doing any further paving from July 19 to August 14, 1957, when personnel and equipment were removed from the job-site.

At the insistence and direction of defendants, plaintiff returned its equipment and crew to the job-site on September 30, 1957, but no grading was complete for paving at that time. Some grading was completed by October 17, 1957, at which time plaintiff resumed paving. Because of requirements of minimum temperature for pouring concrete, plaintiff was unable to pave continuously during the cool fall and winter weather, and special, additional procedures were required to satisfactorily “cure” the concrete.

Concrete was completed by January 1, 1958, and the joints were sealed by February 2, 1958, which completed plaintiff’s con *425 tract: Apparently the delay in sealing joints (after January 2, 1958) was- not deemed material.

Plaintiff’s suit was filed on January 28, 1959, alleging $42,531.57 damages by “breach of express and implied contractual obligations of defendants.”

On February 17, 1959, defendants petitioned the U.S. District Court for removal of the cause to that jurisdiction.

On October 3, 1962, the U.S. District Court remanded the cause to the State (Chancery) Court, where the cause was pending until finally determined January 3, 1978, in the manner previously stated.

Defendants have filed five assignments of error, the first three of which are as follows:

“1. The trial court erred in ruling that Tyler-Hyde acted unreasonably in bringing Foster & Creighton onto the job to begin work by July.
2. The trial court erred in holding that by bringing Foster & Creighton onto the job by July 1, Tyler-Hyde incurred a duty to provide so much site preparation at that time as to enable Foster & Creighton to complete its work and move on without interruption or at its own pace.
3. The trial court erred in ruling that the delay experienced by Foster & Creighton was unreasonable.”

The Chancellor held:

“The contract between Foster and Creighton and Tyler-Hyde does not expressly provide that Foster and Creighton will be allowed to proceed without delay once they have started their work. Foster and Creighton relies on authority which recognizes an implied obligation on the part of the general contractor to facilitate the work required by the sub-contract. Wright & Kremers v. State, 263 N.Y. 615, 189 N.E. 724 (1934), V. C. Edwards & Co. v. Port of Tacoma, 83 Wash.2d 7, 514 P.2d 1381 (1973).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mark Ross v. Orion Financial Group, Inc.
Court of Appeals of Tennessee, 2019
Sparton Technology, Inc. v. Util-Link, LLC
248 F. App'x 684 (Sixth Circuit, 2007)
Scipio v. Sony Music Entertainment, Inc.
173 F. App'x 385 (Sixth Circuit, 2006)
Barnes & Robinson Co. v. OneSource Facility Services, Inc.
195 S.W.3d 637 (Court of Appeals of Tennessee, 2006)
Larry Frankenbach v. Larry Rose
Court of Appeals of Tennessee, 2004
Sharron Johnson, Rodney Lockhart
Court of Appeals of Tennessee, 2003
Edward Risher v. Cherokee Buick-Pontiac-Oldsmobile
Court of Appeals of Tennessee, 2003
Shah v. Racetrac Petro Co
Sixth Circuit, 2003
Leroy McBee v. David Elliott
Court of Appeals of Tennessee, 2003
NBC Capital Markets Group, Inc. v. First Bank
25 F. App'x 363 (Sixth Circuit, 2002)
Gulf Insurance Co. v. Construx, Inc.
Court of Appeals of Tennessee, 2001
Brooks Varner v. David M. Marrs And Latitia M. Marrs
Court of Appeals of Tennessee, 2001
Bank of Gleason v. Weakley Farmers
Court of Appeals of Tennessee, 2000
Calabro v. Calabro
15 S.W.3d 873 (Court of Appeals of Tennessee, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
579 S.W.2d 422, 1978 Tenn. App. LEXIS 339, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foster-creighton-co-v-wilson-contracting-co-tennctapp-1978.