Pittman Construction Co. v. City of New Orleans

178 So. 2d 312
CourtLouisiana Court of Appeal
DecidedNovember 8, 1965
Docket1887
StatusPublished
Cited by36 cases

This text of 178 So. 2d 312 (Pittman Construction Co. v. City of New Orleans) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittman Construction Co. v. City of New Orleans, 178 So. 2d 312 (La. Ct. App. 1965).

Opinion

178 So.2d 312 (1965)

PITTMAN CONSTRUCTION COMPANY, Inc.
v.
The CITY OF NEW ORLEANS.

No. 1887.

Court of Appeal of Louisiana, Fourth Circuit.

July 15, 1965.
Rehearing Denied September 27, 1965.
Writ Refused November 8, 1965.

*313 Gerald J. Gallinghouse, J. Richard Reuter, Jr., and Arthur C. Reuter, New Orleans, for plaintiff-appellee-appellant.

Alvin J. Liska and Joseph H. Hurndon, New Orleans, for defendant-appellant.

Deutsch, Kerrigan & Stiles, A. Morgan Brian, Jr., New Orleans, for David W. Godat, third-party defendant-appellant.

Albert J. Flettrich, New Orleans, for S. K. Whitty & Co., Inc., intervenor-appellee.

Before REGAN, YARRUT, and BARNETTE, JJ.

YARRUT, Judge.

Pittman Construction Company, Inc. (Pittman), as the general contractor, sued the City of New Orleans (City), as the owner, to recover $86,980.67, plus 5% interest from judicial demand, and all court costs, as the balance due for the erection of a project, known as the "Algiers Refuse Incinerator," located on a site near the intersection of Hendee and Anson Streets, near the approaches of the Mississippi River Bridge, in the Fifth Municipal District (Algiers) of New Orleans. The structure was to be a 200-ton daily capacity incinerator of the pit-and-crane type, complete with building, crane, ash and air handling facilities, furnaces, grates, a truck maintenance and storage facility, and certain sitework-paving, grading and drainage. The whole project was to cost $704,213.00 and Pittman was awarded the contract after competitive bidding for the major structural part at a net base price of $444,200.00.

Pittman alleges it completed all work required by the contract in strict accordance with plans and specifications furnished by the City, under the constant on-site supervision and approval of the City's consulting engineers, and is entitled to recover all contract funds due it by the City; plus $29,999.90 as the fair value of two items of extra work: (1) $26,576.94 for remedial pile work; and (2) $3,422.96 for installation of concrete gutter in maintenance garage; that the extra piling work was rendered necessary by serious latent unstable soil conditions encountered during construction that rendered the City's plans and specifications defective and inadequate; all work having been done under protest in compliance with the City's revised plans and specifications.

The City answered denying any indebtedness to Pittman, charging that Pittman failed to perform the work in accordance with the contract; then reconvened against Pittman for $33,783.81 as the cost of "remedial work," removal of floating concrete slabs and the construction of new slabs upon structural supports. The City then alternatively filed a third-party action against David W. Godat d/b/a David W. Godat & Associates (Godat), the City's engineers and supervisors, to recover the same claims for "remedial work" sought by *314 Pittman, together with any amount awarded Pittman against the City.

A petition of intervention was filed by S. K. Whitty & Co., Pittman's pile-driving subcontractor, to recover $16,666.83 from Pittman and the City. The City denied any liability to Whitty, and Pittman answered that their subcontract bound Whitty to them, as it is bound to the City under the prime contract.

The district judge, after a trial lasting five days, entailing more than 1000 pages of testimony, both expert and lay, and numerous documents consisting of the construction contract, the plans and specifications, and considerable correspondence between all parties, rendered judgment in favor of Pittman and against the City for $85,763.56, consisting of $55,763.66 earned contract funds retained by the City; $29,999.90 additional for extra work composed of $26,576.94 for remedial pile work and $3,422.96 for installing concrete gutter, plus 5% interest from January 25, 1963 (date of judicial demand) until paid, and all costs. Pittman's other claims have been abandoned.

Intervenor Whitty was awarded judgment against Pittman for $16,666.83. While the City's reconventional demand for $33,783.81 against Pittman was dismissed, the City obtained judgment against Godat in its third-party action for $60,360.75, $26,576.94 of which is for remedial pile work, and $33,783.81 for remedial concrete slab work.

The City appealed from the judgment in favor of Pittman. Godat, third-party Defendant, appealed from the judgment in favor of the City; and Pittman from the judgment in favor of Whitty.

