Northwestern Engineering Co. v. Thunderbolt Enterprises, Inc.

301 N.W.2d 421, 1981 S.D. LEXIS 204
CourtSouth Dakota Supreme Court
DecidedJanuary 28, 1981
Docket13090
StatusPublished
Cited by22 cases

This text of 301 N.W.2d 421 (Northwestern Engineering Co. v. Thunderbolt Enterprises, Inc.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwestern Engineering Co. v. Thunderbolt Enterprises, Inc., 301 N.W.2d 421, 1981 S.D. LEXIS 204 (S.D. 1981).

Opinions

DUNN, Justice.

This is an appeal from a judgment entered in favor of Northwestern Engineering Company (Northwestern) in the amount of $51,015.00, plus prejudgment interest of $11,403.02, plus costs of $834.67, against Thunderbolt Enterprises, Inc. (Thunderbolt), with an offset to Thunderbolt in the amount of $12,200.00. We affirm in part, reverse in part, and remand with directions to enter a judgment consistent with this opinion.

[422]*422On September 25, 1973, Thunderbolt and Lakota Enterprises (Lakota) entered into a written subcontract agreement dealing with the horizontal or groundwork construction of a residential construction project on the Cheyenne River Indian Reservation. Northwestern was engaged as the indemnitor on the performance bond. During November of 1973 Lakota commenced work under this contract. Lakota became insolvent during the winter of 1973.

Thunderbolt then requested that Northwestern, as indemnitor of the performance bond, assume performance of the subcontract. Northwestern began performance under the Lakota-Thunderbolt subcontract. A disagreement arose regarding the scope of the work to be performed by Northwestern. Northwestern refused to perform certain tasks, claiming that the extent of the work was limited by a three-page document attached to the subcontract. This document is typed on Lakota letterhead and is currently attached to the subcontract. The substance of this three-page document is an itemized list of unit prices, total prices, and the type of tasks involved. Furthermore, the document contains a qualification at the bottom of the last two pages stating that, “[t]his quote includes only the above quantities.”

The trial court made a finding of fact that the three-page document was attached to the subcontract at the time of its execution, thereby limiting Northwestern’s obligation to those items listed in the three-page document. The trial court then unex-plainably granted a $12,200.00 offset to Thunderbolt for an item listed as yardwork, which is found only in the body of the subcontract and is absent from the three-page document.

This brings us to the first issue raised by Thunderbolt on appeal. Did the trial court err in finding that the three-page document was attached to and a part of the subcontract?

The standard to be applied in reviewing the trial court’s findings of fact is:

On review, the successful party is entitled to the benefit of his version of the evidence and of all inferences fairly deducible therefrom which are favorable to the court’s action .... “Findings of fact shall not be set aside unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge of the credibility of the witnesses.” ...
... The question is not whether this court would have made the same findings that the trial court did, but whether on the entire evidence we are left with a definite and firm conviction that a mistake has been committed ....

Cunningham v. Yankton Clinic, P. A., 262 N.W.2d 508, 512 (S.D.1978) (citations omitted).

We hold that the trial court did not err in finding that the three-page document was attached at the time of the execution of the subcontract and that the finding is not clearly erroneous. Because of the voluminous nature of the record, we shall list only a modicum of the evidence which supports this finding.

The trial court had before it testimony of a signatory of the contract that the three-page document was part of the subcontract at the time of the execution. This testimony was as follows:

Q [Mr. Carpenter]: Now, calling your attention particularly to the three sheets, typewritten sheets that are on Lakota Enterprises, Inc. stationery, were those a part of the subcontract at the time you executed it?
A [Mr. Swan]: Yes, they were.

Swan then went on to testify that it was clearly understood by all parties that only the items set out in this three-page document were being subcontracted for. Furthermore, there was testimony that the customary method of identifying the scope of the work that was bid upon was by attachment of a unit-price breakdown, similar to what was done here. The subcontract itself contemplates the attachment of exhibits by providing in Article I thereof that: “The contract Documents for this Subcontract consist of this Agreement and any exhibits attached hereto ...” Finally, the three-[423]*423page document was present when the subcontract was filed with the director of the Cheyenne River Housing Authority.

