Ault v. Shepherd

8 La. App. 595, 1928 La. App. LEXIS 194
CourtLouisiana Court of Appeal
DecidedMarch 14, 1928
DocketNo. 3062
StatusPublished
Cited by4 cases

This text of 8 La. App. 595 (Ault v. Shepherd) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ault v. Shepherd, 8 La. App. 595, 1928 La. App. LEXIS 194 (La. Ct. App. 1928).

Opinion

ODOM, J.

On May 28, 1923, the plaintiffs, Ault & Burden, entered into a contract to build the Washington Hotel in the City of Shreveport.

On January 25, 1924, said Ault & Burden entered into a contract with the defendants, J. C. Shepherd & Company, to do the lathing and plastering work for said structure at a stipulated price.

Shepherd & Company furnished bond in the sum of $40,000.00 to secure the performance of the contract.

During the progress of the work, Shepherd & Company became financially embarrassed and were about to default on their contract, whereupon a separate or supplemental written agreement was entered into between Ault & Burden, the general contractors, and Shepherd & Company, the sub-contractors, with the concurrence of Shepherd & Company’s bondsman to the effect that Ault & Burden were to advance to Shepherd & Company all such sums of money as might be necessary to take care of Shepherd & Company’s pay-rolls until the work under the sub-contract was completed and to charge all such sums to the sub-contractor, and if the sums so advanced exceeded the amount due the sub-contractors under the contract, such excess payments should be refunded to Ault & Burden by the sub-contractors or by their bondsman.

[596]*596Ault & Burden bring this suit against Shepherd & Company and the Standard Accident & Insurance Company, Shepherd & Company’s bondsman, for $1,915.71, which they allege, they advanced to Shepherd & Company in excess of the amount due under the contract.

Plaintiffs also alleged that the subcontractors, Shepherd & Company, had caused to be inscribed in the mortgage records of Caddo Parish a statement showing that plaintiffs are indebted to them in the sum of $6,165.47 coupled with an affidavit claiming a lien on the Washington Hotel for said amount, which statement and affidavit are alleged to be untrue, and they asked that said inscription be can-celled and erased from the records.

Defendants, in answer, ■ denied any indebtedness to plaintiffs and alleged that plaintiffs are indebted unto them in the sum of $6,165.47

“for extras done at the special instance and request of said Ault & Burden, as shown by statement hereto attached and made part hereof.”

There was judgment in the lower court in favor of plaintiffs for the full amount sued for, ordering the cancellation of the inscription of the • lien filed by defendants, and rejecting defendants’ reconventional 'demand.

Defendants appealed.

OPINION

There is but little controversy over plaintiff’s claim against defendants for $1,915.71 for • advances made in excess of the contract price for the work.

Attached to plaintiffs’ petition is an itemized statement dated .January 1,, 1925, .addressed ,to J. C. Shepherd & Company for “materials and labor furnished your men, Washington Hotel job,” the items thereon totaling $650.28. All other excess charges are for money advanced and they are not disputed. But defendants contend that they should not be required to reimburse the $650.28 shown on this separate statement.

As a witness in his own behalf, Mr. Shepherd did not dispute any of the items on this separate satement, except one for $29.00 for “setting screeds” and those for “hoist.” He testified that he knew nothing of the item for $29.00, and we note that when Mr. Copeman, plaintiffs’ foreman, was questioned about this item he was unable to explain it. There is no proof of that item, and it must be rejected.

The charges for “hoist” and current to operate the same amount to $324.00. These charges defendants say they should not be required to. pay.

The contract between plaintiffs and defendants provides that the — ■

“contractors (Ault & Burden) is to furnish the subcontractors (Shepherd & Com•pany) with one of the elevator shafts for use in installing sub-contractors’ hoist for use in hoisting his materials.”

At the time defendants began work, there was installed in the elevator shaft which they desired to use, an electric hoist belonging to plaintiffs. Mr. Copeman, plaintiffs’- foreman, testified that at that time defendants ' did not have a hoist available for installation in the shaft and as the hoist was necessary for defendants to carry on their work, it was agreed that defendants should use plaintiffs’ hoist until defendants’ could be installed' in the shaft.

Mr. Copeman testified, and his testimony is not disputed, that defendants did use plaintiffs’ hoist from about March 9th to the latter part of July. Plaintiffs made no charge for the use of the hoist but did [597]*597charge to defendants the bills which they paid for the electricity used in operating it, and also charged amounts paid the engineer for overtime in operating the hoist. It' seems that defendants used the hoist after five o’clock.

Mr. Copeman says that Shepherd agreed to pay these charges, but Shepherd denies that. Copeman says that during the five months in which the hoist was being used, he rendered to Shepherd weekly statements showing these charges, and that Shepherd made no objection to them.

Plaintiffs were under no obligation to furnish defendants a hoist or to pay the expense of operating it, and there is no testimony that Mr. Copeman or any one else agreed to pay the expense of operating it without charge.

Shepherd knew that it took electricity to operate the hoist, for which some one had to pay, and he knew the engineer had to be paid for his overtime work. He accepted and used the hoist, thereby agreeing, tacitly at least, to pay the expense, and this fact, coupled with Copeman’s testimony that Shepherd agreed to pay the bills and that regular statements of the charges were rendered to him and that he made no objection thereto, we think sufficiently prove the "charges.

Our conclusion, therefore, is, that plainIffs’ claim, except the item of $29.00 for “letting screeds” is made out.

The Standard Accident and Insurance Coipany, defendants’ surety on the bond, denes liability for the charges against defeidants for “materials and labor furnishd” amounting to $650.28.

Tht original bond and contract of suretyship is dated January 29, 1924, is in favor f Ault & Burden, and is conditioned upon the faithful performance of the contract by the sub-contractors.

Thereafter, on July 1, 1924, a supplemental written contract was entered into between Ault & Burden, on the one side, and the sub-contractors and the bonding company, on the other, in which it is recited, among other things, that said Shepherd, the sub-contractor, had defaulted on his contract and that—

“the same can be declared terminated by the contractor, and the said Shepherd, furthermore, is in need of advances of cash in order to enable him to comply with his contract if such forfeiture be not declared.”

Then follows a stipulation that if Shepherd will continue to devote his time to the completion of the work, employing plasterers at the usual wage scale, Ault & Burden

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roff v. Southern Construction Corporation
163 So. 2d 112 (Louisiana Court of Appeal, 1964)
Meaux v. Southern Construction Corporation
159 So. 2d 156 (Louisiana Court of Appeal, 1963)
Womack v. Lafayette Furniture Co.
50 So. 2d 843 (Louisiana Court of Appeal, 1951)
Wilson v. T. L. James & Co.
122 So. 137 (Louisiana Court of Appeal, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
8 La. App. 595, 1928 La. App. LEXIS 194, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ault-v-shepherd-lactapp-1928.