WALTERS AIR CONDITION. CO., INC. v. Firemen's Fund Ins. Co.

252 So. 2d 919, 1971 La. App. LEXIS 5430
CourtLouisiana Court of Appeal
DecidedSeptember 8, 1971
Docket11652
StatusPublished
Cited by9 cases

This text of 252 So. 2d 919 (WALTERS AIR CONDITION. CO., INC. v. Firemen's Fund Ins. Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WALTERS AIR CONDITION. CO., INC. v. Firemen's Fund Ins. Co., 252 So. 2d 919, 1971 La. App. LEXIS 5430 (La. Ct. App. 1971).

Opinion

252 So.2d 919 (1971)

WALTERS AIR CONDITIONING COMPANY, Inc., Plaintiff-Appellee,
v.
FIREMEN'S FUND INSURANCE COMPANY, Defendant-Appellant.

No. 11652.

Court of Appeal of Louisiana, Second Circuit.

September 8, 1971.
Rehearing Denied October 12, 1971.

Snellings, Breard, Sartor & Shafto, by George M. Snellings, III, Monroe and John S. C. Massey, West, Monroe, for defendant-appellant.

Carl F. Walker, Monroe, for plaintiff-appellee.

Before AYRES, BOLIN and PRICE, JJ.

En Banc. Rehearing Denied October 12, 1971.

BOLIN, Judge.

Walters Air Conditioning Company, Inc. instituted suit against defendant, Firemen's Fund Insurance Company, surety for Pruitt Sheet Metal Works, Inc., for $5,843.95, representing the difference between the original subcontract price with Pruitt and the total sums expended by plaintiff to complete the subcontract for ductwork. Pruitt completed approximately one-half of *920 the subcontract and then defaulted. It became necessary for Walters to employ another sheet metal company to complete the air-conditioning job originally contracted. In addition, Walters seeks reimbursement of $480 for attorney's fees expended by it for legal services in a prior injunction proceeding instituted to compel Pruitt to discontinue the work with non-union labor in violation of the contract.

The lower court rendered judgment in favor of plaintiff and against Firemen's Fund for $1,262.30, and in favor of Firemen's Fund for a like amount against third party defendant, Pruitt Sheet Metal Works, Inc. Defendant appeals and plaintiff answers the appeal seeking an increase in the award to the amount originally demanded. Pruitt has not appealed.

The essential facts are not in dispute. This is an action against a surety because of non-performance on the part of the subcontractor for whom defendant, Firemen's Fund Insurance Company, was surety on its performance bond. The subcontract was one for installation of ductwork regulators, grills, and other sheet metal work necessary for the air-conditioning system in a new addition to St. Paul's Methodist Church in the City of Monroe, Louisiana. The subcontract and the bond were in the amount of $8,800. The contract in question contained the following clause or provision, the terms of which lead to the original dispute and subsequent non-performance:

"General Contractor uses men that are affiliated with the Building & Construction Trades Council of Monroe, and Sub-Contractor agrees to use men from this organization on all work at site." (Emphasis added)

At the time the subcontract was entered into, and at the time it commenced its undertaking, Pruitt's employees were in fact affiliated with the Building & Construction Trades Council of Monroe, as required by the quoted clause. Following completion of part of the work, Pruitt's agreement with the named union expired and arrangements were made with a different union to use and employ persons not affiliated with the Building & Construction Trades Council. This action resulted in pickets being placed on the job site and, since other union-affiliated trades refused to cross the picket lines, the entire job was brought to a standstill.

