Brooks Varner v. David M. Marrs And Latitia M. Marrs

CourtCourt of Appeals of Tennessee
DecidedJune 18, 2001
Docket2000-01029-COA-R3-CV
StatusPublished

This text of Brooks Varner v. David M. Marrs And Latitia M. Marrs (Brooks Varner v. David M. Marrs And Latitia M. Marrs) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brooks Varner v. David M. Marrs And Latitia M. Marrs, (Tenn. Ct. App. 2001).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT JACKSON JUNE 18, 2001 Session

VARNER CONSTRUCTION COMPANY, INC., and THE ESTATE OF BROOKS VARNER v. DAVID M. MARRS AND LATITIA M. MARRS

An Appeal from the Chancery Court for Shelby County No. 90765-2 Floyd Peete, Chancellor

No. W-2000-01029-COA-R3-CV - Filed April 18, 2002

This is a construction case. In 1981, the defendant owners hired the plaintiff construction company to build a custom home. Over the course of construction, the parties disagreed over many things, and their relationship ended in July or August 1983. The construction company sued the owners, alleging that the owners had not paid the full amount due under the contract. The owners filed a counterclaim, alleging that the construction company owed them for amounts expended in completing the project and for estimated amounts to cure remaining defects. The chancellor referred the case to a special master who, after taking the case under advisement for a lengthy time, issued findings which favored the construction company. The chancellor adopted the findings of the master and awarded the construction company damages plus prejudgment interest. The owners now appeal. We affirm in part, reverse in part and modify.

Tenn. R. App. P. 3 Appeal as of Right; Judgment in the Chancery Court is Affirmed in Part, Reversed in Part and Modified.

HOLLY K. LILLARD, J., delivered the opinion of the court, in which ALAN E. HIGHERS, J., and DAVID R. FARMER , joined.

John J. Heflin, III, and Kenneth P. Jones, Memphis, Tennessee, for the appellants, David M. Marrs and Latitia M. Marrs.

J. Frank Hall, Memphis, Tennessee, for the appellees, Varner Construction Company and the Estate of Brooks Varner.

OPINION This is a construction case. About twenty years ago, defendants David M. Marrs and Latitia Montague Marrs (collectively “Owners”) hired Varner Construction Company (“Contractor”), owned by James Varner, to build a custom-designed, concrete, partially-underground residence at 3191 Airline Road in Eads, Tennessee.1 On November 24, 1981, the parties signed a standard Amercan Institute of Architects Contract (“AIA Contract”), which detailed the specifications of the residence and set the contract price at $328,000. Over the course of construction, approximately twenty-eight change orders were issued relating to a variety of details ranging from ice-makers to spiral ducts. The changes resulted in approximately $30,000 more due under the contract.

All of the work performed on the home took place in 1982 and 1983. It is undisputed that the parties disagreed over many things including, but certainly not limited to, the timeliness and quality of the Contractor’s work, the Owners’ failure to make progress payments to the Contractor in a complete and timely manner, and the Contractor’s failure to pay subcontractors. On approximately July 14, 1983, James Varner and David Marrs engaged in a “fist fight,” apparently stemming from Mr. Marrs’ belief that Mr. Varner had a romantic interest in Mrs. Marrs. Mr. Marrs told Mr. Varner not to come back on the property. Mr. Marrs changed the locks on his residence, and the altercation apparently marked the end of James Varner’s work on the job.

In a letter dated August 22, 1983, the architect on the job, Bill Fuller (“Fuller”),2 wrote a letter to the Contractor detailing twenty-two items on the project that needed to be completed:

On all exterior conc. drill holes missing so as to continue the pattern left by the tie rods. Caulk over the backer rod at the skylite [sic]. Clean the skylite [sic] on the east side between the two plastic panels. install [sic] cover flanges at the solar system conection [sic] of the PVC and metal duct at the roof. Tighten the fire place flue head. Tighten the ‘c’ anchors that hold the solar panels to the frame. Clean the tape marks off the solar panels. Install the Kitch. Exhaust fan on the roof. Clean and polish all door knobs. Touch up paint at the metal hand rails. At the upper gtass [sic] between the M. bedroom and the garden clean the white paint off of the metalso [sic] as to have a straight line. Install the hand sprayer on the sink at the N.W. bathroom. Repair the leaks at the downstaires [sic] mech. room at the mech. system and at the solar system. Anchor and level commode in the S.W. bathroom. At the downstairs mech room use wire nuts at the splices of wires for the intercom system. Install relief valves at the water tanks and water storage tanks.

