Excel Underground, Inc. v. Brant Lake Sanitary District

941 N.W.2d 791, 2020 S.D. 19
CourtSouth Dakota Supreme Court
DecidedApril 1, 2020
Docket28580
StatusPublished
Cited by7 cases

This text of 941 N.W.2d 791 (Excel Underground, Inc. v. Brant Lake Sanitary District) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Excel Underground, Inc. v. Brant Lake Sanitary District, 941 N.W.2d 791, 2020 S.D. 19 (S.D. 2020).

Opinion

#28580-a-JMK 2020 S.D. 19

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

****

EXCEL UNDERGROUND, INC., Plaintiff and Appellee,

v.

BRANT LAKE SANITARY DISTRICT, Defendant and Appellant.

---------------------------------------------------------------------------------------------------------------------

BRANT LAKE SANITARY DISTRICT, Plaintiff and Appellant,

EXCEL UNDERGROUND, INC. & GRANITE RE, INC., Defendants and Appellees,

and

GRANITE RE, INC., Third-Party Plaintiff and Appellee,

REED I. OLSON & MELISSA D. FISCHER-OLSON, Third-Party Defendants.

APPEAL FROM THE CIRCUIT COURT OF THE THIRD JUDICIAL CIRCUIT LAKE COUNTY, SOUTH DAKOTA

THE HONORABLE PATRICK T. PARDY Judge

ARGUED FEBRUARY 20, 2019 OPINION FILED 04/01/20 ELIZABETH S. HERTZ VINCE M. ROCHE of Davenport, Evans, Hurwitz & Smith, LLP Sioux Falls, South Dakota

HEATHER M. LAMMERS BOGARD of Costello, Porter, Hill, Heisterkamp, Bushnell & Carpenter, LLP Rapid City, South Dakota

JEROME B. LAMMERS of Lammers Kleibacker, LLP Madison, South Dakota Attorneys for appellants.

DANIEL K. BRENDTRO Sioux Falls, South Dakota Attorney for appellee Excel Underground, Inc.

JOSEPH A. NILAN DAVID H. GREGERSON of Gregerson, Rosow, Johnson & Nilan, LTD Minneapolis, Minnesota

WILLIAM P. FULLER of Fuller & Williamson, LLP Sioux Falls, South Dakota Attorneys for appellee Granite Re, Inc.

GREGORY WHEELER of Boyce Law Firm, LLP Sioux Falls, South Dakota Attorneys for appellee Schmitz Kalda & Associates.

TODD MEIERHENRY of Meierhenry & Sargent, LLP Sioux Falls, South Dakota Attorneys for amicus curiae Dakota Homestead Title Insurance Company and South Dakota Conservancy District. #28580

KERN, Justice

[¶1.] In 2012, the Brant Lake Sanitary District (the District) contracted

with Schmitz, Kalda, and Associates, Inc. (SKA) to engineer a sewer system and

with Excel Underground, Inc. (Excel) to install it. After lengthy delays, the District

terminated Excel’s contract, and Excel and the District sued each other for breach of

contract. The District also sued Excel’s surety, Granite Re, Inc. (Granite). In

response, Granite filed a third-party complaint for contribution, reimbursement, or

indemnity against the owners of Excel—Reed Olson and Melissa D. Fischer-Olson.

Additionally, the District filed a third-party complaint against SKA for contribution

and indemnity.

[¶2.] Prior to trial, the court granted Excel’s motion to dismiss the District’s

claim for liquidated damages. The court also granted SKA’s motion for summary

judgment on the District’s third-party complaint against it and dismissed SKA from

the suit. However, the court denied the District’s motion for summary judgment

against Excel, and their claims against each other proceeded to a jury trial.

[¶3.] At the close of the evidence and over the District’s objection, the circuit

court instructed the jury that SKA served as the District’s agent. The court also

instructed the jury regarding the District’s statutory emergency bidding procedures.

The jury returned a verdict in favor of Excel, and the District unsuccessfully moved

for judgment notwithstanding the verdict or in the alternative, a new trial. The

District appeals. We affirm.

