Jackson Lumber Co. v. Moseley

11 So. 2d 199, 193 Miss. 804, 1942 Miss. LEXIS 160
CourtMississippi Supreme Court
DecidedDecember 14, 1942
DocketNo. 35112.
StatusPublished
Cited by7 cases

This text of 11 So. 2d 199 (Jackson Lumber Co. v. Moseley) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jackson Lumber Co. v. Moseley, 11 So. 2d 199, 193 Miss. 804, 1942 Miss. LEXIS 160 (Mich. 1942).

Opinion

Roberds, J.,

delivered the opinion of the court.

This is a contest between appellant lumber company, as assignee under a building contract, and Maryland Casualty Company, as surety on such contract, over a balance owing by Niles Moseley under the contract, which balance, under bill of interpleader, Moseley has paid into court. Appellant, by cross-bill, also seeks a personal decree against Moseley. The lower court awarded the money to the surety company and denied the personal decree, from which the lumber company appeals.

On October 3, 1940, Tom B. Scott, by written contract, agreed to construct for Moseley, according to designated drawings and specifications, an apartment house in the City of Jackson, Mississippi, furnishing all labor and materials, for $60,500] subject to additions and deductions as provided in the contract. The contract contains these provisions:

“Article 4 — Progress Payments: The owner shall make payments on account of the Contract as provided therein, as follows:
“On or about the first & fifteenth day of each month eighty-five per cent of the value, based on the contract prices, of labor and materials incorporated in the work and of materials suitably stored at the site thereof up to the first and.fifteenth day of that month, as estimated *814 by the Architect, less the aggregate of previous payments; and upon substantial completion of the entire work, a sum sufficient to increase the total payments to ninety per cent of the contract price.
“Article 5. Acceptance and Final Payment: Final payment shall be due fifteen days after substantial completion of the work provided the work be then fully completed and the contract fully performed.
“Upon receipt of written notice that the work is ready for final inspection and acceptance, the Architect shall promptly malee such inspection, and when he finds the work acceptable under the contract and the contract fully performed he shall promptly issue a final certificate, over his own signature, stating that the work provided for in this contract has been completed and is accepted by him under the terms and conditions thereof, and that the entire balance found to be due the contractor, and noted in said final certificate, is due and payable.
“Before issuance of final certificate the Contractor shall submit evidence satisfactory to the Architect that all payrolls, material bills, and other indebtedness connected with the work have been paid. ”

Maryland Casualty Company executed a bond guaranteeing the faithful performance of the contract by Scott, and to hold Moseley harmless from the contractor’s failure to so perform and to “promptly make payment to all persons supplying labor or materials — ” to the contractor, making the construction contract a part of the bond.

The application for the bond contains this provision: “In the event of claim or default under the bond (s) herein applied for, or in the event the undersigned shall fail to fulfill any of the obligations assumed under the said contract and bond (s) . . . all payments due or to become due under the contract covered by the bond (s) herein applied for, shall be paid to the Company— and this covenant shall operate as an assignment thereof *815 and the residue, if any, after reimbursing the Company as aforesaid, shall be paid to the undersigned after all liability of the Company has ceased to exist under the said bond (s), and the Company shall at its option be subrogated to all rights, properties and interest of the undersigned in said contract — .”

On January 28, 1941, the surety company mailed to Moseley a copy of this application.

In the meantime, and on November 20th, 1940, Scott, to secure an existing indebtedness of five thousand dollars to Jackson Lumber Company, appellant, evidenced by a promissory note, and also to secure future advances, not to exceed five thousand dollars at any one time, for use by Moseley in the construction of the Moseley apartment house, assigned, by writing, to said lumber company “all sums of money due and to become due from Niles Moseley or his assigns to the assignor in connection with or in any manner growing or proceeding from said construction contract,” and directed that all checks by Moseley should be made to the lumber company and Scott jointly and empowered the lumber company to endorse said checks in the name and on behalf of Scott, with the further provision “All amounts so paid and delivered to the assignees shall be considered as payment to the assignor.” But “This assignment is made subject to the right of any bonding or surety company, that may be' involved, to the retained percentage of monies to become due under and by virtue of the terms of said construction contract.”

On November 20, 1940, Moseley acknowledged receipt of notice of the assignment.

Scott proceeded with the construction. The lumber company had advanced to him to June 14, 1941, payrolls aggregating $23,138.99, all of which had been repaid except $733.99, which was advanced on that date, and $1100 had been paid on the note. However, to that date Moseley had made progress payments to the contractor *816 and appellant jointly aggregating $49,755.41, appellant permitting' Scott to receive and use from such progress payments $27,350.41.

On June 18, 1941, Scott wrote Moseley “I have mad© default in completing contract for the construction of apartment house on North State Street. I will be unable to meet the payrolls due Saturday and request you to do so. Upon the advancement of future payrolls, I will superintend the completion of the contract and co-operate with you to the fullest extent.” . Moseley immediately notified the surety and lumber company of receipt of this letter. The net result of the correspondence was that the lumber company and the surety agreed to the foregoing arrangement, the lumber company insisting that Moseley advance the payrolls from retained percentages and the surety that he advance them from the earned progress payments. The work proceeded to completion under that arrangement. The lumber company made no further advances to Scott. On the date of that letter from Scott all materials had been purchased and had either been installed or were on the ground. However, there were unpaid claims for such materials aggregating $18,084.54. Moseley thereafter paid out $5,801.28 for payrolls to complete the job. The completed work was accepted July 18, 1941. The total cost thereof, after adjusting additions and deductions, turned out to be $61,-144.55. Moseley gave due notice by publication to laborers and materialmen as the statute requires. Claims for materials to the amount of $18,084.54 were filed, including one of appellant for $5,523.55, all of which the surety paid.

The payments Moseley had made to June 18, plus the amount he thereafter made for payrolls, left in his hands an unpaid balance of $5,791.66 of the total cost of the job, subject to some further slight adjustments, about which there is no controversy here.

*817

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Surety Corp. v. State National Bank of Frankfort
454 S.W.2d 354 (Court of Appeals of Kentucky (pre-1976), 1970)
Talbert v. Bounds & Allen
123 So. 2d 815 (Louisiana Court of Appeal, 1960)
State ex rel. National Surety Corp. v. Malvaney
72 So. 2d 424 (Mississippi Supreme Court, 1954)
STATE, USE OF NATL. S. CORP. v. Malvaney
72 So. 2d 424 (Mississippi Supreme Court, 1954)
Oden Const. Co. v. HELTON
65 So. 2d 442 (Mississippi Supreme Court, 1953)
Old Ladies Home Assn. v. Hall
52 So. 2d 650 (Mississippi Supreme Court, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
11 So. 2d 199, 193 Miss. 804, 1942 Miss. LEXIS 160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jackson-lumber-co-v-moseley-miss-1942.