Federal Surety Co. v. St. Louis Structural Steel Co.

1925 OK 468, 239 P. 154, 111 Okla. 208, 1925 Okla. LEXIS 471
CourtSupreme Court of Oklahoma
DecidedJune 9, 1925
Docket15440
StatusPublished
Cited by10 cases

This text of 1925 OK 468 (Federal Surety Co. v. St. Louis Structural Steel Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Federal Surety Co. v. St. Louis Structural Steel Co., 1925 OK 468, 239 P. 154, 111 Okla. 208, 1925 Okla. LEXIS 471 (Okla. 1925).

Opinion

Opinion by

STEPHENSON, C.

The St. Louis Structural Steel Company commenced its action against the Federal Surety Company on a builder’s bond, for bridge material sold and delivered to Y. O. Mathews, a contractor. The trial of the cause resulted in judgment in favor of the plaintiff. Defendant has perfected its appeal and assigns the following errors for the reversal of the cause: First, error of the court in overruling demurrer to plaintiff’s petition; second, error of the court in overruling defendant’s demurrer to plaintiff’s evidence; third, error of the court in refusing to make V. O. Mathews, the contractor, and principal in the bond, a party defendant.

The board of county commissioners of Lincoln county entered into a written contract with V. O. Mathews, whereby the latter bound himself to construct certain steel bridges for the county. V. O. Mathews executed and delivered a builder’s bond to the state of Oklahoma, pursuant to section 7486, -Comp. St. 1921. The Federal Surety Company became a surety upon the bond for the faithful performance of its conditions.

V. 0. Mathews entered into a written contract with the steel company to fabricate one of the steel bridges for the contractor. The contract provided that shipment should be within 30 days from receipt of the ápproved drawings, terms to be 60 days, net.

The obligation of the steel company under the contract was to furnish the steel necessary for “Bridge O,” fabricate the steel, fashion the same into a bridge, and ship to -the contractor at Midlothian, Okla. An answer to a question directed to a witness of the plaintiff explains what is meant by fabrication of a steel bridge, the answer being in. the following language :

“The St. Louis Structural Steel Company took the steel as it came from the mills and cut it to the proper lengths, fitted it and drilled it, put it together and fastened it in the shape of the bridge and riveted it together for bridge ‘C’.”

The plaintiff fabricated the steel bridge and shipped it to the destination designated by the co¡n]tract. The bridge was unloaded from the railway cars upon the right of way, at a point about 150 yards from the location where the plans and specifications designated that the bridge should be situated. Bridge “C” was one of the several bridges which Mathews contracted to build in Lincoln county. Certain litigation was commenced between the contractor and board of county commissioners, during the process of the completion of the several bridges. Certain taxpayers intervened in the causes, which were finally settled and compromised. It appears that Mathews took judgment against the county for some of the bridges- .which were completed and for the steel involved in this action. It appears that the steel fabricated and shipped to the contractor for bridge “C” was lying on the ground, where it was unloaded from the cars, at the time judgment was taken by Mathews against the county for the bridges and steel, and was there on the ground at the time this action -was tried.

The surety company makes the following point: That the materialman in this case *209 cannot recover upon the builder’s bond for the reason that the fabricated bridge did not find its way into a completed structure upon the site provided for by the .plans and specifications.

The disposition of the question as made by the surety company depends upon the construction to be placed upon section 748®, supra, and the conditions of the bond as sued on in this action. Section 7486, supra, is in the following language:

“Whenever any public officer shall, under the laws of the state, enter into contract in any sum exceeding one hundred dollars, with any person or persons, for the purpose of malting anjy public improvements, or constructing any public buildings or making repairs on the same, such officer shall take from the party contracted with, a bond with good and sufficient sureties to the state of Oklahoma, in a sum not less than the sum total in the contract, conditioned that such contractor or contractors shall pay all indebtedness incurred for labor or material furnished in the construction of said public building or in making said public improvements.”

The conditions of the bond sued on in this action are in the following language:

“Now, therefore, if said principal shall well and truly pay or cause to be .paid all sums of money due or which may hereafter become due for any and all labor and material employed and used in the construction of said work under said contract then this obligation shall be void; otherwise to remain in full force and effect.”

The provisions of the statutes refer to that indebtedness incurred for labor and material furnished in 'the construction of a public building. The condition of the bond refers to labor and material employed and used in the construction of the public building involved in this case. There can be but little difference, if any, between the phraseology of the statutes and that of the bond sued on.

The phrase “furnished in the construction of said building,” as used in the statutes, is not substantially different from the phrase “in the construction of said work under said contract,” as used in the condition of the bond sued on. The phrase, as used in the condition of the bond and last referred to, has reference to tihe construction of the bridge according to the contract entered into between the contractor and the board of county commissioners. The particular point made by the plaintiff in error in this respect is that the material must be used in a completed structure in order to give the materialman a right of action on the builder’s bond. Neither the statutes nor the condition of the bond expressly provide that; the material should be used in a “completed structure.”

The main principle supporting a mechanic’s lien for material sold and delivered to the contractor, as against the owner of the structure, is that the owner has set in operation a contract for an improvement which results in enhancing the value of his premises. Although there is a lack of privity of contract between the owner of the premises and the materialman who furnished material to the builder, under a contract with the latter, it is said that the benefits accruing to the owner, through the enhancement of his premises, will support the lien against his premises. The right of action between the materialman who furnishes material to the contractor as against the owner of the premises, does not rest upon a contract with the owner. The owner is held to liability on the mechanic’s lien filed by the materialman upon the principal that he has willingly accepted the value of labor and material in the enhancement of his premises, and ought to answer for the value thereof to the person contributing to his enrichment.

The surety company has cited the cases of Pittsburg Plate Glass Co. v. Leary (S. D.) 126 N. W. 271, Fuller v. Ryan (Wash.) 87 Pac. 485, and Shultz v. Quereau County (N. Y.) 104 N. E. 621, to support its contention that the material and labor must be used in the building. These were cases involving the right of the materialman to a lien as against the owner of the premises.

The structure involved in this case is a public building, and a mechanic’s lien would not run against the structure under any circumstances.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Casualty Company v. Town of Shattuck, Okl.
228 F. Supp. 834 (W.D. Oklahoma, 1964)
Nance v. Hester
1960 OK 72 (Supreme Court of Oklahoma, 1960)
United States Fidelity & Guaranty Co. v. Cagg
1937 OK 601 (Supreme Court of Oklahoma, 1937)
Sherman MacHine & Iron Works v. Iverson Specialty Co.
1935 OK 473 (Supreme Court of Oklahoma, 1935)
Southern Surety Co. v. Dolese Bros. Co.
1931 OK 254 (Supreme Court of Oklahoma, 1931)
Eagle Oil Co. v. Altman
1928 OK 66 (Supreme Court of Oklahoma, 1928)
Chicago Bridge & Iron Works v. Walker
1926 OK 813 (Supreme Court of Oklahoma, 1926)
Fuller v. Brooks
1926 OK 190 (Supreme Court of Oklahoma, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
1925 OK 468, 239 P. 154, 111 Okla. 208, 1925 Okla. LEXIS 471, Counsel Stack Legal Research, https://law.counselstack.com/opinion/federal-surety-co-v-st-louis-structural-steel-co-okla-1925.