Ahlers Building Supply, Inc. v. Larsen

535 N.W.2d 431, 1995 S.D. LEXIS 97, 1995 WL 455533
CourtSouth Dakota Supreme Court
DecidedAugust 2, 1995
Docket18686
StatusPublished
Cited by12 cases

This text of 535 N.W.2d 431 (Ahlers Building Supply, Inc. v. Larsen) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ahlers Building Supply, Inc. v. Larsen, 535 N.W.2d 431, 1995 S.D. LEXIS 97, 1995 WL 455533 (S.D. 1995).

Opinion

KONENKAMP, Justice.

Homeowners appeal damages awarded to a contractor on a home remodeling project. We affirm in part and reverse in part.

FACTS

Vickie and Peter Larsen (Larsens) solicited bids for remodeling their home. After presenting preliminary architectural plans to Ahlers Building Supply (Ahlers), its agent, Todd Lindgren, developed a blueprint and offered a base contract bid of $45,500. Any additional changes the Larsens might later request beyond the original plans would cost more. The Larsens accepted. Construction *433 was scheduled to begin the week of April 22, 1991 and end the week of June 15, 1991.

Assured construction would be completed within sixty days, the Larsens arranged for project financing. At the half-way point, they paid Ahlers half the base contract price ($22,750). The Larsens requested a number of changes and additions during the course of construction. Ahlers kept separate records on the labor and materials needed for these changes. From time to time the Larsens were dissatisfied 'with Ahlers’ workmanship, so many corrections were made. After months of delay the Larsens paid additional fees to extend the bank’s loan commitment, but they eventually lost their financing anyway. Communications between the parties broke down and the Larsens made no further payments to Ahlers. In January 1992, with the project almost complete and building defects yet uncorrected, Ahlers sent a letter to the Larsens ending their business relationship.

The floor of the new addition was several inches lower than the rest of the house, despite the fact the plans provided otherwise. Ahlers thought the level should be lower to prevent damage to the rest of the house should the hot tub in the addition leak. The Larsens wanted it level with the rest of the home in the event handicap accessibility was ever needed. Wood siding was installed without alternating the joints, thereby creating visible seams, which the contract was silent about, but was nonetheless aesthetically unpleasant to the Larsens. Stain Ahlers’ painting contractor used on the siding was applied inconsistent with manufacturer instructions, was the wrong shade of color, and portions of the siding were left unstained.

The cement contractor warned Lindgren and Peter Larsen the garage drainage pipe was not far enough below the garage floor and would cause the concrete to crack. Larsen and Lindgren had the contractor pour the concrete anyway. Shortly afterwards, because the drain was at the high point of the floor, water would not drain. Two to three weeks later, the floor cracked. The cement contractor agreed to correct the problem if the Larsens would provide the materials needed, but the Larsens rejected the offer. Ahlers later sent the Larsens a letter stating the cement contractor would “take care of the garage floor.” Nothing came of it.

Metal beading strips were merely pressed, rather than nailed, to the edges of sheetrock eventually causing cracks in the interior walls when the strips loosened. Nails used to hang sheetrock popped loose. Shake shingles were installed at a seven inch exposure rather than ten inches — meaning more had to be used thereby increasing costs. A skylight window was installed in the shake roof although installation instructions warned against doing so. Other windows were ill-fitted into rough openings preventing them from opening and closing properly. Although the plans called for a two foot by four foot fireplace, its dimensions were two by two. The chimney was also improperly installed.

The Larsens hired a new contractor in July 1992 who corrected the defects with the garage floor, fireplace and chimney, walls, and windows. New wood siding was installed and stained. The Larsens saved the improperly stained pieces for Ahlers, but Ah-lers never retrieved them. Ahlers corrected many other defects, which are not at issue here.

The following August, Ahlers sued to recover on the remainder of the contract price, plus the agreed upon change order amounts. The Larsens counterclaimed alleging Ahlers’ failure to finish the contract and seeking expenses for hiring someone else to complete it. At trial, both parties produced different written versions of their agreement. Both copies contained sixteen identical provisions, several change orders and an addendum. The Larsens’ copy, however, bore the signatures of Peter Larsen and Ahlers’ agent and contained fourteen pages not found in Ahlers’ version. Ahlers’ version contained no signatures and included one page not a part of the Larsens’ copy. Both sides agree their documents were prepared by Ahlers’ agent, who did not testify. Although the trial court never revealed which version it determined was the true contract, the findings of fact imply it accepted Ahlers’ version.

*434 The trial court found the parties agreed to allowances for plumbing and painting whereby expenses exceeding the estimated contract amounts for the respective tasks would be added to the final price as specifically outlined in Ahlers’ version. According to the trial court’s findings, the $1,450 plumbing allowance was exceeded by $3,061 and the $800 painting allowance was exceeded by $1,155. Overall, the trial court concluded Ahlers expended $17,138.10 above the base contract price for change orders, additions, and allowance excess and Larsens spent $10,-637 correcting Ahlers’ mistakes. Ahlers was awarded $29,251: the difference between Ah-lers’ and Larsens’ expenditures plus the remaining half of the base contract price. The court disallowed prejudgment interest. On appeal, the Larsens raise four issues; we examine the following two issues:

I. Did the trial court err in not specifying which contract applied?
II. Did Ahlers substantially comply with the written contract?

We conclude the trial court erred in awarding Ahlers for alleged painting allowance overages, thus we reverse that award only and otherwise affirm.

DECISION

I. Different Versions of Contract

The parties presented dissimilar copies of the remodeling agreement to the trial court thereby leaving it to determine which one was the valid express contract. Werner v. Norwest Bank, 499 N.W.2d 138, 141 (S.D.1993); Mid-America Marketing. Corp. v. Dakota Industries, 289 N.W.2d 797, 799 (S.D.1980). The trial court never specifically decided which contract version prevailed. Yet we can answer the question as a matter of law. North River Ins. Co. v. Golden Rule Const., 296 N.W.2d 910, 912-13 (S.D.1980); Teigen Const. v. Pavement Specialists, Inc., 267 N.W.2d 574 (S.D.1978).

The first fourteen pages of the Larsens’ version contain twelve “divisions” detailing specifics of the construction project. Although these divisions are absent from Ah-lers’ copy, Ahlers neither contests them nor are they part of the dispute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith Masonry v. Wipi Group, USA, Inc.
2023 S.D. 48 (South Dakota Supreme Court, 2023)
Dakota Style Foods, Inc. v. Sunopta Grains & Foods, Inc.
329 F. Supp. 3d 794 (U.S. District Court, 2018)
Mathis Implement Co. v. Heath
2003 SD 72 (South Dakota Supreme Court, 2003)
Ambur v. United States
206 F. Supp. 2d 1021 (D. South Dakota, 2002)
Setliff v. Akins
2000 SD 124 (South Dakota Supreme Court, 2000)
Campion v. Parkview Apartments
1999 SD 10 (South Dakota Supreme Court, 1999)
Singpiel v. Morris
1998 SD 86 (South Dakota Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
535 N.W.2d 431, 1995 S.D. LEXIS 97, 1995 WL 455533, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ahlers-building-supply-inc-v-larsen-sd-1995.