At the outset we must conclude that the site for construction of the incinerator was selected by the City's representatives; that, after repeated conferences, the entire project was designed by Godat, the City's consulting engineers who prepared the plans and specifications in cooperation with the City's own engineer; that the construction work was performed under, and subject to, the continuous and constant supervision and direction of Godat; that the contract required Pittman to perform the work in strict accordance with the plans and specifications, which prescribed in minute detail the work to be done; the sequence of operations; and the methods, ways and means by which the work was to be accomplished; that immediately on receipt from the City's engineers of a notice to proceed, Pittman commenced the construction, and proceeded promptly with the execution of the work; that, during an early stage of construction, serious latent and unstable subsurface soil conditions were encountered, which Pittman immediately called to the attention of the City's representatives and Godat, who had stationed a resident engineer on the project for continuous supervision of Pittman's performance.

Godat finally approved and accepted the work as having been done in strict accordance with the plans and specifications, and recommended that the City make final payment to Pittman.

As his reasons for judgment in favor of Pittman the district court concluded that Pittman had performed the entire project in strict accordance with the plans and specifications; that Pittman had encountered serious latent unstable soil conditions during the construction; that the design of the project was defective, and the plans and specifications were faulty and insufficient with respect to piling, and floating concrete slabs; and the floating concrete slabs and resulting damage were due to the insufficiency of the City's plans and specifications; and LSA-R.S. 9:2771, as amended by Act 84 of 1960, relieved Pittman of liability, which statute reads:

"No contractor shall be liable for destruction or deterioration of or defects in any work constructed, or under construction, by him if he constructed, or is constructing, the work according to plans or specifications furnished to him which he did not make or cause to be made and if the destruction, *315 deterioration or defect was due to any fault or insufficiency of the plans or specifications. This provision shall apply regardless of whether the destruction, deterioration or defect occurs or becomes evident prior to or after delivery of the work to the owner or prior to or after acceptance of the work by the owner. The provisions of this Section shall not be subject to waiver by the contractor." Acts 1958, No. 183, § 1, as amended Acts 1960, No. 84, § 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lingoni v. Hibernia National Bank
33 So. 3d 372 (Louisiana Court of Appeal, 2010)
Borne v. King
799 So. 2d 853 (Louisiana Court of Appeal, 2001)
Dumas and Associates, Inc. v. Lewis Enterprises Inc.
704 So. 2d 433 (Louisiana Court of Appeal, 1997)
Colbert v. BF Carvin Const. Co.
600 So. 2d 719 (Louisiana Court of Appeal, 1992)
McKeen Homeowners Ass'n, Inc. v. Oliver
586 So. 2d 679 (Louisiana Court of Appeal, 1991)
Conmaco, Inc. v. Southern Ocean Corp.
581 So. 2d 365 (Louisiana Court of Appeal, 1991)
Carter v. Deitz
556 So. 2d 842 (Louisiana Court of Appeal, 1990)
Morrison v. JA Jones Const. Co., Inc.
537 So. 2d 360 (Louisiana Court of Appeal, 1988)
MJ Womack, Inc. v. State House of Rep.
509 So. 2d 62 (Louisiana Court of Appeal, 1987)
Sams v. Kendall Const. Co.
499 So. 2d 370 (Louisiana Court of Appeal, 1986)
Bowman v. Coursey
433 So. 2d 251 (Louisiana Court of Appeal, 1983)
Hogan Exploration v. Monroe Engineer. Assoc.
430 So. 2d 696 (Louisiana Court of Appeal, 1983)
City of Covington v. Heard
428 So. 2d 1132 (Louisiana Court of Appeal, 1983)
Wetzka v. Big Three Industries, Inc.
409 So. 2d 393 (Louisiana Court of Appeal, 1982)
Segall Co., Inc. v. WD Glassell Co.
401 So. 2d 483 (Louisiana Court of Appeal, 1981)
Am. Fid. Fire Ins. Co. v. Pavia-Byrne Engineering Corp.
393 So. 2d 830 (Louisiana Court of Appeal, 1981)
Vitenas v. Centanni
381 So. 2d 531 (Louisiana Court of Appeal, 1980)
Gretna Glass & Mirror Works, Inc. v. Crescent City Baptist Church
357 So. 2d 836 (Louisiana Court of Appeal, 1978)
Lawyers Title Ins. Co. v. Carey Hodges & Associates, Inc.
358 So. 2d 964 (Louisiana Court of Appeal, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
178 So. 2d 312, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittman-construction-co-v-city-of-new-orleans-lactapp-1965.