Charles Carter & Company v. McGee

213 So. 2d 89, 1968 La. App. LEXIS 4844
CourtLouisiana Court of Appeal
DecidedJuly 1, 1968
Docket7434
StatusPublished
Cited by7 cases

This text of 213 So. 2d 89 (Charles Carter & Company v. McGee) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles Carter & Company v. McGee, 213 So. 2d 89, 1968 La. App. LEXIS 4844 (La. Ct. App. 1968).

Opinion

213 So.2d 89 (1968)

CHARLES CARTER & COMPANY, Inc.
v.
Edward C. McGEE, Jr.

No. 7434.

Court of Appeal of Louisiana, First Circuit.

July 1, 1968.
Rehearing Denied August 12, 1968.

*90 Jack Wise of Caillouet & Wise, Thibodaux, for appellant.

Gerald F. Lofaso, Houma, for appellee.

Before LANDRY, REID and BAILES, JJ.

LANDRY, Judge.

This action by plaintiff Charles Carter & Company, Inc. (Carter), seeks recovery of damages from defendant Edward C. McGee, Jr. (McGee), a registered surveyor, allegedly resulting from McGee's negligence, carelessness and lack of skill in performing professional services in staking piling locations for a building project on which Carter was prime contractor. Defendant reconvened for judgment in the sum of $600.00, the agreed price for the work in question. After trial on the merits, judgment was rendered below in favor of defendant on the main demand, rejecting and dismissing plaintiff's suit. On the reconventional demand, judgment was entered in favor of McGee for the amount prayed for, with interest and costs. From said judgment plaintiff has appealed. We are in accord with the judgment of the trial court and therefore affirm the decree rendered.

The record discloses that Carter was engaged by the Roman Catholic Church of the Archdiocese of New Orleans to construct a high school complex in Houma, Louisiana. The project, designed and planned by Nolan, Norman & Nolan, Architects, New Orleans, Louisiana, called for the construction of three separate but connected and related buildings designated on the plans and specifications as Buildings A, B and C, respectively. According to the plans, the buildings were located one behind the other facing the front or northern boundary line of the construction site, Building A being situated nearest said front property line. Defendant's crew staked the piling locations called for. The pilings were then driven by a subcontractor engaged for that purpose. Shortly thereafter, when batter boards were being erected preparatory to commencing work on the foundations, it was discovered by plaintiff's carpenter foreman, Rivet, that the piling locations allowed for only a 37 foot space between Buildings A and B, whereas it was intended that this distance be 48 feet. On the advice of its architect, the owner declined to approve construction with a spacing of only 37 feet between the edifices concerned. Carter was therefore required to relocate the piling for Building A so that it would be spaced the desired 48 feet from Building B. Plaintiff's suit is for the cost of the additional work involved. Defendant's reconventional demand is for the agreed surveyor's fee which Carter refused to pay.

In essence plaintiff contends defendant was engaged on a professional basis because plaintiff desired to have the work done properly and therefore relied upon defendant's knowledge and skill. Plaintiff further argues that because of defendant's negligence, carelessness and lack of skill, plaintiff sustained a monetary loss equal to the amount required to relocate the piling. Defendant maintains the work was performed in a competent professional manner in accordance with the plans and specifications as supplemented by certain instructions from plaintiff's job superintendent, Porter. Alternatively, defendant argues *91 plaintiff was guilty of contributory negligence through the ineptness of its said job superintendent. Plaintiff counters with the argument that the doctrine of res ipsa loquitur is applicable herein thus imposing on defendant the burden of exculpating himself from the inference of negligence resulting therefrom. Plaintiff also parries with the contention that defendant possessed the last clear chance to avoid the mistake and alternatively asserts defendant is liable in solido with plaintiff as a joint tort feasor in the event Porter be found guilty of any negligence contributing to the error.

There is no real dispute on the question that the pilings as staked out by defendant would have located Building A within 37 feet of Building B instead of 48 feet as desired by the owner. Narration of certain background information, concerning which there is little or no disagreement, will afford a clearer understanding of the manner in which the error occurred.

The record contains the architect's plot plan for the project. Said plot plan is in effect a detailed drawing and portrayal of the size and shape of the three buildings and designates their precise location within the construction site in relation to the front or northern boundary line thereof and also in relation to each other. The plot plan indicates the front "building line" of Building A is 137 feet south of the northern boundary of the construction site. It also indicates that the roof line of Building A, a two-story structure, overhangs or extends northerly beyond its front building line but does not indicate the extent of said projection. The plans and photographs of Building A appearing of record indicate the structure to be approximately 107 feet wide. On either end of its northerly or front side is situated two-story brick and glass enclosed staircases, each being approximately 16 feet in width and extending northerly from the second story projection of the building a distance of about 24 feet. Between these two stairwells the first or ground floor, consisting of a glass facade approximately 74 feet wide, is overhung 11 feet by the second story. The north wall of the second story, between the enclosed stairwells, is of solid brick and supported by visible columns spaced along the northern extremity of the second story overhang between the aforementioned stairwells. Also in evidence is Architect's drawing designated S-1 which details the piling layout within each of the respective buildings. Said drawing indicates three parallel rows of 6 pile clusters extending across the main portion of Building A from east to west, the number of piles in each cluster being expressly shown. It further shows lesser pilings at the east and west ends of the northern extremity of Building A to support the stairwells located at these points. Said piling plan, however, does not specify either the front or rear building line of Building A. In addition there appears of record a drawing designated "Structural layout plan" which in essence sets forth the location of the principal superstructure columns of the entire building in relation to the pilings shown on S-1. Neither the structural layout sheet nor the piling plan indicated on S-1 relate the pilings or superstructure columns to the building line. The fact that the first or most northerly row of main pile clusters was intended to be situated approximately 11 feet north of the building line and support the columns which uphold the overhang of the second story rather than buttress the main front wall of the first or lower story is the circumstance giving rise to the error in the placement of the building concerned. More precisely, in locating Building A with reference to the front property line, the first row of pilings, which supports the overhand of the second story, was placed 137 instead of 126 feet south of the front property line thus resulting in the building line being 148 instead of 137 feet south of the front property line and consequently some 11 feet closer to Building A than called for in the plans and specifications.

*92 We first dispose of plaintiff's contention that the doctrine of res ipsa loquitur and alternatively the principle of last clear chance are applicable to the case at hand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carter v. Deitz
556 So. 2d 842 (Louisiana Court of Appeal, 1990)
Crawford v. Gray and Associates
493 So. 2d 734 (Louisiana Court of Appeal, 1986)
Hogan Exploration v. Monroe Engineer. Assoc.
430 So. 2d 696 (Louisiana Court of Appeal, 1983)
Wetzka v. Big Three Industries, Inc.
409 So. 2d 393 (Louisiana Court of Appeal, 1982)
Am. Fid. Fire Ins. Co. v. Pavia-Byrne Engineering Corp.
393 So. 2d 830 (Louisiana Court of Appeal, 1981)
Lawyers Title Ins. Co. v. Carey Hodges & Associates, Inc.
358 So. 2d 964 (Louisiana Court of Appeal, 1978)
Calandro Development, Inc. v. RM Butler Contr., Inc.
249 So. 2d 254 (Louisiana Court of Appeal, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
213 So. 2d 89, 1968 La. App. LEXIS 4844, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-carter-company-v-mcgee-lactapp-1968.