National American Bank v. SOUTHCOAST CONTR., INC.

276 So. 2d 777
CourtLouisiana Court of Appeal
DecidedJune 29, 1973
Docket9254
StatusPublished
Cited by6 cases

This text of 276 So. 2d 777 (National American Bank v. SOUTHCOAST CONTR., INC.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National American Bank v. SOUTHCOAST CONTR., INC., 276 So. 2d 777 (La. Ct. App. 1973).

Opinion

276 So.2d 777 (1973)

NATIONAL AMERICAN BANK OF NEW ORLEANS
v.
SOUTHCOAST CONTRACTORS, INC., et al.

No. 9254.

Court of Appeal of Louisiana, First Circuit.

March 19, 1973.
Rehearing Denied May 14, 1973.
Writ Refused June 29, 1973.

*778 Marian Mayer Berkett and Frederick R. Bott (Deutsch, Kerrigan & Stiles), New Orleans, for defendant and 3rd Party plaintiff-appellant, American Emp. Ins. Co.

Peter J. Butler (Sehrt, Boyle, Wheeler & Butler), New Orleans, for plaintiff-appellee.

R. Paul Greene, Baton Rouge, for defendant & 3rd Party defendant-appellees, Clarence and Thomas Pruyn.

Before LANDRY, TUCKER and PICKETT, JJ.

TUCKER, Judge.

This litigation involves a suit brought by the plaintiff-appellee, National American Bank of New Orleans (Bank), to recover individually and in its capacity as assignee of its borrower, P. H. P., Inc., the sum of $206,602.23, allegedly spent by PHP in order to complete a contract to construct an apartment complex in Houma, Louisiana, plus $50.00 per day as demurrage, attorney fees, and interest.

The named defendants are Southcoast Contractors, Inc., (Southcoast) the building contractor, and American Employers Insurance Company (Employers), which surety concern had executed its bond, guaranteeing the performance of the construction contract between PHP as owner and Southcoast as builder and also securing the payment of liens.

The trial court rendered a judgment in favor of the Bank and against Employers in the principal sum of $191,569.98 plus $38,300.00 attorney fees and $50.00 per day *779 demurrage from September 10, 1966 until the liens on the property were cancelled. Legal interest was awarded on the accrued demurrage from judicial demand, and interest on the demurrage, subsequently accruing, was calculated from the date on which each charge matured. From this judgment Employers has appealed suspensively. Third party judgments in favor of Employers against R. Grady Williams, architect for the subject building contract, Thomas R. Pruyn and Clarence S. Pruyn, indemnitors on the Employers bond have not been appealed.

The facts of the case are relatively undisputed. Southcoast had been in the general contracting business for a number of years, and Employers had on several occasions, previous to the subject transaction, bonded the performance of Southcoast under its building contracts. Southcoast's stockholders were Thomas R. and Clarence S. Pruyn Jr. In the course of making arrangements for the construction of a 60 unit apartment complex in Houma, the Pruyns, together with John H. Higgins, formed PHP. On February 23, 1966 a formal building contract was executed whereby Southcoast, as builder, agreed to construct the apartment project for PHP, as owner, for the sum of $383,000.00 in accordance with the plans and specifications of R. Grady Williams, architect, within 180 days from the date of recordation thereof. The contract provided that Mr. Williams was the supervising architect and all work was to be done under his direction or any other capable expert appointed by lender (Bank). PHP was named as the obligee under Employers bond, and the Bank was referred to in the contract as the "Lender" and "Subrogee" of PHP.

The contract called for partial payments to be made on the 10th day of each month upon certificates signed by the architect.

