Merchants National Bank & Trust Co. Of Indianapolis v. Smith, Hinchman & Grylls Associates, Inc. And the Mathes Group

876 F.2d 1202, 1989 U.S. App. LEXIS 9743, 1989 WL 65615
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 7, 1989
Docket88-3716
StatusPublished
Cited by3 cases

This text of 876 F.2d 1202 (Merchants National Bank & Trust Co. Of Indianapolis v. Smith, Hinchman & Grylls Associates, Inc. And the Mathes Group) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merchants National Bank & Trust Co. Of Indianapolis v. Smith, Hinchman & Grylls Associates, Inc. And the Mathes Group, 876 F.2d 1202, 1989 U.S. App. LEXIS 9743, 1989 WL 65615 (5th Cir. 1989).

Opinion

WISDOM, Circuit Judge:

In this case we decide that the Louisiana one-year prescriptive period for torts governs this third party action against architects for economic loss.

I

The plaintiff, as assignee of Robbins Electric Co., Inc., seeks recovery against the defendants, architects, for Robbins’s economic losses incurred as a result of defects and deficiencies in the defendants’ architectural plans and specifications for the construction of the Fort Polk Army Hospital.

The defendants, Smith, Hinchman & Grylls Associates, Inc. and The Mathes Group, as joint venturers, provided the designs and plans for the hospital under their contract with the United States Army Corps of Engineers (Corps). The Corps awarded the construction contract to Alger-non Blair, Inc. (Algernon) on September 25, 1978. On December 7,1979, Algernon subcontracted the electrical work for the project to Robbins. Under the contract Robbins was to receive $5,233,339.

After the construction contracts were entered into, the architects made numerous changes and corrections in their drawings and specifications. By October 1979 Robbins knew that 800 of the drawings had been revised and as a result its job site personnel and facilities had to be increased substantially. During 1980 and 1981, Robbins made several requests to Algernon *1204 and the Corps for additional compensation for cost overruns caused by the changes in the plans. On October 22, 1981, Algernon and the Corps agreed to increase the amount of Robbins’s subcontract by $651,-867.

The Corps accepted the hospital on August 17, 1983. It is undisputed that Robbins knew before the hospital was completed, and certainly more than one year before this suit was filed on August 21, 1987 that it had not been compensated for substantial economic losses it suffered as a result of the extensive revisions made in the architectural plans.

II

The plaintiff sued the architects seeking recovery on tort and contract grounds. The district court initially granted the defendants’ motion for summary judgment on the contractual claim because of the lack of privity between Robbins and the architects. With regard to the plaintiff’s delictual claim, however, the court noted that because of the overlap in coverage of Louisiana Civil Code Article 3492’s one-year prescriptive period for tort suits and article 3500’s ten-year period for certain suits against architects and contractors, it was appropriate to resolve doubt in favor of the plaintiff and apply the ten-year period of article 3500. On the defendants’ motion to reconsider, after carefully analyzing the scope of article 3500 in the light of related article 2762, the court concluded that the one-year period for torts of article 3492, not the ten-year period of article 3500, is applicable to the plaintiff’s claim for economic loss. The district court therefore granted summary judgment in the defendants' favor on the tort claim as well.

Because the applicability of prescriptive periods is a question of law, we make an independent review of the law. That the district court’s conclusion on rehearing differed from its initial determination is illustrative of the lack of clarity in the codal provisions. We are mindful, however, that in reconsidering the prescription issue the court was aided by the defendants’ briefing on the applicability of article 3492, a question not addressed in their memorandum in support of their summary judgment motion. 1 To resolve the prescription question, we consider the applicability of the general one-year period for torts of article 3492, the ten-year period of article 3499 for personal actions, and the ten-year period of article 3500 and La.Rev.Stat.Ann. § 9:2772 for certain tort suits against contractors and architects.

Ill

To determine which prescriptive period governs the plaintiff’s delictual claim we first look to the type of injury sustained and the nature of the duty breached. It is undisputed that Robbins, the electrical subcontractor, incurred economic loss in the form of substantial job cost overruns as a result of the numerous alterations made to the defendants’ architectural drawings and specifications. According to the plaintiff, the revisions were necessary to correct defects and deficiencies in the plans and specifications. Courts have recognized that under Louisiana law a contractor or subcontractor may bring an action in tort for economic loss caused by an architect’s failure to provide adequate plans or specifications. 2

There are no Louisiana appellate or supreme court decisions addressing the question of the proper prescriptive period governing a tort action against an architect for economic loss. Several courts have considered, however, whether the one-year period for torts of article 3492 or the ten-year period for personal actions of article 3499 governs tort suits against physicians and *1205 attorneys. In Sciacca v. Polizzi, 3 the Louisiana Supreme Court held that an action for medical malpractice sounds in tort and is governed by the one-year tort prescriptive period of Civil Code article 3492 unless the physician has contracted with the patient for a specific cure or result. Courts also agree that under Louisiana law, unless an attorney warrants a specific result and fails to achieve it or agrees to do certain work and fails to perform it, a client’s action for legal malpractice sounds in tort and is subject to the one-year prescriptive period for tort actions of article 3492. 4

This Court in McLaughlin v. Herman & Herman, 5 addressed the attorney malpractice prescription issue at a time when there was still some doubt about the applicable period. 6 In McLaughlin we noted that in determining that the one-year period of article 3492 applies to legal and medical malpractice claims, the Louisiana courts relied on this Court’s explanation in Kozan v. Comstock 7 that the standard of care a physician or attorney owes to his patient or client is one imposed by law, regardless of any contract. 8 Only if there is a contractual arrangement would the ten-year period of article 3499 apply.

The nature of an architect’s duty to a contractor with whom he is not in privity was addressed recently by a Louisiana appellate court in Milton J. Womack, Inc. v. House of Representatives of Louisiana. 9 In Womack a contractor sued an architectural firm seeking to recover an amount equal to the “early completion incentive payment” the contractor would have received if the project had been timely completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landis & James Construction Co. v. Gee Cee Corp.
669 So. 2d 1265 (Louisiana Court of Appeal, 1996)
Preston Glove Co. v. Bentsen
845 F. Supp. 401 (N.D. Mississippi, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
876 F.2d 1202, 1989 U.S. App. LEXIS 9743, 1989 WL 65615, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merchants-national-bank-trust-co-of-indianapolis-v-smith-hinchman-ca5-1989.