Arcon Construction Co. v. South Dakota Cement Plant

349 N.W.2d 407, 38 U.C.C. Rep. Serv. (West) 1481, 1984 S.D. LEXIS 295
South Dakota Supreme Court·Decided May 2, 1984·No. 14139, 14140, 14147 and 14148·Published·Cited by 61 cases

Opinions

DUNN, Justice

(on reassignment).

The South Dakota Cement Plant and the South Dakota Cement Plant Commission (referred to collectively as “the cement plant”) appeal a judgment entered against them for their breach of two contracts for the sale of cement to Arcon Construction Co., Inc. (Arcon). We affirm in part, reverse in part, and remand.

The first contract at issue here involved the sale of cement to Arcon for a project on Interstate 29 north of Watertown, South Dakota. The other contract involved the sale of cement for Arcon’s paving project on Highway 281 near Aberdeen, South Dakota. Both contracts called for the delivery of cement during construction year 1978. However, due to a severe cement shortage in 1978, the cement plant failed to deliver the cement as called for under the contracts. As a result, Arcon was not able to perform work on the projects until the 1979 and 1980 construction seasons.

Arcon commenced its action for breach of contract on April 17, 1980; the cement plant counterclaimed for damages caused by Arcon’s failure to use certain amounts of cement which were delivered to Arcon. A jury trial began on October 6, 1982. After hearing the evidence and deliberating for eight days, the jury returned a verdict for Arcon in the amount of $1,175,974.00, and a verdict for the cement plant in the amount of $89,089.00 on its counterclaim.

Numerous issues are raised by the parties in this appeal, including the following: 1) Is Arcon’s lawsuit barred by the principle of sovereign immunity? 2) Is Arcon’s lawsuit barred by the running of the statute of limitations? 3) Did the trial court properly instruct the jury as to the cement plant’s contractual and statutory defenses? 4) Did the trial court properly instruct the jury as to the proper measure of damages for contractor-owned idle equipment? 5) Did the trial court abuse its discretion when it taxed costs against the cement plant? 6) Is Arcon entitled to prejudgment [410] interest on the damages awarded by the jury?

I

The threshold question in this appeal is whether the doctrine of sovereign immunity extends to the cement plant. Article III, section 27 of the South Dakota Constitution provides: “The Legislature shall direct by law in what manner and in what courts suits may be brought against the state.” Accordingly, we have consistently held that it is the exclusive province of the legislature and not the courts to abrogate or limit the doctrine of sovereign immunity. In the absence of an express statutory waiver, we strictly adhere to this constitutionally mandated doctrine. Kringen v. Shea, 333 N.W.2d 445 (S.D.1983); Merrill v. Birhanzel, 310 N.W.2d 522 (S.D.1981); High-Grade Oil Co., Inc. v. Sommer, 295 N.W.2d 736 (S.D.1980); Arms v. Minnehaha County, 69 S.D. 164, 7 N.W.2d 722 (1943).

The cement plant is clearly an arm of the state. Article XIII, section 10 of the South Dakota Constitution declares that the manufacture, distribution, and sale of cement and cement products is a function of state government. Not only is such activity for a public purpose, Eakin v. South Dakota State Cement Commission, 44 S.D. 268, 183 N.W. 651 (1921); In re Opinion of the Judges, 43 S.D. 648, 180 N.W. 957 (1920), but, when this cause of action arose in 1978, SDCL 5-17-2.1 specifically provided: “The state cement commission and the state cement plant under its control shall comprise a principal department of state government.” * It follows that in pursuing its cement plant operation, the state retains its sovereign status.

Even though the cement plant is an arm of the state, Arcon argues that the legislature has waived immunity for suits arising out of cement plant contracts, especially those within the scope of the Uniform Commercial Code (UCC), SDCL title 57A. The trial court reached a waiver of immunity conclusion under a non-UCC theory based on statutory construction and constitutional interpretation. We do not reach all the waiver of immunity considerations noted by the trial court. We do find, however, for the following reasons, that when the legislature enacted the UCC it expressly waived sovereign immunity for the cement plant whenever the cement plant enters into contracts for the sale of goods.

First, all transactions in goods clearly fall within the provisions of UCC-Sales. SDCL 57A-2-102. The contracts which formed the basis for this lawsuit involved the sale of cement. Cement is “goods” under UCC-Sales. SDCL 57A-2-105(l). Consequently, the type of transaction engaged in between Arcon and the cement plant is governed by the UCC.