In summation, we hold that even though we may or may not have reached the same findings of fact as were reached by the trial court, we are not left with a firm and definite conviction that a mistake has been committed and that these findings as they relate to the three-page document are clearly erroneous.

The next issue raised by Thunderbolt upon appeal is whether any ambiguities in the subcontract should have been construed against the drafter.

We are cognizant of the general rule “ ‘... where an ambiguous contract exists, it should be interpreted more strongly against one who drafted the contract and caused the uncertainty to exist.’ ” Delzer Const. Co. v. South Dakota State Bd., 275 N.W.2d 352, 357 (S.D.1979). This issue, however, does not appear to have been presented or argued to the trial court. Thus, as we stated in Chipperfield v. Woessner et al, 84 S.D. 13, 19, 166 N.W.2d 727, 730 (1969): “Since our function is that of review, issues not presented to the trial court are not before us on appeal.” Even if this issue was properly before us, the record does not disclose who drafted the subcontract. Without knowing who is the scrivener, neither we nor the trial court could apply this rule of construction.

We now turn to the only issue raised by Northwestern’s notice of review: Whether Thunderbolt was properly granted an offset of $12,200.00 for yardwork. The trial court’s Findings of Fact state:

8. That under the terms of the subcontract agreement Lakota Enterprises, Inc. was to perform an item designated as yardwork, Item 54, on the Form 51000 which included the installation and furnishing of clothesline poles, garbage rack holders and stair railings.
9. That Northwestern Engineering Company did not perform the yardwork and Defendant Thunderbolt Enterprises, Inc. is therefore entitled to an offset for that item in the sum of Twelve Thousand Two Hundred Dollars ($12,200.00).

Those items listed as yardwork may only be found through a meticulous tracing of oblique references to plans and drawings made in specification section 0270 of Article II of the subcontract and then by way of another painstaking trek through reams of plans and drawings, these items listed as yardwork appear. The yardwork items, however, are omitted from the three-page document.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SDDS, Inc. v. State
502 N.W.2d 852 (South Dakota Supreme Court, 1993)
King County v. Puget Sound Power & Light Co.
852 P.2d 313 (Court of Appeals of Washington, 1993)
South Dakota Building Authority v. Geiger-Berger Associates, P.C.
414 N.W.2d 15 (South Dakota Supreme Court, 1987)
Hageman v. Vander Vorste
403 N.W.2d 420 (South Dakota Supreme Court, 1987)
Valloric v. Dravo Corp.
357 S.E.2d 207 (West Virginia Supreme Court, 1987)
Buhl v. Bak
400 N.W.2d 903 (South Dakota Supreme Court, 1987)
Amert v. Ziebarth Construction Co.
400 N.W.2d 888 (South Dakota Supreme Court, 1987)
Barton Masonry, Inc. v. Varilek
375 N.W.2d 200 (South Dakota Supreme Court, 1985)
Bethel v. Janis
597 F. Supp. 56 (D. South Dakota, 1984)
American State Bank v. List-Mayer
350 N.W.2d 44 (South Dakota Supreme Court, 1984)
Dougherty v. Beckman
347 N.W.2d 587 (South Dakota Supreme Court, 1984)
Jandreau v. Sheesley Plumbing & Heating Co.
324 N.W.2d 266 (South Dakota Supreme Court, 1982)
Golden v. Oahe Enterprises, Inc.
319 N.W.2d 493 (South Dakota Supreme Court, 1982)
Northwestern Engineering Co. v. Thunderbolt Enterprises, Inc.
301 N.W.2d 421 (South Dakota Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
301 N.W.2d 421, 1981 S.D. LEXIS 204, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwestern-engineering-co-v-thunderbolt-enterprises-inc-sd-1981.