The record reflects that there was a commitment for permanent financing of the project in the amount of $510,000.00 issued by IFC Collateral Corporation to the owner with the proviso that the permanent loan must be closed no later than June 14, 1967. Despite the fact that the contract obviously was not completed at the time, the owner PHP accepted the contract on May 12, 1967, which acceptance was filed in the mortgage records of Terrebonne Parish. In explanation of the premature acceptance, John Higgins, secretary of PHP, stated the document was executed in order that the 30 day period for the filing of liens against the subject property would begin to run so that a prime mortgage could be furnished the permanent lender by June 14, 1967, the date on which the commitment was to expire. Mr. Higgins assertedly was informed by the contractor that, though the building contract was not completed at the time, it would be finished by June 14, 1967.

From the inception of the contract through June, 1967, amounts totalling $343,393.02 were paid by the Bank for the account of PHP to the contractor Southcoast. Had the schedule of progress payments been followed, these total payments would have indicated that the project was substantially completed. However, this was not the case as subsequent events established. Several meetings were convened between the owner, surety and lender during the summer of 1967, and at a meeting in August of 1967 these interested parties agreed that the owner should complete the contract with the lender furnishing the necessary funds. The contractor had abandoned the construction site, and Employers declined to complete the contract.

Prior to the owner PHP commencing the completion work, it was estimated that the fulfillment of the contract obligations would require $68,788.90. This estimate of completion cost was substantially less than the sum of $206,602.23, allegedly actually expended by the owner PHP in completing the job. This latter sum was over and above the contract price of $383,000.00.

*780 A third party supplier of materials filed suit on August 27, 1967 and obtained a judgment ordering the cancellation of the acceptance of May 12, 1967 on the ground that it was premature and improperly filed.

After owner's intervention and completion of the contract, another acceptance, dated January 26, 1968, was recorded in the mortgage records of Terrebonne Parish on February 7, 1968.

The testimony of Mr. Martin, vice-president of Bank, who, along with Mr. Coleman, inspected and observed the various aspects of the subject construction for Bank, reflects that during the early part of 1967, it came to his attention that certain bills attributable to the complex had not been paid. When Mr. Martin contacted Thomas Pruyn of Southcoast about this turn of events, he was assured by Pruyn that the bills, which were then small, would be taken care of. After receiving additional calls that other bills due by the contractor were not being paid, in late February or early March of 1967, Mr. Martin personally inspected the project and met with Thomas Pruyn, at which time he told Pruyn that the project had not advanced as far as the progress payments made by Bank would indicate. Nevertheless, despite this inspection and meeting with Pruyn, pointing to the imbalance of the progress payments as compared to the proportion of the work actually completed, and after the acceptance of PHP on May 12, 1967, Bank made a payment on the contract in the sum of $7,207.92 on June 28, 1967.

After owner (PHP) undertook the responsibility of completing the construction, lender (Bank) claimed it disbursed $182,929.15 to complete the complex, and that an additional sum of $75,959.59 was due D. H. Holmes Co., Ltd. for the cost of appliances and carpeting in accordance with the plans and specifications. In the initial meeting of June 1967 Employers agreed to file lien bonds on $19,000.00 of disputed and unpaid bills, but the surety continued its refusal to complete the job during all the meetings held between Bank, PHP and Employers during the summer of 1967.

In August of 1967 surety placed the parties on formal notice that it would not complete the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BOSSIER MED. PROP. v. Abbott & Williams Constr. Co.
557 So. 2d 1131 (Louisiana Court of Appeal, 1990)
Am. Fid. Fire Ins. Co. v. Pavia-Byrne Engineering Corp.
393 So. 2d 830 (Louisiana Court of Appeal, 1981)
Bowles & Edens Co. v. H & H Sewer Systems, Inc.
324 So. 2d 528 (Louisiana Court of Appeal, 1975)
Smolinski v. Taulli
285 So. 2d 577 (Louisiana Court of Appeal, 1974)
National American Bank of New Orleans v. Southcoast Contractors, Inc.
279 So. 2d 694 (Supreme Court of Louisiana, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
276 So. 2d 777, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-american-bank-v-southcoast-contr-inc-lactapp-1973.