Pittsburg Plate Grass Co. v. Leary

126 N.W. 271, 25 S.D. 256
CourtSouth Dakota Supreme Court
DecidedMarch 30, 1910
StatusPublished
Cited by18 cases

This text of 126 N.W. 271 (Pittsburg Plate Grass Co. v. Leary) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittsburg Plate Grass Co. v. Leary, 126 N.W. 271, 25 S.D. 256 (S.D. 1910).

Opinion

WHITING, P. J.

This is an action brought by the plaintiff, as subcontractor, against the contractors, joined as defendants with the owner of a.building erected by such contractors, for the erection of which building the plaintiff claimed to have furnished certain glass. The plaintiff demanded, in its complaint, personal judgment against the contractors as well as foreclosure of plaintiff’s mechanic’s lien against the building and land upon which the same rested. The contractors were not personally served with summons in the state and did not answer. Upon the trial, as [259]*259between the plaintiff and owner of the property, which trial was before tile court without a jury, the court made certain findings of fact and conclusions of law, and rendered judgment in accordance with same. Both parties having moved for a new trial, the same was denied, and both parties are appealing to this court from the judgment and order denying a new trial.

The findings of fact are quite voluminous, and exceptions are taken to some of them. In the view which we take of this case, it is unnecessary to refer to any facts except such as appear undisputed, and which are as follows: The contractors entered mto a contract, whereby the3 were to erect a business block for their codefendant, which said block was to be finished on or before December i, 1901. The contractors also entered into a contract with the plaintiff company, under which the plaintiff agreed to furnish the glass for said building. During" October and November, 1901, the plaintiff shipped to the contractors three shipments of glass; the first and largest including three large plate glass. Two plates cf this glass were broken into fragments before they reached the building, and they never entered into the construction of same. The second shipment was a small one, and the third shipment was of two plates of glass to> take the place of the two plates that were broken. It is undisputed that all of the glass so shipped, except the two plates broken, entered into the construction of the building. No dispute as to the value of said glass was raised, and it appears that the glass which went into the building was of the value of $1,090.57, and the two broken plates of the value of $588.94. The above glass not being paid for, the subcontractor, within the time fixed by statute, filed in the proper office a mechanic’s lien with the necessary statements thereto attached, under which instrument the plaintiff claimed a lien for the value of all the glass furnished to the contractors. Such lien was filed under the provisions • of sections 696 and 697 of the Revised Code of Civil Procedure. Said mechanic’s lien was dated March x, 1902, and in said, lien the plaintiff claimed a balance due of $1,679.51 without interest, claiming the above amount to be due on said March 1, 1902, which said amount, it will be noted, is the sum of the value of the glass used and that [260]*260broken. Thereafter, and on June 22, 1902, the defendant tendered to the plaintiff $1,112.31 in payment and satisfáction of such mechanic’s lien, but tendered the same on condition that said lien be satisfied and discharged in full. This tender was refused on the terms under which made, and the defendant afterwards, and before this action was brought, deposited the money in a bank with the notice that same could be obtained upon delivery to said bank of a discharge of 'such lien and of all claims against such defendant. Plaintiff attempted to check this money out of the bank, but did not tender a release of the lien, and the bank refused to'pay the money; the plaintiff offering only to receive the money and apply same on the claim and partially discharge lien. The court further found that the money due plaintiff from contractors bore interest from the xst of December, 1901, and that the same, with such interest, was secured by the lien filed.

As conclusions of law the court held there was due from the contractors to the plaintiff said sum of $1,090.57, with interest thereon from December x, 1901, and that the plaintiff was entitled to collect the said sum and interest by foreclosure of the hen and sale of the property. It will be seen that the court held against the plaintiff upon its claim of a right to a lien for the value of the glass broken, and it is from this holding that the plaintiff appeals. It will be seen that the court granted plaintiff a lien for the value of the glass, other than the broken glass, together with interest thereon from December 1, 1901; the effect of this holding of the court being to render the tender made by defendant insufficient, because the amount due, with interest from December ist, would be greater than the amount tendered, while the amount due, with interest from March ist,- would be less than the amount tendered. The court held that such tender did not stop the running of interest nor destroy the lien. It is from this part of the decree that the defendant appeals.

