Beka v. Lithium Corporation of America

92 N.W.2d 156, 77 S.D. 370, 1958 S.D. LEXIS 27
CourtSouth Dakota Supreme Court
DecidedSeptember 16, 1958
DocketFile 9697
StatusPublished
Cited by57 cases

This text of 92 N.W.2d 156 (Beka v. Lithium Corporation of America) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beka v. Lithium Corporation of America, 92 N.W.2d 156, 77 S.D. 370, 1958 S.D. LEXIS 27 (S.D. 1958).

Opinion

RENTTO, P. J.

The plaintiff partnership instituted this action on August 19, 1957, to recover damages from the defendant corporation caused by its 'breach of a contract. On trial to a jury the court directed a verdict for plaintiff in the sum of $3,000 and allowed a recovery of interest from the first day of the month after the breach. Defendant appeals from the judgment entered on this verdict.

The Lithium Corporation had contracted to furnish the Maywood Chemical Works with specified quantities and types of lithium. That contract gave to the Lithium Corporation the right to remove lithium ores from an old waste dump at a .mine owned by the Chemical Works and treat it at a mill owned by the Lithium Corporation. They were to remove a minimum of 100 tons a day of materials that would pass through a one and one-half inch screen. To accomplish this it was necessary that the material at the dump be screened and those portions thereof small enough to go through the screen loaded on trucks and hauled to and dumped at the mill, which was about eight-tenths of a mile away.

By the contract here involved the Lithium Corporation subcontracted this work to the plaintiff partnership. The partnership contracted to screen the materials in this dump and deliver daily to the Lithium Corporation at its mill 100 tons of the screened material. For this service it was to receive $3.50 per ton to be paid on monthly billings. Performance by the partnership was begun in January 1954. The contract stipulated that the partnership would continue this service until March 31, 1955. The *372 Lithium Corporation reserved the right to terminate the contract on ten days’ written notice to the partnership.

In addition to delivering the required daily tonnage the partnership accumulated a stockpile of screened material from which to secure the daily requirement in the event of a 'breakdown in its operation. On June 17, 1954, without prior written notice, the defendant terminated the contract. At that time the partnership had in its stockpile 1,500 tons of screened ore. This action is predicated on the theory that if the ten days’ notice had been given, as agreed in the contract, the partnership during the period remaining before such notice became effective would have delivered to the Lithium Corporation another 1,000 tons of ore from its stockpile at $3.50 per ton. In its complaint it asks for $3,000 as damages with interest from July 1, 1954.

The record discloses that at the time this contract was entered into and during the time it was performing its obligations thereunder, plaintiff partnership had not filed the statement required by our fictitious name statute SDC 49.08. However, it did file the statement on April 15, 1957. This was almost three years after the contract was terminated and about four months before the institution of this action. This dereliction is the basis of the principal defense urged by the defendant.

In brief, it argues that since SDC 49.0801 makes it unlawful for a partnership to engage in or conduct a business for profit under a name which does not plainly show the true surname of each person interested in the business without filing the described statement, that the contract here involved is invalid and unenforceable. This contention was before us recently in Mellgren Plumbing Shop, Inc., v. Lewis and Tinsley, Inc., 77 S. D. 193, 90 N. W. 2d 78. The opinion in that case, which was handed down a short time after oral argument was heard in this case, forecloses the view here urged. It was there held that contracts entered into or performed under such circumstances are valid. Since the statement required by SDC 49.0801 was filed before the institution of this litigation, the plaintiff partnership is authorized by SDC 49.0802 to maintain this action.

*373 The second reason urged by the defendant corporation for reversal is that the court should not have withdrawn from the jury the determination of the amount of detriment suffered by plaintiff. The $3,000 asked as damages was arrived at by deducting from the $3,500 which the Lithium Corporation would have paid under the agreement for the 1,000 tons the partnership would have delivered in the ten-day period, which was taken from it by defendant’s failure to give the ten days’ notice, the cost of loading it at the stockpile and hauling it to the mill.

On this element the only evidence in the record is that given by one of the members of the plaintiff partnership. His testimony was that the going price for this service was about 50^ a ton. The defendant does not seem to question the accuracy of this testimony. It does, however, contend that the matter should have been submitted to the jury because the jurors were privileged to believe this testimony or not as they saw fit, or to draw such inferences from it as they thought justified. We think the court’s action in this regard was in keeping with the rule laid down by this court in Jerke v. Delmont State Bank, 54 S.D. 446, 223 N.W. 585, 594, 72 A.L.R. 7.