Walters Air Conditioning Company, Inc. obtained a temporary restraining order to prevent Pruitt from making further use of employees not affiliated with the Building & Construction Trades Council of Monroe on this job site. That proceeding before the district court ultimately resulted in the issuance of a permanent injunction against Pruitt as to further use of employees not affiliated as prescribed above. Pruitt filed an answer and reconventional demand in the injunction suit alleging that prior to the injunction it had performed a portion of the contract work amounting to $6,600, for which it had been only partially paid, and sought recovery of the balance allegedly due, although it had not completed the contract. The answer of Walters to the reconventional demand denied the demand and alleged Pruitt had been paid all that it was due for ductwork already installed in the church. Trial was had on the reconventional demand, and judgment was rendered in favor of Pruitt. No issue of breach of contract by Pruitt was raised, nor was Pruitt's bonding company made a party, nor did Walters plead any offset or damages, or other rights relating to completion of the contract. The judge in that suit found Pruitt was entitled to payment for all work done at his shop, as well as that performed at the job site, thus concluding Pruitt had completed 70% of the contract by the time he was enjoined. There was no appeal from this judgment which was ultimately paid by Walters.

Plaintiff contends on this appeal it notified Firemen's that Pruitt had defaulted on its subcontract, and that the surety replied by letter that it did not wish to exercise its *921 right to continue completion of Pruitt's contract. This letter, it is alleged, also advised plaintiff either to continue completion of the contract itself, or to secure another contractor to complete the work. Thus plaintiff alleges its right to recover from the surety all expenses caused by the default of Pruitt, including the cost of obtaining another subcontract with Covington to complete the unfinished air-conditioning ductwork. Defendant-appellant asserts the trial judge committed errors in each of the following respects:

"In failing to recognize that because of the judgment in the injunction and reconventional demand for payment for work performed there was a judicial determination that 70% of the Pruitt subcontract had been performed, and in failing to hold that the most that Walters could claim against the surety would be the reasonable cost of completing 30% of the original contract;
"In failing to apply the doctrine of `collateral estoppel';
"In allowing the claim of $480.00 for attorney's fees expended by Walters in the original proceeding and
"In failing to reject all demands of plaintiff-appellee, Walters, at its cost."

The trial judge's excellent written reasons for judgment contain, we believe, a very concise resume of the facts as well as a correct statement of the law except as it relates to attorney's fees.

With regard to the earlier suit on the reconventional demand of Pruitt, he found that no issue of breach of contract was raised, nor was Pruitt's bonding company made a party, nor did Walters plead any offset or damages or other rights relating to the contract. He concluded Walters paid funds "dedicated" to the performance of the contract, after Pruitt's default, in the total amount of $4,416.00; that the litigation with Pruitt was conducted and the judgment of $3,019.20 was paid long after the surety had advised plaintiff in writing it objected to any payments and considered itself prejudiced thereby. We have reviewed the correspondence between Walters and Firemen's Fund and find it supports this finding. While we are cognizant of the hardship which this finding imposed upon plaintiff, since under its contract progress payments were to be made at regular intervals and payment of the judgment could not be said to be voluntary, nevertheless, these payments without the prior consent of the surety, and without making the surety a party to the suit, did prejudice the latter's ability to protect itself. It was admitted by Pruitt at the time of trial his corporation was insolvent, and was not even in business at that time.

Louisiana Civil Code Article 3061 provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spiers v. Seal
426 So. 2d 631 (Louisiana Court of Appeal, 1982)
State v. Wilco Const. Co., Inc.
393 So. 2d 885 (Louisiana Court of Appeal, 1981)
Airtrol Eng. Co., Inc. v. US Fid., Etc.
345 So. 2d 1271 (Louisiana Court of Appeal, 1977)
Watkins v. Waller Oil Co.
341 So. 2d 1264 (Louisiana Court of Appeal, 1977)
Fireman's Fund Ins. Co. v. Myrick
317 So. 2d 632 (Louisiana Court of Appeal, 1975)
Master Maintenance Engineering, Inc. v. McManus
292 So. 2d 284 (Louisiana Court of Appeal, 1974)
National American Bank v. SOUTHCOAST CONTR., INC.
276 So. 2d 777 (Louisiana Court of Appeal, 1973)
Kelloch v. S & H Subwater Salvage, Inc.
397 F. Supp. 742 (E.D. Louisiana, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
252 So. 2d 919, 1971 La. App. LEXIS 5430, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walters-air-condition-co-inc-v-firemens-fund-ins-co-lactapp-1971.