Kulseth v. Rotenberger

320 N.W.2d 920, 1982 N.D. LEXIS 308
CourtNorth Dakota Supreme Court
DecidedJune 10, 1982
DocketCiv. 10131
StatusPublished
Cited by8 cases

This text of 320 N.W.2d 920 (Kulseth v. Rotenberger) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kulseth v. Rotenberger, 320 N.W.2d 920, 1982 N.D. LEXIS 308 (N.D. 1982).

Opinion

VANDE WALLE, Justice.

Rotenberger appealed from a judgment and an order denying his motion to alter or amend findings of fact, conclusions of law, and order for judgment. The judgment awarded Kulseth $1,525.95 following a dispute involving an oral contract. We modify the judgment and, as modified, affirm.

In the spring of 1974 Kulseth agreed to construct for Rotenberger two metal buildings, a shop and a barn. He prepared a worksheet, which the parties have referred to as a contract or bid. The shop was to cost $9,634, which included the cost for materials, insulation, a cement slab in place, three metal overhead doors, and labor. Sales tax, freight, a drain, and a steel bin were separate. The cost for the materials alone was $4,350.

The materials for the two buildings were delivered to the construction site in July 1974. In August, Kulseth poured the footings for both buildings. He did not, however, pour the cement slab for the floor of the shop.

On August 20, Kulseth presented to Ro-tenberger a job invoice in the amount of $8,000 for the materials for the two buildings, of which Rotenberger paid $5,000. No further payments were made.

Prior to October 9,1974, Kulseth removed the materials for the barn from the work-site, the parties apparently having mutually agreed to a rescission of that part of their agreement. Hence the barn was no part of this lawsuit except as to the footings.

The trial court found that by December 21, Kulseth had completed the shop except for the slab, the hanging of the three overhead doors, and the insulating of the building. It found the overhead doors to have been installed by February 18,1975, but one door was not operational because of a missing part. Kulseth’s testimony indicates that the shop was 90 percent complete at that time, except for the insulation, the slab, and some trim around the doors.

Work on the shop stopped on February 19. Kulseth’s son, LaVerne, the foreman on the job, was told by Rotenberger on February 18 not to install galvanized trim around the doors because Rotenberger wanted white trim. The next day Roten-berger telephoned LaVerne and told him to stop any further work but gave no reason for the order. No further work was done on the building by Kulseth.

Rotenberger testified that he stopped work because Kulseth had installed fiberglass doors when the contract called for steel doors. There is testimony that Roten-berger’s reason for stopping work was not communicated to Kulseth until July 24 at which time Rotenberger, through his attorney, contacted Kulseth by letter requesting him to either install steel doors, pour and finish all concrete work, and install all insulation or effect mutual rescission of the contract with no more work to be done by Kulseth and nothing to be paid by Roten-berger.

Correspondence involving the dispute was exchanged between the parties — Rotenber-ger insisting that, at all times, the contract called for steel doors; and Kulseth, on the other hand, insisting that Rotenberger originally ordered fiberglass doors and changed his mind after they were installed. Kulseth *922 thereafter offered to install steel doors only if Rotenberger would pay for the steel doors and for additional labor as well as making an adjustment for the fiberglass doors. Unable to settle their dispute, they proceeded to trial with Kulseth suing Ro-tenberger on a theory of quantum meruit for the reasonable value of materials and services rendered.

Rotenberger believed the $5,000 he had already paid was adequate compensation for what Kulseth had done, and he counterclaimed for damages for the amount he was required to pay over the original contract price to have others install steel doors and complete the shop.

The trial court found that Kulseth furnished to Rotenberger materials and services of the reasonable worth of $7,243.25, from which was deducted $180, which the court determined to be the reasonable worth of installing steel doors as called for by the contract, and also offset $537.30, representing the difference between the quoted price for doors under the contract ($1,050) and the price quoted for steel doors by Kulseth some months later ($1,587.30). The court further allowed for the $5,000 which had already been paid by Rotenber-ger.

The trial judge stated that Rotenberger failed to show that he was damaged any further by Kulseth’s failure to furnish steel doors.

ISSUES

The issues are as follows:

1. Whether or not the trial court erred in awarding damages to Kulseth.

2. Whether or not the trial court’s finding of fact No. XI as to the amount of materials and labor furnished by Kulseth is clearly erroneous.

Rotenberger argues that Kulseth failed to substantially perform under the contract and is precluded from recovering anything. Rotenberger’s position is that he would have to expend $10,494.32 to complete the building, which is $92.81 more than the $10,401.51 that he would have had to pay Kulseth. For this reason Rotenberger claims the trial court erred in not returning a judgment in his favor in the amount of at least $92.81. Rotenberger’s argument is based on the trial court’s finding of fact No. IX, that the contract called for steel doors, and conclusion of law No. I, that Kulseth breached this part of the contract.

Kulseth, on the other hand, argues that his cause of action does not involve substantial performance but is based on quantum meruit, for which he is entitled to recover the reasonable value of materials and services rendered to Rotenberger. If a contractor does not substantially perform he is entitled, at most, to the value of the benefit that he has conferred upon the owner under a theory of quantum meruit or unjust enrichment, and not the contract price minus the defects. Van Den Hoek v. Bradwisch, 273 N.W.2d 152 (S.D.1978). Rotenberger relies on the case of Dittmer v. Nokleberg, 219 N.W.2d 201, 206 (N.D.1974), which states that “if the contractor fails substantially to perform he may not recover at all under his contract.” However, that decision does not necessarily preclude a recovery on a quantum meruit, which is a recovery of the reasonable value of goods and services rendered as opposed to a recovery based on contract values. This interpretation is reinforced by our recent decision in Allied Realty, Inc. v. Boyer, 302 N.W.2d 774 (N.D.1981), in which Allied did not satisfy the terms of an exclusive listing agreement. This court, however, determined that Allied was entitled to a recovery upon quantum meruit because the defendant, Boyer, received some value for the services performed by Allied.

We have no disagreement with the principles regarding substantial performance enunciated in Nokleberg. The instant case, however, involves a claim based upon quantum meruit and Nokleberg is not, therefore, dispositive.

The cross-rights of the parties to a contract when there has been a breach by the plaintiff are explained in Williston on Contracts, 3d Ed., § 1484, as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Butera v. Boucher
798 A.2d 340 (Supreme Court of Rhode Island, 2002)
Towne v. Dinius
1998 ND 162 (North Dakota Supreme Court, 1998)
Circle B Enterprises, Inc. v. Steinke
1998 ND 164 (North Dakota Supreme Court, 1998)
Tobias v. North Dakota Department of Human Services
448 N.W.2d 175 (North Dakota Supreme Court, 1989)
Podoll v. Brady
423 N.W.2d 151 (North Dakota Supreme Court, 1988)
Lancellotti v. Thomas
491 A.2d 117 (Supreme Court of Pennsylvania, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
320 N.W.2d 920, 1982 N.D. LEXIS 308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kulseth-v-rotenberger-nd-1982.