BOSSIER MED. PROP. v. Abbott & Williams Constr. Co.

557 So. 2d 1131
CourtLouisiana Court of Appeal
DecidedFebruary 28, 1990
Docket21260-CA
StatusPublished
Cited by8 cases

This text of 557 So. 2d 1131 (BOSSIER MED. PROP. v. Abbott & Williams Constr. Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BOSSIER MED. PROP. v. Abbott & Williams Constr. Co., 557 So. 2d 1131 (La. Ct. App. 1990).

Opinion

557 So.2d 1131 (1990)

BOSSIER MEDICAL PROPERTIES, Plaintiff-Appellee,
v.
ABBOTT AND WILLIAMS CONSTRUCTION COMPANY OF LOUISIANA, INC., Abbott and Williams Construction Company of Texas, Inc., and Great American Insurance Company, Defendants-Appellants.

No. 21260-CA.

Court of Appeal of Louisiana, Second Circuit.

February 28, 1990.

*1132 Mayer, Smith & Roberts, Henry R. Bellamy, Shreveport, for defendant-appellant, Great American Ins. Co.

Blanchard, Walker, O'Quin & Roberts, James W. Wyche, Shreveport, for plaintiff-appellee.

Before HALL, NORRIS and HIGHTOWER, JJ.

HIGHTOWER, Judge.

In this action involving the breach of a building contract, Great American Insurance Company, surety on a contractor's performance bond, appeals an award in favor of a partnership, Bossier Medical Properties, which has answered the appeal. Finding merit in one of the surety's contentions, we amend and, as amended, affirm.

Factual and Procedural Context

On March 2, 1983, Bossier Medical Properties, a Louisiana partnership consisting of Dr. John M. Brady and Dr. Charles A. Powers, entered into a building contract with Abbott Construction Company of Louisiana, Inc. ("the contractor") for the construction of a three story medical office building in Bossier City, Louisiana. Abbott and Williams Construction Company of Texas also executed the agreement in the capacity of guarantor, and the contractor posted a performance bond with Great American as surety.

The contract provided that the construction work was to be commenced within ten days of receiving the building permit or on April 1, 1983, whichever came first. Further, the ground floor was to be ready for occupancy no later than August 1, 1983, with 150 calendar days allotted from commencement to total completion of the building. Work was not begun until mid or late July, only a few weeks before the ground floor was to be ready for occupancy. The partnership intended to lease the building to various medical tenants and, toward that objective, had secured commitments from several potential lessees before construction began.

Because the work was not completed as scheduled, tenants were unable to move into the premises as planned. On May 3, 1985, the partnership instituted suit against the contractor, the guarantor, and the surety, for damages resulting from the delay, it being alleged that portions of the office building were not ready for occupancy until March 1984. Additionally, the partnership sought attorney's fees and penalties from the surety pursuant to LSA-R.S. 22:658. Work on the building, as found by the trial *1133 court, was completed after the filing of suit. [An exception of prescription was rejected after trial on the merits.]

At trial, demands against the surety were severed from those against the other two defendants, who apparently had not received notice of trial. The partnership and surety stipulated, during the trial, that the net rental loss to the partnership (lost rent minus interest gains), caused by the untimely completion of the project, was $60,355.69. The judgment awarded: (1) $29,574.32[1] against the contractor, guarantor and surety in solido, plus legal interest; (2) $2,272.80[2] against the contractor and guarantor in solido, plus legal interest as specified in the judgment; (3) $2,957.43 against Great American Insurance Company only, representing attorney's fees of 10 percent granted pursuant to LSA-R.S. 9:3902; and (4) court costs against all three defendants in solido.

The surety, the only defendant appealing, contends that its liability under the bond does not extend to lost rental income caused by the contractor's breach. It is asserted that, interpreting the bond language fairly and reasonably, the surety simply promises to assume the expense of completing all defective or unfinished work left by the contractor, and that such items as lost rent are not contemplated by the bond provisions.

