Am. Fid. Fire Ins. Co. v. Pavia-Byrne Engineering Corp.

393 So. 2d 830, 1981 La. App. LEXIS 3444
CourtLouisiana Court of Appeal
DecidedJanuary 13, 1981
Docket14403
StatusPublished
Cited by13 cases

This text of 393 So. 2d 830 (Am. Fid. Fire Ins. Co. v. Pavia-Byrne Engineering Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Am. Fid. Fire Ins. Co. v. Pavia-Byrne Engineering Corp., 393 So. 2d 830, 1981 La. App. LEXIS 3444 (La. Ct. App. 1981).

Opinion

393 So.2d 830 (1981)

AMERICAN FIDELITY FIRE INSURANCE COMPANY, Plaintiff-Appellee,
v.
PAVIA-BYRNE ENGINEERING CORPORATION, et al., Defendants-Appellants.

No. 14403.

Court of Appeal of Louisiana, Second Circuit.

January 13, 1981.

*832 Dawkins & Coyle by Michael S. Coyle, Ruston, for plaintiff-appellee.

Many, LoCoco & Dwyer by M. Hepburn Many, New Orleans, for defendants-appellants.

Hale M. Walker, Ruston, for City of Ruston.

Before PRICE, MARVIN and JASPER E. JONES, JJ.

JASPER E. JONES, Judge.

Defendants, Pavia-Byrne Engineering Corporation, and its President and Chief Engineer, Edgar H. Pavia, appeal a judgment against them in favor of plaintiff, American Fidelity Fire Insurance, for a sum equal to 71/2% of a contract price of a sewer line installation job performed by a now insolvent contractor for the City of Ruston. Plaintiff answers the appeal contending it was also entitled to a judgment for the same amount against the City of Ruston which was also a defendant in the suit. Ruston had entered into a contract with the D. T. Atkison Company to install approximately 16,000 feet of sewer line in the City of Ruston. The contract was a unit price contract, as opposed to a sum certain contract. Under these circumstances, the contractor does not bid a fixed price to do the entire job, but rather bids a price per unit for the units as estimated by the engineer in the proposal, and gets paid only for as many units as he performs, installs or furnishes. The bid was based on different prices listed in the contract for dissimilar units included within the sewer system to be installed. By way of example, the contractor received more for installation of pipe in areas where the ditch in which the pipe to be laid had to be bored under a street or driveway than he received for installation of pipe in areas where he could simply cut an open ditch. The contractor further received more for installing pipe pressure rated 100 PSI than for installing pipe pressure rated at 47 PSI. The final contract price was not to be determined until the entire project was completed.

Plaintiff executed the contract as surety for the contractor. The sewer system installed under the contract was designed by appellants, Pavia-Byrne Engineering Corporation and Edgar H. Pavia, its President. These appellants were not parties to nor signatories on the construction contract. The evidence establishes that there was a contract between Pavia-Byrne Engineering Corporation and the City of Ruston, by the terms of which it undertook to inspect the work performed by the contractor and to approve the contractor's monthly estimate of work performed. This estimate formed the basis upon which the contractor was entitled, under the terms of the contract, to be paid on the 15th day of each month for the value of the work performed by it in the previous month, less the retainage provided for in the contract.

The contract contained two provisions which described the amount of retainage which Ruston was entitled to withhold from the value of the work performed by the contractor each month. One provision provided that Ruston would retain ten percent (10%) upon the value of the first fifty (50%) percent of the work performed by the contractor and five (5%) percent on the value of the remaining fifty (50%) percent to be performed by the contractor, for a total *833 retainage of 7½%. The other provision stated that after 10% was retained from the first 50% that the subsequent retainage would be reduced in a manner that only 5% would be retained of the total value of the work performed, thereby resulting in Ruston having in retainage at the conclusion of the job 5% of the value of the total work performed.

