Calandro Development, Inc. v. RM Butler Contr., Inc.

249 So. 2d 254
CourtLouisiana Court of Appeal
DecidedMay 31, 1971
Docket8360
StatusPublished
Cited by26 cases

This text of 249 So. 2d 254 (Calandro Development, Inc. v. RM Butler Contr., Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Calandro Development, Inc. v. RM Butler Contr., Inc., 249 So. 2d 254 (La. Ct. App. 1971).

Opinion

249 So.2d 254 (1971)

CALANDRO DEVELOPMENT, INC.
v.
R. M. BUTLER CONTRACTORS, INC. and United Bonding Insurance Company.

No. 8360.

Court of Appeal of Louisiana, First Circuit.

May 31, 1971.

*255 Leon Gary, Jr., of Ellison & Gary, Baton Rouge, for appellant.

Marcel Livaudais, Jr., of Loeb & Livaudais, New Orleans, A. Leon Hebert of Hebert, Moss & Graphia, Baton Rouge, Drury, Lozes & Curry, New Orleans, for appellee.

Before LANDRY, ELLIS and BLANCHE, JJ.

LANDRY, Judge.

The principal and res nova question involved in this appeal is whether the surety on a defaulting contractor's performance bond has a cause of action in tort against the engineer who designed and supervised construction of a subdivision for a third party owner in whose favor the performance bond was given. We find that such a cause of action does exist, but that the claim asserted herein must be denied for reasons hereinafter set forth. Incidental to this main issue is the question whether the owner-obligee in a construction contract performance bond may sue the surety thereon for such items as added interest cost incurred on a construction mortgage loan attributable to the fault of the defaulting contractor. Under the circumstances of this case, we deny recovery for such items.

This litigation evolved as a concursus proceeding invoked by Calandro Development, Inc. (Owner), in which Owner impleaded *256 R. M. Butler Contractors, Inc. (Contractor), and also impleaded several lienors of the construction project together with United Bonding Insurance Company (United), the surety on Contractor's performance bond.

Pursuant to an oral contract of employment, Owner engaged Boudreaux Fergus Consulting Engineers (Engineer) to design and supervise construction of a residential subdivision known as Acadian Gardens Subdivision (Acadian), situated in Donaldsonville, Ascension Parish. The construction site was surveyed, a hospital site of undetermined acreage was carved therefrom, and Engineer prepared all plans and specifications for the necessary sewerage lines, street paving, sidewalks, curbing and drainage facilities. Contractor, the sole bidder on the project at a price of $79,000.00, was awarded the contract with the approval of the Engineer. The contract specifies that Contractor shall post a performance bond, with acceptable surety, in the contract sum. The contract also contains the following provisions:

"Upon failure on the part of the contractor to forthwith comply with any order of the engineer made under the provisions of this article, the engineer shall have the authority to cause defective work to be remedied or removed and replaced an unauthorized work to be removed and such costs to be deducted from any monies due to or to become due to the contractor, or the engineer if he so elects may withhold any money due or becoming due to the contractor until such time as the work is satisfactorily corrected.
"Concrete shall be placed only on a subgrade prepared and maintained as specified and only when the subgrade has been approved by the Engineer.
"No work shall be done, no materials used, without suitable supervision or inspection by the Engineer or his representative."

Work on the project commenced on or about August 1, 1966, and continued until approximately October 15, 1966. Subsequently, on February 1, 1967, Contractor was formally placed in default after having received payments aggregating $64,188.69 for work performed. Owner then deposited the remaining $14,811.31 due under the contract into the registry of the trial court and invoked this concursus proceeding.

The trial court awarded Owner $41,700.00 against United, which sum was found to be required to correct defective work and complete the contract. Owner was awarded an additional $2,811.35 against Contractor, which sum was subordinated in rank and privilege to certain lien claimants. United third partied Engineer and Engineer's insurer claiming Engineer is liable in tort to United for any claims United is obligated to pay Owner. United bases its claim on the premise that the duty of inspection owed by Engineer to Owner pursuant to Engineer's oral contract with Owner, and the provisions of the construction contract between Owner and Contractor, is also owed to a surety as well, and that Engineer negligently failed to discharge said obligation.