Did the court hold correctly, wherein it held that no lien could be claimed for material furnished for, but which did not enter into, the construction of the building? Upon this question the courts differ, and numerous authorities are to be found upon either side. Two classes of merchanic’s lien laws are in force in [261]*261this country. One belongs to what is known as the “New York system,” under which the lien of a 'subcontractor depends upon, and is limited by, the amount remaining due the contractor at the time of, or which may become due after, the service upon the owner by subcontractor of notice that he has already furnished, or is about to furnish, labor and material for the structure to be erected. Such a statute is to be found in sections 699, 700, and 701 of the Revised Code of Civil Procedure of this state. The other class belongs to what is known as the “Pennsylvania system,” under which the right of the subcontractor to a lien does not de-pend at all upon the existence of any indebtedness due from the owner to the contractor. Such a statute is found in our sections 696 and 697 of the Revised Code of Civil Procedure, and it is under these sections that the plaintiff filed his lien. Under the sections last above referred to, the subcontractor becomes entitled to a lien, not by virtue of any contract between himself and the owner of the land, creating any personal liability on the part of the owner, not by virtue of any implied agency on the part of the contractor, under which such contractor is held to have the right and authority to render the owner personally liable to pay for the labor or material furnished to the contractor, but, instead of resting upon such personal liability of the owner, it rests upon the theory that, the subcontractor having furnished, under a contract with contractor so to do, certain labor or material which has entered into the erection or construction of the improvement to the owner’s real estate, by virtue of which the owner has been benefited, the property should be holden for the payment of the value of the material or labor with which it has been benefited, and should be so holden for a reasonable length of time after such labor or material has been furnished. While there are numerous cases holding that the owner’s property should be liable for all labor or material furnished to the contractor for the erection or construction of the improvements, whether or not such labor or material actually goes into such improvements, which rule relieves the subcontractor of any duty or responsibility in following his material and seeing.to it that it is actually used as agreed, yet we are satisfied that the better rule — one founded upon better reason [262]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stromberger Farms, Inc. v. Johnson
942 N.W.2d 249 (South Dakota Supreme Court, 2020)
Anderson v. Aesoph
2005 SD 56 (South Dakota Supreme Court, 2005)
Schmidt v. Iowa Beef Processors, Inc.
347 N.W.2d 897 (South Dakota Supreme Court, 1984)
Dougherty v. Beckman
347 N.W.2d 587 (South Dakota Supreme Court, 1984)
Bauer v. Uniroyal Tire Co.
630 F.2d 1287 (Eighth Circuit, 1980)
State Ex Rel. Farmers State Bank v. Ed Cox & Son
132 N.W.2d 282 (South Dakota Supreme Court, 1965)
Smith v. Widmann Hotel Co.
49 N.W.2d 301 (South Dakota Supreme Court, 1951)
Bluefield Supply Co. v. M. P. Smith Construction Co.
177 S.E. 296 (West Virginia Supreme Court, 1934)
Niland v. Gill
99 Pa. Super. 107 (Superior Court of Pennsylvania, 1930)
J. F. Anderson Lumber Co. v. National Surety Co.
207 N.W. 53 (South Dakota Supreme Court, 1926)
Federal Surety Co. v. St. Louis Structural Steel Co.
1925 OK 468 (Supreme Court of Oklahoma, 1925)
Boise Lumber Co. v. Independent School District
214 P. 143 (Idaho Supreme Court, 1923)
Erickson v. Thelin
128 N.W. 598 (South Dakota Supreme Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
126 N.W. 271, 25 S.D. 256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittsburg-plate-grass-co-v-leary-sd-1910.