Dougherty v. Beckman

347 N.W.2d 587, 1984 S.D. LEXIS 288
CourtSouth Dakota Supreme Court
DecidedApril 25, 1984
Docket14018, 14026
StatusPublished
Cited by30 cases

This text of 347 N.W.2d 587 (Dougherty v. Beckman) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dougherty v. Beckman, 347 N.W.2d 587, 1984 S.D. LEXIS 288 (S.D. 1984).

Opinions

BERNDT, Circuit Judge.

CASE HISTORY

This action arose from a disagreement over the price of a townhouse constructed by defendants for plaintiff. Construction was completed May 3, 1981, and plaintiff tendered defendants $172,739 as full payment for thei townhouse. Defendants returned the tender. Plaintiff filed a complaint on July 1, 1981, asking for a permanent injunction enjoining defendants from disposing of the townhouse except through a warranty deed to him during the penden-cy of the action. Plaintiff requested an order for specific performance ordering defendants to convey real property to plaintiff in exchange for $172,739. Defendants counterclaimed, asking that the contract between the parties be rescinded and that defendants be awarded interest on the money they had used to build the townhouse. In the alternative, defendants asked that plaintiff be required to pay $202,195.93, plus interest thereon from April 17, 1981, if the court granted specific performance.

After trial, the court decided that plaintiff should be allowed to complete the purchase of the townhouse for a total of $196,-400. It found that plaintiff paid a total of $28,400 and tendered an additional amount of $144,339, totaling $172,739. The court found that the tender was refused and the money returned to plaintiff on June 12, 1981. The trial court held that this tender stopped the interest on this amount from June 12, 1981, but that interest on the difference of $23,661 should be paid from June 12, 1981, to the date of final payment, and that total payment would be a condition precedent to the requirement of specific performance. The court also provided that failure to make the required payment within a specified time would constitute a forfeiture and would terminate any interest plaintiff had under the contract, or otherwise.

After the trial plaintiff paid to defendants $200,995, which was the Court’s purchase price of $196,400, plus interest on $23,661 of the purchase price from June 12, 1981, to date of payment. The defendants conveyed the property to plaintiff. Defendants then filed a notice of appeal and plaintiff filed a notice of review. The de[589]*589fendants appealed only the issue of whether the trial court erred in denying them recovery of pre-judgment interest on $172,-739. Plaintiffs notice of review asked the Court to review the purchase price set by the trial court for specific performance.

FACTS

In a contract executed in 1977 with plaintiff, defendants agreed to construct a townhouse in Sioux Falls, South Dakota, “to be finished, according to specifications and plans, designated as Plan No. 9-19.” The purchase price agreed upon was $142,000. The contract states that no extras are included in the contract price unless they are set forth in the contract. The only extras to be included in the townhouse plaintiff contracted for, were set forth in an Addendum to the contract.

Two years later plaintiff hired architect Ward Whitwam to incorporate changes he wished to make to the original floor plan. In January, 1980, Whitwam made additional changes in the floor plan of the townhouse. These revisions included major structural changes, such as adding an additional 12 percent in interior wall partitions, requiring double framing in some areas, adding an additional 112 square feet of living area, finishing off the entire basement area, adding additional windows and, finally, adding additional sliding doors.

Defendants were not willing to construct the townhouse with these major revisions for the price stated in the original contract. Defendant Carlson, therefore, wrote a letter to plaintiff on February 27, 1980 (the February 27th letter), telling plaintiff that they would construct the townhouse according to the revised plans and information they had as of that date for $180,000. In the alternative, defendant Carlson told plaintiff that defendants would be willing to return plaintiff’s deposit and pay the architectural fees he had incurred.

Pursuant to defendant Carlson’s letter, a meeting was held at attorney John Burke's office. The purpose of the meeting was to discuss defendant Carlson’s letter of February 27, 1980. Plaintiff apparently agreed to accept the terms of the February 27th letter. Defendant Beckman noted this acceptance on the bottom of his copy of defendant Carlson’s letter.

Plaintiff made even more revisions to the floor plan for the townhouse on July 25, 1980, and October 14, 1980. In addition, plaintiff, or his wife, requested that numerous extras be added to the townhouse. All of these items were included in the townhouse when it was completed and ready for occupancy April 17, 1981. Several dates for finalizing the transfer of the property were set and cancelled by plaintiff for one reason or another. Defendant Beckman and plaintiff finally met on May 3, 1981, to close the transaction. Plaintiff refused to pay the $202,195.93 demanded by defendants for the completed townhouse but, instead, offered defendants $172,739 as full payment. Plaintiff’s offer was refused and all the money he had paid to defendants was returned to him on June 12, 1981.

