O'Leary v. Board of Port Com'rs for Port of New Orleans

91 So. 139, 150 La. 649, 1922 La. LEXIS 2609
CourtSupreme Court of Louisiana
DecidedJanuary 2, 1922
DocketNo. 24559
StatusPublished
Cited by15 cases

This text of 91 So. 139 (O'Leary v. Board of Port Com'rs for Port of New Orleans) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Leary v. Board of Port Com'rs for Port of New Orleans, 91 So. 139, 150 La. 649, 1922 La. LEXIS 2609 (La. 1922).

Opinions

"SOMMERVILLE, J.

On August 25, 1915, plaintiff entered into a contract with the defendant for the construction of pile foundation for workhouse annex, drier house, boiler and transformer house, and connections for the public grain elevator on the banks of the Mississippi river in the city of New Orleans. The contract was completed and the money stipulated for was paid, together with certain extras which were allowed by the plaintiff and allowed by the defendant. This suit is for $13,054.80 for expenses attending the driving of certain piles, which expense [651]*651plaintiff alleges was not in contemplation at the time of making the contract. The board of commissioners answered that it had fully paid plaintiff for all the work mentioned and contemplated in the contract, and that it did not owe for the expenses said to have been incurred by plaintiff in doing a part of the work. That is, in driving a certain group of piles through a dense earth formation under the waters of the Mississippi river, which the parties did not know was in existence.

There was judgment for plaintiff as prayed lor, and defendant has appealed.

[1] The contract and specifications are in the transcript in the original; and they contain the law of the parties thereto. The claim of the plaintiff is not for extras on the contract, but for expenses incurred in doing the work contemplated by the contract. There were no extra piles driven, and little or no extra work done.

Plaintiff in his petition alleges that in driving the piling contracted for he struck such a hard stratum in the soil that, according to the ordinary terms and constructions of the contract and usual conditions in engineering, the piles when they encountered said stratum should have been cut off. But, that contrary to such rules, the engineers arbitrarily forced plaintiff to drive said piles to a depth of 40 to 55 feet, the average depth mentioned in the contract, irrespective of the resistance encountered; that he was required to obtain several steel points to penetrate this obstruction; and “that after conference between the engineers and the contractor the engineers ordered the contractor to jet the piles, jetting not being contemplated in the contract or required of the contractor. He agreed to jet this work only after it was understood that he would be compensated therefor.”

In the first part of the contract it is provided :

“That for and in consideration of the payments hereinafter stipulated to be made to him by the port commission, the contractor and his surety hereby agree and bind themselves in solido at their own proper cost to furnish all materials, apparatus, falsework, machinery, tools, supplies, transportation and labor necessary and requisite for and to perform, construct, complete and deliver in a substantial and workmanlike manner, to the entire satisfaction of Ford, Bacon, and Davis, engineers of the said port commissioners and hereinafter called the ‘engineers,’ all of the work embraced and described in the plans and specifications of said port commission for the construction of pile foundation for workhouse annex, drier house, boiler and transformer house and connections, in strict accordance with the said plans and specifications and proposal, which are each and every one of them signed by both of the contracting parties to identify them with this contract and as part thereof, as follows, to wit,” etc.

It was further agreed that:

“The work to be done under this contract shall be executed under the immediate direction and supervision of Ford, Bacon & Davis, engineers of the port commission, or their representatives, and the said engineers shall be the judges of, and shall decide all questions or disputes that may arise under this contract with regard to the interpretation of the plans and specifications, quality of material or workmanship or any other dispute or question arising thereunder, and their decision shall be binding upon the parties hereto, except in cases of protest by the contractor, m which event the port commission shall be appealed to and the decision of the said board on the objection or protest of the contractor shall be deemed binding and conclusive on said contractor.

“The engineers acting for the port commission reserve the right to make such alterations or modifications in the said plans or specifications, or both, in accordance with paragraph 39 of said specifications as they may deem advisable, but the contractor shall not proceed with these changes without a written order from the engineers approved by the port commission; this order shall stipulate the work to be done under the changed, modified, or altered conditions, the difference in-time allowance and the difference in price, whether in favor of or against the contractor. The contractor shall, under the circumstances, have the right to increase, diminish or alter the work to be done under this contract; nor shall [653]*653any claim for extra work be allowed or' entertained, either in time allowance or in cost, unless the increase, decrease or extra work shall have been ordered in the same manner as above required for changes, modifications, etc., in the plans and specifications.”

Plaintiff did not obtain the order from the engineers, or the approval from the board to incur the expense which he is here claiming. Such order and approval should have been had in writing upon which to found the claim made in this suit. Neither does he allege the refusal of the engineers to give such order, nor any fraud as to his rights, or such gross mistake as could amount to fraud.

In 17 Am. & Eng. Annotated Cases, p. 81, it is said:

“The well-settled rule is that, where a building contract provides that no charge shall be made for extra work unless a written order for the same shall have been' given to the contractor by the architect, or by the person standing in the place of the architect, or supervising engineer, no recovery can be had without such a compliance with such provision,” with cases cited to that effect.

And in Selby v. City of New Orleans, 119 La. 900, 44 South. 722, it is said:

“Moreover, the agreement between the city of New Orleans and Noullet & Co. was that no claim would be made for extra work unless it was ordered in writing by the city engineer.

“It is certainly out of the ordinary that so large an amount should be charged for extra work in view of the contract which contains such a provision. Moreover, the testimony does not sustain the item with sufficient certainty and to the extent required.

“Plaintiffs are not in a position to claim that they were ignorant of the terms of this contract.”

Plaintiffs, having agreed to furnish all materials, apparatus, falsework, machinery, tools, supplies, transportation and labor necessary and requisite to perform, construct, complete and deliver the work mentioned in the contract “at their own proper costs,” will be held to a compliance therewith.

And, in another provision of the contract, the contractor had to make all necessary arrangements for the use of any and all designs, methods, 'processes, apparatus, or materials shown or required in the plans and specifications and contract, and shall make all payments required as license, royalty, etc., on such -account.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

T L James & Co Inc v. Traylor Bros Inc
294 F.3d 743 (Fifth Circuit, 2002)
Pittman Construction Co. v. City of New Orleans
178 So. 2d 312 (Louisiana Court of Appeal, 1965)
Pittman Construction Co. v. Board of Levee Commissioners
169 So. 2d 192 (Louisiana Court of Appeal, 1964)
Meaux v. Southern Construction Corporation
159 So. 2d 156 (Louisiana Court of Appeal, 1963)
Brasher v. City of Alexandria
41 So. 2d 819 (Supreme Court of Louisiana, 1949)
State Highway Commission v. Green-Boots Const. Co.
1947 OK 221 (Supreme Court of Oklahoma, 1947)
Kansas City Bridge Co. v. State
250 N.W. 343 (South Dakota Supreme Court, 1933)
Jung v. Gwin
147 So. 47 (Supreme Court of Louisiana, 1933)
Fossier v. Knight Motors Co.
127 So. 87 (Louisiana Court of Appeal, 1930)
Ault v. Shepherd
8 La. App. 595 (Louisiana Court of Appeal, 1928)
Harvey v. Mouncou
3 La. App. 231 (Louisiana Court of Appeal, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
91 So. 139, 150 La. 649, 1922 La. LEXIS 2609, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oleary-v-board-of-port-comrs-for-port-of-new-orleans-la-1922.