Talbert v. Bounds & Allen

123 So. 2d 815
CourtLouisiana Court of Appeal
DecidedOctober 27, 1960
Docket9202
StatusPublished
Cited by6 cases

This text of 123 So. 2d 815 (Talbert v. Bounds & Allen) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Talbert v. Bounds & Allen, 123 So. 2d 815 (La. Ct. App. 1960).

Opinion

123 So.2d 815 (1960)

Silas F. TALBERT, Plaintiff-Appellee,[*]
v.
BOUNDS & ALLEN et al., Defendants-Appellants.

No. 9202.

Court of Appeal of Louisiana, Second Circuit.

June 22, 1960.
On Rehearing October 27, 1960.

*816 George T. Anderson, Jr., Coushatta, for Bounds & Allen, defendant-appellant.

Wilkinson, Lewis, Wilkinson & Madison, Shreveport, for Aetna Casualty & Surety Company, defendant-appellant.

Colvin & Hunter, Mansfield, attorneys for plaintiff-appellee.

AYRES, Judge.

This action, a concursus proceeding, was instituted under the provisions of LSA-R.S. 9:4804 by plaintiff as the owner of the Lazy "S" Ranch in DeSoto Parish, Louisiana, upon which, under a contract of June 21, 1956, with Bounds & Allen, a residence was constructed under the supervision of Lester C. Haas, architect, pursuant to plans and specifications prepared by him. For the faithful performance of the contract and for the payment of all labor and materials utilized in the prosecution and completion of the work undertaken, The Aetna Casualty and Surety Company executed its bond in the amount of the contract price of $47,697.

With the filing of this action, plaintiff deposited in the registry of the court, the sum of $1,427.47, as the amount allegedly due by him to the contractors, and prayed that (1) the deposit be accepted and received, not only for the benefit of plaintiff and the aforesaid contractors and surety but, also, for the benefit of the subcontractors, laborers, and furnishers of the material, who may be entitled to participate in the distribution of said fund, (2) the contractors and surety be condemned for all amounts due and owing for labor, materials, and services rendered and performed in connection with the aforesaid improvement, (3) the cost of the proceedings, including the cancellation of the liens filed *817 against the property and an attorney's fee for plaintiff's counsel in provoking this concursus, be paid from the fund deposited, or by the contractor and/or surety, and (4) plaintiff have judgment against the contractors and surety for all amounts which he, as owner, may be required to pay for said construction.

Silas F. Talbert, the owner of the property involved, and for whom the residence was constructed, died subsequent to the institution of this proceeding. Thereafter, Mrs. Amelia H. Talbert, surviving widow, as testamentary executrix, was substituted as party plaintiff.

This controversy is between the owner's succession representative and the contractors and surety inasmuch as the surety has paid all outstanding claims against the property. By assignment and acts of subrogation, the surety has acquired all such claims, amounting to $14,943.69. The contractors and surety reconvened and prayed for judgment against the owner for sums allegedly due by the owner for extra work and services performed by the contractors. These extras are itemized as follows:

1. Laying foundations for
    a water fountain               $  460.00
2. Material and labor in
    replacing defective
    sheetrock ceiling                 9,221.66
3. Charges for water and
    electricity during
    construction                        356.71
4. Extra labor in laying
    brick of the pattern
    and design selected
    by the owner                      1,300.00
5. Extras approved and
    itemized by the
    architect                         1,698.10
                                   ____________
                        Total       $13,036.47
                                   ============

In addition, the surety reconvened for the further sum of $4,139.85, allegedly due because of a premature and prejudicial payment to the contractors of a portion of the contract price, or for a total of $17,176.32. The surety also prayed that it be decreed entitled to the deposit and, in reconvention, for judgment against the owner for the aforesaid sum.

The owner's liability under the contract was determined and recognized in the sum of $2,054.81, against which credit was allowed for $342.13, representing work not done, or work incorrectly done, by the contractors. Out of the deposit made, an attorney's fee of $400 was fixed and ordered paid. The balance thus found to be due by the owner was $1,312.68, leaving a surplus of $114.79 in the deposit which was then applied to supplement the attorney's fee. The owner's succession representative was discharged from further liability unto the contractors, the surety, and lien claimants. The reconventional demands of the contractors and the surety were rejected. From a judgment thus rendered and signed, the contractors and surety, referred to herein as defendants, appealed.

The contention of the defendants is that the court erred in its failure to allow recovery against the owner's succession representative for the items constituting their aforesaid reconventional demands. These contentions will now be discussed and given consideration in the order listed.

The first for consideration is the claim for material and labor for the construction of a concrete foundation for a water fountain. This item was included under a separate contract, by the owner with Powell & Akin, for landscaping the residential site. Powell & Akin, however, subcontracted this portion of the work to plaintiff's principal contractors, Bounds & Allen. The trial court, on concluding this construction was not included in the general contract or covered by the surety's bond, excluded all evidence concerning it. Consequently, the rights of the parties will be preserved, as to this portion of the claim, by its rejection as of nonsuit.

Second, for consideration, is the claim for material and labor required in *818 replacing defective sheetrock ceiling. That the sheetrock purchased and originally installed in the ceiling was defective and unfit for the purpose is clearly established by the record. In fact, this was conceded by all parties concerned, including the architect and a representative of the manufacturer who made an inspection, at the residential site, of the sheetrock as originally used. The record leaves no doubt that the defectiveness was due to an imperfection in the composition of the material. After being nailed to the laths or ceiling joists, the nailheads would sink into and/or pull through the sheetrock, leaving holes. It could not be substantially nailed. While on the job site, the representative of the manufacturer suggested the use of sheetrock of 1/2-inch thickness instead of 3/8-inch thickness as designated in the plans and specifications. This, the contractors did without any expressed authority of the owner or of the architect.

Whose responsibility is it for the payment of the cost of this additional sheetrock and the labor required for its installation? The contractors and surety contend that the sheetrock originally furnished and installed complied with the specifications in that it was of a standard brand of manufacture and of the thickness designated, and that it was properly installed according to customary methods and best practices of the trade. When the material was delivered, the manufacturer's labels, attached to the packages, indicated the material was of the kind and quality designated in the specifications. That 3/8-inch sheetrock is ordinarily and customarily used as ceiling is established by the record, and the imperfection of the material is not attributable to its thickness.

The contract provided that the contractors furnish all of the materials and perform all of the work required for the completion of the residence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Wilco Const. Co., Inc.
393 So. 2d 885 (Louisiana Court of Appeal, 1981)
Am. Fid. Fire Ins. Co. v. Pavia-Byrne Engineering Corp.
393 So. 2d 830 (Louisiana Court of Appeal, 1981)
Airtrol Eng. Co., Inc. v. US Fid., Etc.
345 So. 2d 1271 (Louisiana Court of Appeal, 1977)
National American Bank v. SOUTHCOAST CONTR., INC.
276 So. 2d 777 (Louisiana Court of Appeal, 1973)
WALTERS AIR CONDITION. CO., INC. v. Firemen's Fund Ins. Co.
252 So. 2d 919 (Louisiana Court of Appeal, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
123 So. 2d 815, Counsel Stack Legal Research, https://law.counselstack.com/opinion/talbert-v-bounds-allen-lactapp-1960.