1 At the time of the contract, the Marrs w ere m arried , but now they are divorced.

2 Fuller was also the Own ers’ neighbor on A irline Road .

-2- repair [sic] the steam shower head leak. Install the icemaker with pump at the bar. Restain the bridge floor. Clean all [the] trash from site. Complete cabinets. Install intercom system in livingroom.

(“August 22 letter”). In the letter, Fuller stated that “[w]hen the . . . list is complete to my satisfaction I shall issue a certificate of substantial completion.” Brooks Varner, James Varner’s father who had joined his son in working on the job, testified that he and his subcontractors went back to the site four or five times to complete the items on the architect’s list. On September 13, 1983, however, Mr. Marrs filed a Notice of Completion in the Shelby County Register’s Office in which he stated that he, rather than the Contractor, substantially completed the work. Whether the Contractor or the Owners should receive credit for completing different parts of the project is the subject of much dispute. Over the course of construction, the Owners paid the Contractor at least $313,868 and paid the Contractor’s subcontractors at least $19,789.

In late August 1983, the owners moved into their new house. On January 10, 1984, the Contractor filed suit against the Owners, claiming that the Owners still owed money under the construction contract. The case was not pursued, however, until 1990, when the Owners answered the complaint and asserted their counterclaim for costs incurred in completing the construction of their residence. In October 1990, the chancellor entered an order referring the case to a master and directing the master to answer twenty-five specific questions pertaining to the parties’ claims. The master held hearings on February 5 and 6, 1991, and continued on July 2, 1991.

For reasons not apparent in the record, the master’s report was not issued until approximately seven years later, on April 24, 1998. The report answered all of the chancellor’s inquiries and ultimately recommended a finding in favor of the Contractor. The Contractor filed a motion to confirm the master’s report, and the Owners filed an objection the report. Following oral argument, on April 3, 2000, the chancellor entered a final judgment adopting all of the master’s conclusions, including the finding that the Owners owed the Contractor $21,838 on the construction contract and $12,000 in prejudgment interest, for a total judgment of $33,838.3 In accordance with the recommendation in the master’s report, the trial court dismissed the Owners’ counterclaims. The Owners now appeal, challenging the chancellor’s order adopting the findings in the master’s report.

We review this case in accordance with the concurrent finding rule. Under that rule, concurrent findings of the master and the chancellor are conclusive and binding on the appellate court, except where the finding under scrutiny is (1) upon an issue not proper to be referred; (2) based on an error of law; (3) based on a mixed question of law and fact; or (4) not supported by any

3 The judgment is in favor of the estate of Brooks Varner, Jame s Varner’s father, because the original plaintiff, Varner Construction Comp any , assign ed its interest in the suit to B rooks V arner, wh o is no w d eceased.

-3- material evidence. See Staggs v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alexander v. Inman
974 S.W.2d 689 (Tennessee Supreme Court, 1998)
Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
Martin H. Aussenberg v. Bruce S. Kramer, David J. Cocke, and Borod and Kramer
944 S.W.2d 367 (Court of Appeals of Tennessee, 1996)
Foster & Creighton Co. v. Wilson Contracting Co.
579 S.W.2d 422 (Court of Appeals of Tennessee, 1978)
Staggs v. Herff Motor Co.
390 S.W.2d 245 (Tennessee Supreme Court, 1965)
Mitchell v. Mitchell
876 S.W.2d 830 (Tennessee Supreme Court, 1994)
Shepherd v. Griffin
929 S.W.2d 336 (Court of Appeals of Tennessee, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Brooks Varner v. David M. Marrs And Latitia M. Marrs, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brooks-varner-v-david-m-marrs-and-latitia-m-marrs-tennctapp-2001.