DISCUSSION

The two issues requiring resolution are:

(1) The price of the townhouse

(2) The award of pre-judgment interest

The Price of the Townhouse

Plaintiff’s brief concedes that the central issue in the case is the amount owed by plaintiff to defendants for the construction work. The major dispute is whether the $142,000 figure delineated in the contract is binding or whether the $162,500 sum, as quoted in the February 27th letter, controls this case. The trial court held that the latter sum was correct.

The contract provides guidance. The pivotal language is:

Which property the undersigned, as agent for the owner, has this day sold to the buyer for the sum of $142,000 ... Included in the above price are the following extras: (none, if not set forth) $142,000 will be the ceiling price of the home. If selling price comparable to # 9 floor plan is less — the price will be adjusted accordingly. Any minor changes [590]*590will be included in the price of home — but large structural changes could effect [sic] the price of the home.

After defendants began construction, plaintiff insisted upon substantial revisions which greatly increased the cost of construction. Thereafter, defendants sent the February 27th letter advising that “[w]e are willing to complete your townhouse for the sum of $162,500 ...”. Defendants contend that plaintiff adopted this letter and its $162,500 figure or, in the alternative, that the contractual caveat of “large structural changes ... effecting] [sic] the price” justifies not applying the $142,000 price. Under either the original contract or the February 27th letter, defendants appear entitled to the higher sum ($162,500). Considering first the contract, it is crucial that defendants included as part of the agreement that, along with a $142,000 price tag, “large structural changes could effect [sic] the price of the home.” Whatever the full breadth of the phrase “large structural changes” may be, it would certainly seem to embrace the substantial revisions to the original floor plan plaintiff demanded. Plaintiffs consent to the contractual language now precludes any black letter reading of the $142,-000. Therefore, the trial court’s decision to award the higher figure was correct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stromberger Farms, Inc. v. Johnson
942 N.W.2d 249 (South Dakota Supreme Court, 2020)
Buffalo Ridge Corp. v. Lamar Advertising of South Dakota, Inc.
2011 S.D. 4 (South Dakota Supreme Court, 2011)
Berbos v. Krage
2008 SD 68 (South Dakota Supreme Court, 2008)
Anderson v. Aesoph
2005 SD 56 (South Dakota Supreme Court, 2005)
Adrian v. McKinnie
2004 SD 84 (South Dakota Supreme Court, 2004)
Century 21 Associated Realty v. Hoffman
503 N.W.2d 861 (South Dakota Supreme Court, 1993)
Matter of Estate of Gibbs
490 N.W.2d 504 (South Dakota Supreme Court, 1992)
Ducheneaux v. Miller
488 N.W.2d 902 (South Dakota Supreme Court, 1992)
Mash v. Cutler
488 N.W.2d 642 (South Dakota Supreme Court, 1992)
Matter of Hughes Cty. Action No. Juv 90-3
452 N.W.2d 128 (South Dakota Supreme Court, 1990)
Heer v. State
432 N.W.2d 559 (South Dakota Supreme Court, 1988)
South Dakota Building Authority v. Geiger-Berger Associates, P.C.
414 N.W.2d 15 (South Dakota Supreme Court, 1987)
Associated Press v. Bradshaw
410 N.W.2d 577 (South Dakota Supreme Court, 1987)
Varilek v. Charles Mix Electric Ass'n
409 N.W.2d 117 (South Dakota Supreme Court, 1987)
Hageman v. Vander Vorste
403 N.W.2d 420 (South Dakota Supreme Court, 1987)
Amert v. Ziebarth Construction Co.
400 N.W.2d 888 (South Dakota Supreme Court, 1987)
Barton Masonry, Inc. v. Varilek
375 N.W.2d 200 (South Dakota Supreme Court, 1985)
Cargill, Inc. v. Elliott Farms, Inc.
363 N.W.2d 212 (South Dakota Supreme Court, 1985)
Gross v. Connecticut Mutual Life Insurance Co.
361 N.W.2d 259 (South Dakota Supreme Court, 1985)
Williams Insurance Agency, Inc. v. Dee-Bee Contracting Co.
358 N.W.2d 231 (South Dakota Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
347 N.W.2d 587, 1984 S.D. LEXIS 288, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dougherty-v-beckman-sd-1984.