United appeals rejection of its demands against Engineer. Owner has appealed seeking recovery from United of the following items of expense allegedly incurred as the result of Contractor's default and the attending delay in project completion: (1) Interest in the sum of $34,036.95 paid on construction loans from the time of scheduled completion until final completion; (2) engineering fees paid Engineer in the sum of $4,170.00 for preparing plans for correction and completion of the project; (3) attorney's fees in the sum of $12,500.00 incurred in the concursus proceeding; (4) depreciation of subdivision lots, $38,940.00, and (5) damages to Owner's reputation as a subdivision developer, $50,000.00. A lienor, Altex Ready Mixed Concrete Corporation, has appealed seeking recovery of *257 attorney's fees incurred in the concursus proceeding.

There is little, if any, dispute concerning the facts of this case.

Mr. Joseph D. Calandro (Calandro), president and sole proprietor of Owner, is a builder and developer with extensive experience spanning a period of 22 years. By verbal agreement, he engaged Engineer, at an agreed price of $7,900.00, to survey, stake out and supervise construction of the project. He relied on Engineer to check progress on the work and authorize periodic payments to the Contractor on the basis of completed work. He expected Engineer to directly supervise the work and provide such inspection to insure that the contract would be properly executed. Calandro could not recall whether Engineer suggested that Calandro engage a construction testing laboratory to make compaction tests and check the laying of forms and pouring of concrete streets to be constructed. Calandro was certain, however, he did not inform Engineer not to employ a construction testing laboratory for the project. Calandro concedes that during the approximately eight weeks of construction, he visited the site once or twice weekly. On approximately ten to fifteen of these occasions, he saw either Paul Boudreaux (Boudreaux), a senior member of Engineer, or a subordinate employee, Marshall, inspecting the project.

On Contractor's third pouring of concrete streets (which were to be six inches thick), Calandro noted the surface was improperly finished in that it had a "rub board effect" which condition was called to Boudreaux's attention. Calandro also observed considerable curbing was not properly finished and street drainage was defective. After Contractor had been placed in default and cleanup operations undertaken to determine the status of the project, it was discovered that the street paving was broken and crumbled in several areas. This condition was found to be due to the fact that a considerable portion of the streets were poured with only two inches of concrete instead of six. Calandro concedes that at least one, and perhaps two, progress payments were made to Contractor after defects were noted. These payments, he stated, were made on Boudreaux's assurance the Contractor would correct the defects before final acceptance. Calandro paid Engineer $4,170.00 to prepare plans to correct the defects and complete the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoffman v. Theriot
249 So. 3d 297 (Louisiana Court of Appeal, 2018)
Lathan Co. v. State
237 So. 3d 1 (Louisiana Court of Appeal, 2017)
Greater Lafourche Port Commission v. James Construction Group, L.L.C.
104 So. 3d 84 (Louisiana Court of Appeal, 2012)
Gulf Liquids New River Project, LLC v. Gulsby Engineering, Inc.
356 S.W.3d 54 (Court of Appeals of Texas, 2011)
Young v. City of Plaquemine
818 So. 2d 892 (Louisiana Court of Appeal, 2002)
Livingston Parish v. Millers Mut. Fire
767 So. 2d 949 (Louisiana Court of Appeal, 2000)
Colbert v. BF Carvin Const. Co.
600 So. 2d 719 (Louisiana Court of Appeal, 1992)
Century Ready-Mix Co. v. Campbell County School District
816 P.2d 795 (Wyoming Supreme Court, 1991)
BOSSIER MED. PROP. v. Abbott & Williams Constr. Co.
557 So. 2d 1131 (Louisiana Court of Appeal, 1990)
Standard Roofing Co. v. ELLIOT CONST. CO.
535 So. 2d 870 (Louisiana Court of Appeal, 1988)
MJ Womack, Inc. v. State House of Rep.
509 So. 2d 62 (Louisiana Court of Appeal, 1987)
Boudreaux v. Panger
481 So. 2d 1382 (Louisiana Court of Appeal, 1986)
Dubea v. State Through La. Dept. of Corr.
465 So. 2d 245 (Louisiana Court of Appeal, 1985)
Bowman v. Coursey
433 So. 2d 251 (Louisiana Court of Appeal, 1983)
Gantt v. Boone, Wellford, Clark, Langschmidt & Pemberton
559 F. Supp. 1219 (M.D. Louisiana, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
249 So. 2d 254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/calandro-development-inc-v-rm-butler-contr-inc-lactapp-1971.