Van Den Hoek v. Bradwisch

273 N.W.2d 152, 1978 S.D. LEXIS 353
CourtSouth Dakota Supreme Court
DecidedDecember 29, 1978
Docket12287
StatusPublished
Cited by9 cases

This text of 273 N.W.2d 152 (Van Den Hoek v. Bradwisch) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Van Den Hoek v. Bradwisch, 273 N.W.2d 152, 1978 S.D. LEXIS 353 (S.D. 1978).

Opinion

PORTER, Justice.

CASE SUMMARY

Plaintiff-respondent Van Den Hoek (contractor) brought this action against defendant-appellant Bradwisch (owner), seeking to recover the balance due on a contract to construct a house. The trial court entered a judgment in favor of the contractor for $5,650.00 based on a jury verdict in that amount. We hold that the trial court’s instructions allowed the jury to give the contractor damages based on the contract price, whether the contractor substantially performed the contract or not. Thus the jury was not required to determine the question of substantial performance. Since this critical factual question remains undetermined, we reverse the judgment and remand for a new trial.

FACTS

The owner and the contractor entered into a contract whereby the contractor agreed to construct a house in Stickney. The contractor prepared a written agreement in April, 1973, and the parties met in May of the same year to agree on details. The owner expressed a desire to have the house completed by August 1,1973, and the contractor said he would make an effort to complete the house as soon as possible. There was, however, no completion date in the written contract.

The contractor began construction of the house in May, 1973. During construction, the parties discussed various additions, and although the evidence conflicted, the contractor testified that the owner requested additions with a value of over $2,000.00. The parties apparently did not agree on a price for these additions to the contract.

The house was enclosed by July, 1973, and inside work continued. In July or August, the owner became dissatisfied with the pace of the work. He testified that the contractor left sometime in July or August and did not get back to the project until September 26,1973. The owner moved into the house on October 1, 1973, even though the furnace was not hooked up and the plumbing was only partially completed.

The testimony of the parties conflicts as to occurrences after October 1, 1973. The contractor testified that he tried to come back to complete inside work on November 20, 1973, and was refused admission to the house. The owner testified that he became aware of certain construction and plumbing defects in November or December, 1973, and called a state plumbing inspector. The inspector’s report is a part of the record and lists numerous violations of state plumbing regulations. The owner testified further that he never refused admission to the contractor in 1973, and that the contractor did some plumbing on December 8, 1973. The contractor said he had no recollection of being at the owner’s house on December 8, 1973.

Although the parties did talk with one another during the next few months, the contractor did not attempt to complete any further work until March, 1974. By this time, mechanics liens had been filed against the property by suppliers of materials whom the contractor had not paid. The owner testified that he told the contractor to have the liens discharged before he did any further work on the house. The contractor testified that the owner refused to let him work on the house after March, 1974. He also claimed that the owner converted tools and materials left at the site.

*154 The owner claims that the construction was defective in a number of particulars. The greatest fault is said to be in the plumbing. The plumbing defects are set forth in the state plumbing inspector’s report. The owner hired a plumber to correct some of these defects, but most of them remained uncorrected to the date of trial, even though the owner and his family were living in the house. The owner also claims that the electrical wiring was incomplete and that he spent nearly $400.00 to complete it. Numerous other defects and unfinished work are also claimed.

The contractor claims that the work was substantially completed, and that the owner prevented him from completing the rest and from correcting defects in original construction.

The jury returned a verdict of $5,650.00 in favor of the contractor. The trial court entered judgment in this amount. The owner appeals.

ISSUE

The issue dispositive of this appeal is: Do the instructions adequately set out the rule of substantial performance of construction contracts as it relates to the measure of damages applicable under that rule? We conclude that the instructions misdirected the jury.

DECISION

We have long recognized the rule of substantial performance of building contracts. We first stated the rule in Aldrich v. Wilmarth, 3 S.D. 523, 54 N.W. 811 (1893): “But where the builders have in good faith intended to and have substantially complied with their contract, although there may be slight defects caused by inadvertence or unintentional omissions, they may recover the contract price, less the damages sustained on account of such defects.” [Emphasis supplied]. The other cases recognizing this doctrine are collected in Dixon v. Nelson, 79 S.D. 44, 48, 107 N.W.2d 505, 507 (1961).

As we said in Dixon, supra, no absolute criteria prevail whereby the courts determine whether performance is sufficient to invoke this doctrine. In Hulst v. Benevolent Hall Ass’n, 9 S.D. 144, 68 N.W. 200 (1896), we held that defects not easily remedied, and not caused by inadvertence, were sufficient to deny the contractor recovery. An important factor in this determination is whether the deviation from the contract defeats the purpose of the contract in any substantial manner. It is also important to view the extent of nonperformance in relation to the full performance promised. Dixon v. Nelson, supra.

This inquiry is essentially factual. It is thus the duty of the jury to determine whether there has been substantial performance. Hulst v. Benevolent Hall Ass’n, supra; Dixon v. Nelson, supra. We cannot substitute our judgment on factual questions for that of the jury, where sufficient evidence is presented to allow reasonable minds to reach differing conclusions.

The question of whether the performance rendered was substantial is central to this case. If performance was substantial, the contractor is entitled to recover the contract price less deductions for defects in performance. Aldrich v. Wilmarth, supra. If performance was not substantial, the contractor is entitled, at most, to the value of the benefit that he conferred upon the owner under a theory of quantum me-ruit or unjust enrichment, and not to the contract price minus defects. See Thurston v. Cedric Sanders Company, 80 S.D. 426, 125 N.W.2d 496 (1963); Woodford v. Kelley, 18 S.D. 615, 101 N.W. 1069 (1904). We believe that the trial court misdirected the jury on this critical issue. The fourth paragraph of instruction 31 1 tells the jury that it is to *155 deduct defendant owner’s damages, if any, from the unpaid contract balance due the contractor. The jury is instructed to do so

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith Masonry v. Wipi Group, USA, Inc.
2023 S.D. 48 (South Dakota Supreme Court, 2023)
Mathis Implement Co. v. Heath
2003 SD 72 (South Dakota Supreme Court, 2003)
Ahlers Building Supply, Inc. v. Larsen
535 N.W.2d 431 (South Dakota Supreme Court, 1995)
Rosebud Sioux Tribe v. A & P Steel, Inc.
874 F.2d 550 (Eighth Circuit, 1989)
Barton Masonry, Inc. v. Varilek
375 N.W.2d 200 (South Dakota Supreme Court, 1985)
Kulseth v. Rotenberger
320 N.W.2d 920 (North Dakota Supreme Court, 1982)
Reif v. Smith
319 N.W.2d 815 (South Dakota Supreme Court, 1982)
Northern Farm Supply, Inc. v. Sprecher
307 N.W.2d 870 (South Dakota Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
273 N.W.2d 152, 1978 S.D. LEXIS 353, Counsel Stack Legal Research, https://law.counselstack.com/opinion/van-den-hoek-v-bradwisch-sd-1978.