STATE, USE OF NATL. S. CORP. v. Malvaney

72 So. 2d 424, 221 Miss. 190
CourtMississippi Supreme Court
DecidedMay 10, 1954
Docket39172
StatusPublished
Cited by4 cases

This text of 72 So. 2d 424 (STATE, USE OF NATL. S. CORP. v. Malvaney) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
STATE, USE OF NATL. S. CORP. v. Malvaney, 72 So. 2d 424, 221 Miss. 190 (Mich. 1954).

Opinion

221 Miss. 190 (1954)
72 So.2d 424
64 Adv. S. 56

STATE FOR USE OF NATIONAL SURETY CORP.
v.
MALVANEY, et al.

No. 39172.

Supreme Court of Mississippi.

May 10, 1954.

*193 Young & Daniel, Jackson; Witherspoon & Bordeaux, Meridian, for appellant.

*196 Creekmore & Beacham, Jackson, for appellee E.L. Malvaney.

*197 Snow & Covington, Meridian; L.L. Forman, Meadville, for appellees W.E. Boggan and United States Fidelity and Guaranty Company.

HOLMES, J.

The appellant brought this suit originally in the Chancery Court of the First Judicial District of Hinds County, as an attachment in chancery, against W.E. Boggan, Superintendent of Education of Franklin County, United States Fidelity and Guaranty Company, the surety on the said Boggan's official bond, Bank of Franklin, a banking corporation domiciled at Meadville in Franklin County, Mississippi, E.L. Malvaney, a resident of the *198 First Judicial District of Hinds County, and certain other parties who were named as defendants for the purpose of binding in their hands any funds or effects owing or belonging to the United States Fidelity and Guaranty Company, but who were discharged by agreement of counsel upon the filing of an appropriate bond by the United States Fidelity and Guaranty Company in the penalty of $10,000.

The suit sought recovery of the sum of $11,000 upon the ground that retainage funds in that amount had been negligently released to the contractor under a construction contract, thereby depriving appellant of resort thereto under the equitable doctrine of subrogation.

On motion of the defendant W.E. Boggan, the cause was transferred to the Chancery Court of Franklin County where it was finally heard and decided on its merits and a final decree rendered therein dismissing the original bill as to the defendants W.E. Boggan, United States Fidelity and Guaranty Company, and Bank of Franklin, and awarding a money decree in the sum of $5,500 in favor of the complainant, National Surety Corporation, and against the defendant E.L. Malvaney. From the final decree entered, the National Surety Corporation and the said E.L. Malvaney each prosecuted an appeal to this Court. There was no appeal as against the decree in favor of the Bank of Franklin.

The litigation arose out of the following facts and circumstances: Shortly prior to October 12, 1950, the Board of Trustees of the Meadville Consolidated School District entered into a verbal agreement with the appellee, E.L. Malvaney, whereby the said Board of Trustees employed the said Malvaney as an architect to prepare plans and specifications for and to supervise the construction of an auditorium and cafeteria building in Meadville, Franklin County, Mississippi. The compensation of the architect was fixed at six per cent of the contract price. On October 12, 1950, the said Board of Trustees entered into a written contract with L. *199 Chester Owens as contractor to construct the aforesaid building for the total contract price of $93,577.00, in accordance with the plans and specifications prepared by the said architect and adopted by the said board of Trustees. Among other provisions of the contract were the following:

"Article 4. Progress Payments — The owner shall make payments on account of the Contract as provided therein, as follows: On or about the 5th day of each month 85 per cent of the value, based on the Contract prices, of labor and materials incorporated in the work and of materials suitably stored at the site thereof up to the 1st day of that month, as estimated by the Architect, less the aggregate of previous payments; and upon substantial completion of the entire work, a sum sufficient to increase the total payments to ____ per cent of the Contract price ____ (Insert here any provision made for limiting or reducing the amount retained after the work reaches a certain stage of completion.)

"Article 5. Acceptance and Final Payment — Final payment shall be due 30 days after substantial completion of the work provided the work be then fully completed and the contract fully performed. Upon receipt of written notice that the work is ready for final inspection and acceptance, the Architect shall promptly make such inspection, and when he finds the work acceptable under the Contract and the Contract fully performed he shall promptly issue a final certificate, over his own signature, stating that the work provided for in this Contract has been completed and is accepted by him under the terms and conditions thereof, and that the entire balance found to be due the Contractor, and noted in said final certificate, is due and payable.

"Before issuance of final certificate the Contractor shall submit evidence satisfactory to the Architect that all payrolls, material bills, and other indebtedness connected with the work have been paid.

*200 "If after the work has been substantially completed, full completion thereof is materially delayed through no fault of the Contractor, and the Architect so certifies, the Owner shall, upon certificate of the Architect, and without terminating the Contract, make payment of the balance due for that portion of the work fully completed and accepted. Such payment shall be made under the terms and conditions governing final payment, except that it shall not constitute a waiver of claims."

On October 16, 1950, the said Owens executed a performance bond on which the appellant, National Surety Corporation, became surety. As the construction progressed, and on periodic estimates approved by the architect, progress payments were made to the contractor, which by May 28, 1951, amounted to the total sum of $78,209.62. On July 2, 1951, the architect wrote a letter to the board of trustees advising that an inspection of the auditorium and cafeteria building indicated substantial completion of the contract with certain exceptions therein stated, and recommended the acceptance of the building with the exceptions stated. This letter, signed by the architect, was as follows:

"Board of Trustees "Meadville Schools "Meadville, Mississippi "Gentlemen:

"An inspection of the auditorium and cafeteria building indicates substantial completion of the contract with the following exceptions:

1. Clear building, wash windows, remove debris.

2. Flag halyard too short.

3. Complete hanging of a few doors and install hardware.

4. Complete electric fixtures in cafeteria and connect heaters in auditorium.

5. Credit due owner for cabinets omitted, hardware for same and fibertile ceiling omitted over stage.

This office recommends the acceptance of the building with the exception of the above mentioned items."

*201 On July 6, 1951, the contractor presented to the architect his estimate No. 8, which was approved by the architect, and was as follows:

              "MEADVILLE AUDITORIUM & GYMNASIUM
                        Estimate No. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FOSTER BY FOSTER v. Bass
575 So. 2d 967 (Mississippi Supreme Court, 1990)
Beaman v. Helton
573 So. 2d 776 (Mississippi Supreme Court, 1990)
American Casualty Company v. Town of Shattuck, Okl.
228 F. Supp. 834 (W.D. Oklahoma, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
72 So. 2d 424, 221 Miss. 190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-use-of-natl-s-corp-v-malvaney-miss-1954.