Appellants provided a full-time inspector on the job who received from the contractor each month his statement of the work performed. This inspector, who was not an engineer, approved the contractor's estimate of the value of the work performed and forwarded the work estimate to Edgar Pavia at his office in New Orleans. Pavia prepared a certificate approving payment to the contractor based upon the estimate of value received from his local inspector. These certificates provided for retainage of 10% on the first 50% of the work and for retainage reducing to 5% on the total work completed after the first 50% had been completed. The certificates approving payment were then signed by a representative of the Ruston Health and Sanitation Department and submitted to Ruston's treasury office for payment. The part of the certificate signed by the Ruston representative contained the estimate of value and the retainage percentage. Ruston made the payment based upon the engineer's approval certificate retaining from the contractor's payment the amount of retainage reflected upon the certificate. After the job was completed a final inspection of the various units included within it was made. When the value of the units of the job was determined in the amount set out for the respective types of work and were totalled, the value of all the work performed was the sum of $233,182.80. If the engineer's certificates on the value of the work performed, upon which Ruston relied, had been correct, the City should have retained funds belonging to the contractor in the amount of 5% × $233,182.80, or $11,659.14. However, the City had only retained $800.02 of the contractor's funds. After completing the job the contractor failed to pay some of the materialmen and subcontractors, and liens were filed upon the job which plaintiff paid in the amount of $23,913.85. Plaintiff filed this suit against appellants and the City of Ruston, contending that these defendants were liable to it for the sum which should have been retained from the contractor calculated upon a 7½% retainage, which amount plaintiff contends would have been available to it to apply upon the liens filed against the job. Plaintiff contended that defendants in the suit were liable to it for this sum because defendants breached their contractual obligations with plaintiff to have protected their security interest in said retainage, and plaintiff alternatively asserted that these defendants owed it a duty under the law of tort to have properly retained under the contract which said defendants negligently failed to do.

The trial court rejected plaintiff's demand against the City of Ruston and awarded judgment against appellants on the theory of negligence. Plaintiff answers the appeal contending that it should also have judgment against the City of Ruston on the theory of contract.

The substantial issues presented on appeal are:

I. Does the surety of a contractor on a public contract have a cause of action against the public body for sums which the public body should have retained from the contract price of an insolvent contractor, but failed to do so under the following circumstance:
A. where the retainage was needed to pay to lien creditors of the contractor but the funds that should have been retained were paid to the contractor by the public body in good faith in reliance upon certificates of the engineer as to the value of the work performed by the contractor and where the contract authorized the City to make payments on this basis?
II. Does the surety of a contract under which the owner fails to fully comply with the retainage provisions, *834 due to the fault of the engineer, have a claim against the engineer in contract for funds which should have been retained and are needed to pay lien creditors where:
A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walton Construction Company, LLC v. GM HORNE & COMPANY, INC.
984 So. 2d 827 (Louisiana Court of Appeal, 2008)
Farboil Co. v. M & M Industrial Maintenance, Inc.
593 So. 2d 806 (Louisiana Court of Appeal, 1992)
Farrell Construction Co. v. Jefferson Parish
693 F. Supp. 490 (E.D. Louisiana, 1988)
Magnolia Const. Co. v. MISS. GULF S. ENG.
518 So. 2d 1194 (Mississippi Supreme Court, 1988)
Alley v. Courtney
448 So. 2d 858 (Louisiana Court of Appeal, 1984)
Emond v. Tyler Building and Const. Co., Inc.
438 So. 2d 681 (Louisiana Court of Appeal, 1983)
Hogan Exploration v. Monroe Engineer. Assoc.
430 So. 2d 696 (Louisiana Court of Appeal, 1983)
Gurtler, Hebert & Co. v. Weyland MacH. Shop, Inc.
405 So. 2d 660 (Louisiana Court of Appeal, 1981)
AF Blair Co., Inc. v. Mason
406 So. 2d 6 (Louisiana Court of Appeal, 1981)
American Fidelity Fire Insurance v. Pavia-Byrne Engineering Corp.
397 So. 2d 1362 (Supreme Court of Louisiana, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
393 So. 2d 830, 1981 La. App. LEXIS 3444, Counsel Stack Legal Research, https://law.counselstack.com/opinion/am-fid-fire-ins-co-v-pavia-byrne-engineering-corp-lactapp-1981.