In that case this court wrote about the duty of the trial court to direct a verdict in a jury case in which the testimony on behalf of the proponent was undisputed. Speaking through Campbell, Judge, it said:

“* * * the rule of reasonable judgment must be applied to each case upon its particular facts, and, if the testimony in behalf of the party having the burden of proof is clear and full, not extraordinary or incredible in the light of general experience, and not contradicted, either directly or indirectly, by other witnesses or by circumstances disclosed, and is so plain and complete that disbelief therein could not arise by rational processes applied to the evidence, but would be whimsical or arbitrary, then, and in such case, it is not only permissible, but highly proper, to direct the verdict, and the direction of such verdict should not be *374 prevented merely by reason of the fact that one or more of the witnesses are interested in the transaction or the result of the suit.”

In Yol. IX, Wigmore on Evidence, 3d Edition, § 2495, p. 305, it is written that this view is accepted by the majority of courts. That authority quotes liberally from the opinion in the Jerke case and says that it “convincingly éxpounds the correct principle with inexorable logic.”

In Crilly v. Fitzsimmons, 73 S.D. 646, 48 N.W.2d 62, this court not only approved the rule in the Jerke case but made it the measure of the duty of the trial court in entering findings in an equity case under similar circumstances. Defendant supports its position by citation of Crilly v. Morris, 70 S.D. 584, 19 N.W.2d 836 and Jorgenson v. Jorgenson, 74 S.D. 239, 51 N.W.2d 632. These cases are not concerned with verdicts directed by the trial court. Rather, in the connection cited, they are authority for the proposition that the trier of facts is not bound by uncontradicted testimony which is grossly improbable.

The Jerke case did not overlook the factor of the credibility as it enters into the direction of a verdict. It is there written:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Honomichl v. Modlin
477 N.W.2d 599 (South Dakota Supreme Court, 1991)
Clements v. Gabriel
472 N.W.2d 480 (South Dakota Supreme Court, 1991)
Jensen Ranch, Inc. v. Marsden
440 N.W.2d 762 (South Dakota Supreme Court, 1989)
Heer v. State
432 N.W.2d 559 (South Dakota Supreme Court, 1988)
South Dakota Building Authority v. Geiger-Berger Associates, P.C.
414 N.W.2d 15 (South Dakota Supreme Court, 1987)
Hageman v. Vander Vorste
403 N.W.2d 420 (South Dakota Supreme Court, 1987)
Amert v. Ziebarth Construction Co.
400 N.W.2d 888 (South Dakota Supreme Court, 1987)
Barton Masonry, Inc. v. Varilek
375 N.W.2d 200 (South Dakota Supreme Court, 1985)
Hanson v. Funk Seeds International
373 N.W.2d 30 (South Dakota Supreme Court, 1985)
Subsurfco, Inc. v. B-Y Water District
369 N.W.2d 129 (South Dakota Supreme Court, 1985)
Cargill, Inc. v. Elliott Farms, Inc.
363 N.W.2d 212 (South Dakota Supreme Court, 1985)
Johnson v. Skelly Oil Co.
359 N.W.2d 130 (South Dakota Supreme Court, 1984)
Williams Insurance Agency, Inc. v. Dee-Bee Contracting Co.
358 N.W.2d 231 (South Dakota Supreme Court, 1984)
American State Bank v. List-Mayer
350 N.W.2d 44 (South Dakota Supreme Court, 1984)
Arcon Construction Co. v. South Dakota Cement Plant
349 N.W.2d 407 (South Dakota Supreme Court, 1984)
Dougherty v. Beckman
347 N.W.2d 587 (South Dakota Supreme Court, 1984)
Fullerton Lumber Co. v. Reindl
331 N.W.2d 293 (South Dakota Supreme Court, 1983)
The Maryland v. Sandidge
652 F.2d 8 (Eighth Circuit, 1981)
Northwestern Engineering Co. v. Thunderbolt Enterprises, Inc.
301 N.W.2d 421 (South Dakota Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
92 N.W.2d 156, 77 S.D. 370, 1958 S.D. LEXIS 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beka-v-lithium-corporation-of-america-sd-1958.