-1- #28580

Facts and Procedural History

[¶4.] The District is a public entity incorporated under the laws of the State

of South Dakota. In 2012, the District decided to install a wastewater collection

system (the Project) for residents near Chester, South Dakota, to replace individual

septic tanks for approximately 200 homes and cabins located around Brant Lake.

This low-pressure system was designed to take waste from each residence by a

gravity sewer pipe to an individual grinder pump to process the waste into slurry

for piping to a main line.

[¶5.] The Project required installation of two main-line branches

surrounding the Lake. The branches were designed to join into a single line on the

west side of the Lake, which would then drain into a sewage lagoon. To avoid

disturbing the ground surface, the plans called for most of the piping to be installed

using “directional boring” rather than open trenching. The District employed SKA

to engineer the Project and awarded Excel, the lowest bidder, the installation

contract. Granite issued a performance bond as a surety for Excel’s work. Reed

Olson, owner of Excel, and his wife Melissa Fischer-Olson, executed a general

agreement of indemnity, in which they agreed to hold Granite harmless for any loss

as a result of the bond.

[¶6.] Excel’s contract began on May 30, 2012. The parties agreed to a

December 30, 2012 deadline for substantial completion and a May 30, 2013 deadline

for final completion. The contract included a liquidated damages clause, which, by

its terms, attempted to anticipate the District’s damages if Excel delayed

completion of the Project beyond the agreed-upon dates. Further, the contract

-2- #28580

provided that in the event of a delay, the District could hire a third party to

complete the Project and recover the cost of completion from Excel.

[¶7.] The District issued a notice to proceed with construction on June 25,

2012. Delays in the construction schedule occurred almost immediately due to

difficult terrain and the late arrival of critical supplies. Excel’s president, Reed

Olson, sent a letter to the District expressing concerns about Excel’s ability to meet

the December 30, 2012 substantial completion date. He requested an extension

until May 31, 2013, with remaining cleanup to be completed in June. The District

denied this request. As construction continued, the parties disagreed regarding

change orders, payment schedules, Excel’s duty to supply troubleshooting services,

and the Project’s price. For example, changes in the construction plans—

specifically, the need to use open trenching around the residences in an area called

Spawn’s Addition rather than proceeding with directional boring—contributed to

the increased costs and delay. Issues also arose regarding selection of the proper

hydraulic pressure testing formula for HDPE 1 pressure sewer pipelines after

installation to ensure its proper performance.

[¶8.] As the project moved towards completion, Excel sent a letter to the

District requesting that it send a punch list of uncompleted contract items. 2 The

District did not send the list. In early January 2014, dozens of grinder stations

1. HDPE pipe is a flexible plastic pipe often used to transfer fluids or gas.

2. A punch list is an itemized list of final work or repairs necessary to complete a job. City of Bridgewater v. Morris, Inc., 1999 S.D. 64, ¶ 2, 594 N.W.2d 712, 714.

-3- #28580

began freezing. Excel, the District, and the grinder pump supplier disputed which

business was responsible for troubleshooting services. Although the District

allowed Excel to continue working on the Project until January 20, 2014, it

ultimately gave Excel notice that it was terminating the contract because Excel had

failed to meet the Project deadlines and requirements. Five days later, the District

hired a replacement contractor to troubleshoot, inspect, and repair malfunctioning

grinder pumps.

[¶9.] On January 19, 2014, Excel sued the District for breach of contract in

Minnehaha County, alleging the District violated the express terms of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trigger Energy Holdings v. Stevens
2025 S.D. 72 (South Dakota Supreme Court, 2025)
Smith Masonry v. Wipi Group, USA, Inc.
2023 S.D. 48 (South Dakota Supreme Court, 2023)
Lowell Lundstrom, Jr. v. Watts Guerra LLP
63 F.4th 692 (Eighth Circuit, 2023)
Peska Properties, Inc. v. Northern Rental Corp.
2022 S.D. 33 (South Dakota Supreme Court, 2022)
Lundstrom, Jr. v. Homolka, P.A.
D. South Dakota, 2022

Cite This Page — Counsel Stack

Bluebook (online)
941 N.W.2d 791, 2020 S.D. 19, Counsel Stack Legal Research, https://law.counselstack.com/opinion/excel-underground-inc-v-brant-lake-sanitary-district-sd-2020.