Secondly, the surety asserts that the trial court erred in awarding attorney's fees under the provisions of LSA-R.S. 9:3902, as this statute is strictly construed to allow such fees only where the full amount claimed in the demand is recovered.[3]

Answering the appeal, the partnership argues that the trial court should have awarded the attorney's fees and penalties contemplated by LSA-R.S. 22:658, rather than simply granting attorney's fees under LSA-R.S. 9:3902. It is requested that the judgment be modified to increase attorney's fees and also award penalties, all as provided in LSA-R.S. 22:658.

Discussion

Suretyship is an accessory promise by which one party binds himself to fulfill the obligation of another if the latter fails to do so. LSA-C.C. Art. 3035 (1870, Rev.1987); National American Bank of New Orleans v. Southcoast Contractors, Inc., 276 So.2d 777 (La.App. 1st Cir.1973), writ denied, 279 So.2d 694 (La.1973). The surety promises to satisfy the entire obligation, unless his agreement is otherwise limited. See Comments to LSA-C.C. Art. 3045 (Rev.1987).

Contractors' surety bonds are of two types, sometimes combined in a single bond: performance bonds, which guarantee the contractor will perform the contract; and labor and material payments bonds, which guarantee that all bills for labor and materials contracted for and used by the contractor will be paid by the surety if the contractor defaults. Congregation of St. Peters v. Simon, 497 So.2d 409 (La.App. 3d Cir.1986). The Private Works Act recognizes both performance and payment bonds. LSA-R.S. 9:4812(C)(1) and (2); Congregation of St. Peters v. Simon, supra. Obligations set forth in a bond given by a compensated surety are strictly construed in favor of protecting the obligee. Louisiana Bank and Trust Co., Crowley v. Roanoke Rice Co-op, 298 So.2d 868 (La. App. 3rd Cir.1974), writ denied, 302 So.2d *1134 35 (La.1974); Prestigiacomo v. Phoenix Insurance Co. of Hartford, 231 So.2d 431 (La.App. 4th Cir.1970); State v. Preferred Accident Insurance Co. of New York, 149 So.2d 632 (La.App. 1st Cir.1963).

In the case at hand, the trial court found the surety liable for lost rental based upon the specific language of the bond agreement. We concur in that interpretation. The pertinent portion of the bond reads as follows:

NOW, THEREFORE, the condition of this obligation is such that, if the Principal [the contractor] shall faithfully perform the work as specified in the contract on his part, and shall fully indemnify and save harmless the Obligee [the partnership], from all costs and damage which the Obligee may suffer by reason of failure to so do and shall fully reimburse and repay the Obligee all outlay and expense which the Obligee may incur in making good any such default, and shall pay all persons who have contracts directly with the Principal for labor or materials, then this obligation shall be null and void, otherwise it shall remain in full force and effect.

Thus, the surety agreed to stand liable if the contractor, upon failing to "faithfully perform the work as specified in the contract," did not fully pay the partnership for "all costs and damage which the [partnership] may suffer by reason" of the breach.

Not completing construction by the dates indicated, the contractor clearly did not "perform the work as specified." Nor, after the breach, did the contractor fully indemnify the partnership for all costs and damage suffered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gootee Construction, Inc. v. Atkins
207 So. 3d 485 (Louisiana Court of Appeal, 2016)
Jefferson Door Co. v. Forman Const., Inc.
836 So. 2d 552 (Louisiana Court of Appeal, 2002)
L & a CONTRACTING v. Ram Indus. Coatings, Inc.
762 So. 2d 1223 (Louisiana Court of Appeal, 2000)
Hershell Corp. v. Fireman's Fund Ins. Co.
743 So. 2d 698 (Louisiana Court of Appeal, 1999)
Certified Finance, Inc. v. Bates
749 So. 2d 687 (Louisiana Court of Appeal, 1998)
Stonecipher v. Mitchell
655 So. 2d 1381 (Louisiana Court of Appeal, 1995)
Nicholson & Loup v. Carl E. Woodward
596 So. 2d 374 (Louisiana Court of Appeal, 1992)
Robbins Tire & Rubber v. Winnfield Retread
577 So. 2d 1189 (Louisiana Court of Appeal, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
557 So. 2d 1131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bossier-med-prop-v-abbott-williams-constr-co-lactapp-1990.