Second, the UCC provisions expressly apply to the state. In its general definitions, the UCC defines “organization” to include “government or governmental subdivision or agency.” SDCL 57A-1-201(28). Because it is a governmental agency, the cement plant is an organization within the meaning of the UCC. As an organization, the cement plant is a “person” under SDCL 57A-1-201(30), and, as a “person who sells or contracts to sell goods,” it is a “seller” within the context of UCC-Sales. SDCL 57A-2-103(l)(d). See Northern Helex Company v. United States, 455 F.2d 546 (Ct.Cl.1972), which applied UCC provisions to a sales contract between the federal government and a private company; and Shea-Kaiser-Lockheed-Healy v. Dept. of W. & P., Etc., 73 Cal.App.3d 679, 140 Cal. Rptr. 884 (1977), which held that a municipal water department was subject to the UCC in a sales transaction.

Third, the UCC grants a buyer specific rights and remedies against a breaching seller, and these rights include lawsuits. [411] When, prior to the first delivery, the cement plant informed Arcon that it would not be able to deliver the contracted fifteen carloads of cement per day, Arcon, as an aggrieved party whose contract had been substantially impaired in value, was empowered by SDCL 57A-2-610 to resort to any of the enumerated remedies for anticipatory repudiation. SDCL 57A-1-106(2) expressly permits an action to pursue these remedies: “Any right or obligation declared by this title is enforceable by action unless the provision declaring it specifies a different and limited effect.” The word “right” includes remedies. SDCL 57A-1-201(36). Therefore, Arcon was entitled to maintain an action against the cement plant to enforce UCC-Sales remedies which became available upon breach of the contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Arcon Construction Co. v. South Dakota Cement Plant, 349 N.W.2d 407, 38 U.C.C. Rep. Serv. (West) 1481, 1984 S.D. LEXIS 295 (S.D. 1984).

349 N.W.2d 407 (Arcon Construction Co. v. South Dakota Cement Plant) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lp6 v. S.D. Dept of Tourism
2020 S.D. 38 (South Dakota Supreme Court, 2020)
Excel Underground, Inc. v. Brant Lake Sanitary District
941 N.W.2d 791 (South Dakota Supreme Court, 2020)
Ford Contracting, Inc. v. Kentucky Transportation Cabinet
429 S.W.3d 397 (Court of Appeals of Kentucky, 2014)
Lewis v. South Dakota State Department of Transportation
2003 SD 82 (South Dakota Supreme Court, 2003)
Clouse Ex Rel. Clouse v. State
16 P.3d 757 (Arizona Supreme Court, 2001)
Clouse v. State
11 P.3d 1012 (Arizona Supreme Court, 2000)
Zahn v. Musick
2000 SD 26 (South Dakota Supreme Court, 2000)
Nelson v. Nelson Cattle Co.
513 N.W.2d 900 (South Dakota Supreme Court, 1994)
City of Sioux Falls v. Kelley
513 N.W.2d 97 (South Dakota Supreme Court, 1994)
In Re State & Municipal Sales & Use Tax Liability of K.O. Lee Co.
489 N.W.2d 606 (South Dakota Supreme Court, 1992)
United Fire & Casualty Co. v. P & C Insurance Services, Inc.
488 N.W.2d 661 (South Dakota Supreme Court, 1992)
Cody v. Leapley
476 N.W.2d 257 (South Dakota Supreme Court, 1991)
Clements v. Gabriel
472 N.W.2d 480 (South Dakota Supreme Court, 1991)
Deutz & Crow Co. v. South Dakota State Cement Plant Commission
466 N.W.2d 631 (South Dakota Supreme Court, 1991)
Magbuhat v. Kovarik
445 N.W.2d 315 (South Dakota Supreme Court, 1989)
Siefkes v. Watertown Title Co.
437 N.W.2d 190 (South Dakota Supreme Court, 1989)
Heer v. State
432 N.W.2d 559 (South Dakota Supreme Court, 1988)
Wolken v. Bunn
422 N.W.2d 417 (South Dakota Supreme Court, 1988)
South Dakota Building Authority v. Geiger-Berger Associates, P.C.
414 N.W.2d 15 (South Dakota Supreme Court, 1987)