American Casualty Company v. Town of Shattuck, Okl.

228 F. Supp. 834, 1964 U.S. Dist. LEXIS 8022
CourtDistrict Court, W.D. Oklahoma
DecidedMarch 23, 1964
Docket9544
StatusPublished
Cited by8 cases

This text of 228 F. Supp. 834 (American Casualty Company v. Town of Shattuck, Okl.) is published on Counsel Stack Legal Research, covering District Court, W.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Casualty Company v. Town of Shattuck, Okl., 228 F. Supp. 834, 1964 U.S. Dist. LEXIS 8022 (W.D. Okla. 1964).

Opinion

DAUGHERTY, District Judge.

In this ease the plaintiff as an Oklahoma statutory payment bond surety has sued several defendants, one, the Town of Shattuck, Oklahoma, as the owner of a municipal sewer construction project, another, Alexander, Myers & Associates, a co-partnership, as the engineer on the project, and the remaining defendants as unpaid creditors of the bonded contractor on such project.

When suit was originally filed, the plaintiff as the statutory payment bond surety had not paid the creditors named herein as defendants, but plaintiff has since elected to pay these creditors and thereby their presence in this litigation has been eliminated. Furthermore, the Court has heretofore sustained a Motion to Dismiss filed herein by the defendant Alexander, Myers & Associates, the engineer, the order of the court in this respect being set out in full as a footnote. 1 Thus, at this moment the controversy involves the plaintiff as the statutory payment bond surety and the defendant Town of Shattuck as the public entity owning the municipal project involved. The plaintiff will be hereinafter referred to as the Surety, and the remaining defendant, Town of Shattuck, as the Town or Owner.

The Town entered into separate contracts with Alexander, Myers & Associates, for engineering services, and with Harold Gouge doing business as Security Construction Company for construction services, both pertaining to a municipal sewer project in the Town of Shattuck, in *837 Ellis County, Oklahoma. Alexander, Myers & Associates will hereinafter be called the Engineer and Harold Gouge doing business as Security Construction Company will hereinafter be called the Contractor. The Contractor furnished a statutory payment bond mandatorily required by Title 61 Oklahoma Statutes Annotated, Sections 1 and 2, and also furnished a separate performance bond which is optional in Oklahoma but required by the Town on the project here involved. The plaintiff was the Surety on each of these separate bonds. The sewer project was completed by the Contractor and he has been paid the agreed amount for the same by the Town. The plaintiff as surety on the performance bond was not called upon by anyone to perform or complete the work agreed upon by the contractor. However, the Contractor did not pay all of his bills owing to laborers and materialmen and pertaining to this project. As stated above, the plaintiff as a statutory payment bond surety has now paid these bills and seeks herein to recover or be reimbursed for such payments from the Town or Owner.

The said construction contract entered into between the Town and Contractor, provided in part as follows:

“No money shall be paid on such monthly estimates until the Contractor shall have furnished proper vouchers showing all of said labor and the bills for all of said material to be fully paid;”

Under the said engineering contract the Engineer had the duty to make monthly progress estimates, which it did. But the Engineer had no duty under either contract (construction or engineering) to see that the Contractor paid his bills or furnished vouchers showing payment thereof, and the Engineer did not assume or undertake to perform such a duty. It was for these reasons that the Court sustained the Motion to Dismiss of the Engineer. In other words, there was no contractual responsibility or duty in this connection on the part of the Engineer, the Engineer did not in fact assume this responsibility by its conduct and this responsibility is not imposed upon the Engineer by law.

Under the evidence of this ease it appears that the Town (and Engineer) did not require nor did the Contractor furnish proper vouchers showing the payment of all labor and material bills at any time during the construction period or at the time the final payment was made upon the completion of the project.

The plaintiff as statutory payment bond Surety contends herein that the above quoted provision of the construction contract was for its benefit with a resulting right in it to rely thereon and that the Town by failing to adhere to same impaired the Surety’s rights of subrogation and exoneration under the statutory payment bond and is therefore liable for the damages or losses the Surety has sustained in its payment of labor and material bills. The plaintiff also appears to assert an alternate right of recovery on the basis of tort, in that the Town as the Owner became duty bound to the plaintiff as the Surety on the statutory payment bond by virtue of said contract provision not to pay monthly estimates until furnished vouchers showing all bills of the Contractor to have been paid and is guilty of negligence in the performance of said duty by not exercising ordinary or due care in fulfilling the same.

The Town contends that said contract provision is not for the benefit of the Surety on the statutory payment bond under Oklahoma law but is for the sole benefit of the Town and the said payment bond Surety had no right to rely upon the same; that the said Surety is not a party to the said construction contract and as a statutory payment bond surety no privity exists between the Surety and the Town; further that since the Town has no construction funds in its possession pertaining to the construction project involved, there is not now nor has there ever existed a right of subrogation or exoneration in favor of the payment bond Surety and against the Town.

*838 At this point it is believed important to observe that whereas the plaintiff was the surety on separate performance and payment bonds furnished for this project its position in this litigation is necessarily based on and is limited to its rights, duties and obligations as a statutory payment bond surety. This is so because the bonds are separate and distinct and because the plaintiff has incurred no loss of any kind under the performance bond for the reason that its principal on said performance bond performed and completed the work covered thereby. Even so, it is necessary to consider the fundamental differences existing between the two bonds in view of the said construction contract provision involved and the cases urged on the Court by the parties as being decisive of this controversy.

The obligation of a surety on a performance bond, upon default of the principal or contractor, is to perform or finish the work agreed upon or pay the owner the cost of performing or finishing the work. The obligation of a Surety on a payment bond is not to perform or finish the work or pay the cost of performing or finishing the work but is to pay any unpaid bills of the contractor or principal relating to the job. The nature of the two obligations is obviously distinct and different. This has eventually led to the general requirement for separate bonds to avoid confusion and indeed the Miller Act, for example, is now specific in this requirement. In Oklahoma the statutory payment bond is mandatory on public construction whereas a performance bond is optional to the owner. The obligee of a statutory payment bond is the State of Oklahoma whereas the obligee in a performance bond is the owner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boren v. Thompson & Associates
2000 OK 3 (Supreme Court of Oklahoma, 2000)
Yellow Pine Lumber Co. v. Insurance Co. of North America
687 F. Supp. 545 (W.D. Oklahoma, 1988)
Gardner v. Bean
677 P.2d 1116 (Utah Supreme Court, 1984)
Givoh Associates v. American Druggists Insurance
562 F. Supp. 1346 (E.D. New York, 1983)
Opinion No. 73-306 (1974) Ag
Oklahoma Attorney General Reports, 1974

Cite This Page — Counsel Stack

Bluebook (online)
228 F. Supp. 834, 1964 U.S. Dist. LEXIS 8022, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-casualty-company-v-town-of-shattuck-okl-okwd-1964.