Smith Masonry v. Wipi Group, USA, Inc.

2023 S.D. 48
South Dakota Supreme Court·Decided September 20, 2023·No. 30007·Published·Cited by 3 cases

Opinion

#30007-r-PJD 2023 S.D. 48

IN THE SUPREME COURT

OF THE

STATE OF SOUTH DAKOTA

****

TOM SMITH DBA TOM SMITH MASONRY, Plaintiff and Appellant,

v.

WIPI GROUP, USA, INC., Defendant and Appellee, and LINCOLN COUNTY, SOUTH DAKOTA, Defendant.

****

APPEAL FROM THE CIRCUIT COURT OF THE SECOND JUDICIAL CIRCUIT LINCOLN COUNTY, SOUTH DAKOTA

****

THE HONORABLE DOUGLAS E. HOFFMAN Judge

****

JEFFREY L. BRATKIEWICZ of Bangs, McCullen, Butler, Foye & Simmons, LLP Sioux Falls, South Dakota Attorneys for plaintiff and appellant.

RONALD A. PARSONS, JR. of Johnson, Janklow & Abdallah, LLP Sioux Falls, South Dakota Attorneys for defendant and appellee.

****

CONSIDERED ON BRIEFS

JANUARY 9, 2023

OPINION FILED 09/20/23

DEVANEY, Justice [¶1.] Tom Smith Masonry (Smith Masonry) instituted a mechanic’s lien foreclosure action against WIPI Group USA, Inc. (WIPI), seeking to recover the unpaid balance due under the parties’ construction contract and an award of attorney fees. WIPI answered, asserting that Smith Masonry failed to properly complete the work called for in the contract. WIPI also asserted claims for breach of contract, breach of express warranty, and breach of implied warranty of reasonable workmanship. After a six-day bench trial, the circuit court determined that Smith Masonry had a valid mechanic’s lien for the unpaid contract balance; however, the court further determined that WIPI was entitled to an offset because Smith Masonry’s work did not meet a reasonable standard for construction of this nature. The court relied on principles of equity to deny both parties relief and ordered that each party be responsible for their own attorney fees and costs. Smith Masonry appeals, asserting the circuit court erred in multiple respects in denying its requested relief and abused its discretion in denying an award of attorney fees. We reverse in part and remand in part.

Factual and Procedural Background [¶2.] Tom Smith owns and operates Smith Masonry, and at the time of the contract at issue, his sons, Brent and Brady, worked for his company. On February 14, 2014, Smith Masonry entered into a contract with WIPI to construct a fence along the front of WIPI’s property in an industrial park. The construction of the fence was part of a larger project wherein WIPI was converting an industrial

building into a commercial office space. WIPI acted as the general contractor for the project, and counsel for WIPI drafted the contract with Smith Masonry. [¶3.] WIPI agreed to pay Smith Masonry a total of $60,387, with 40% paid as a down payment, 57% due “upon satisfactory completion of the work as determined by both parties and as outlined in [the contract],” and 3%, retained by WIPI for one year, to be paid to Smith Masonry after satisfactory completion of the general guarantee contained in the contract. The contract stated that WIPI would pay Smith Masonry $28,620 for the construction and installation of twelve stone veneer columns for the fence and two additional stone veneer columns for a sign, $24,827 for subcontractor American Fence’s portion of the work for fence panels and a gate, and $6,940 for a sign base. The contract incorporated a drawing by Tom depicting a rough layout of the columns and fence panels on the property. The drawing indicated that the columns would be 20 inches by 20 inches in width, with two-by-two-foot caps, and that square footings would be 46 to 48 inches deep. The contract also incorporated a surveyed site plan showing the proposed location of the columns and fence. Pursuant to the contract, if there were any change orders, they were to “be made by written agreement of all the parties.” [¶4.] After WIPI paid the down payment, but before any work on the project began, the parties executed an addendum to the original contract. Under the addendum, Smith Masonry agreed to construct a fence around the entire lot. This change required an additional 40 masonry columns at a sum of $95,400 and additional fence panels at a sum of $23,515. The contract indicated that the columns would be 29 inches by 24 inches in width, 6 feet tall, and spaced 24 feet

apart. Similar to the original contract, Smith Masonry was to construct the columns, American Fence was to install the panels, and any changes to the scope of the work were to “be made by written agreement of all the parties.” WIPI agreed to pay an additional $118,915 under the same payment terms as the original contract. A surveyed site plan depicting the proposed location of the columns and fence was attached to the addendum. [¶5.] When construction began, Smith Masonry subcontracted with Krueger Excavation to perform the dirt work and pour the concrete footings. Smith Masonry had Krueger Excavation pour circular (not square), 24-inch footings at a depth of 46 to 48 inches. Tom claimed that he used circular rather than square footings because the auger drilled circular holes and the use of circular footings made it easier for Smith Masonry to keep the fence within the property boundary lines. [¶6.] While Krueger Excavation was responsible for digging the holes for the column footings and for pouring the concrete, Smith Masonry determined the location of the holes. Tom and his son Brady both testified that the presence of underground utilities played a role in where the holes ended up being dug and in the number of columns Smith Masonry ultimately constructed. As a result, while the contract called for 52 columns, Smith Masonry constructed 59 to avoid utility lines and “for the spacing to work out[.]” The change in the number of columns constructed and other changes raised the total cost of the project to $201,387. Tom claimed that WIPI approved these changes and that change orders were drafted as a result. However, WIPI never signed the change orders.

Free access — add to your briefcase to read the full text and ask questions with AI

Smith Masonry v. Wipi Group, USA, Inc., 2023 S.D. 48 (S.D. 2023).

2023 S.D. 48 (Smith Masonry v. Wipi Group, USA, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Fischer v. Fischer-Olson
2026 S.D. 39 (South Dakota Supreme Court, 2026)
Jed Spectrum, Inc. v. Stoakes
2025 S.D. 31 (South Dakota Supreme Court, 2025)
Smith Masonry v. Wipi Group Inc.
2025 S.D. 26 (South Dakota Supreme Court, 2025)
State v. Foshay
2024 S.D. 12 (South Dakota Supreme Court, 2024)