Dittmer v. Nokleberg

219 N.W.2d 201, 1974 N.D. LEXIS 200
CourtNorth Dakota Supreme Court
DecidedJune 4, 1974
DocketCiv. 8918
StatusPublished
Cited by27 cases

This text of 219 N.W.2d 201 (Dittmer v. Nokleberg) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dittmer v. Nokleberg, 219 N.W.2d 201, 1974 N.D. LEXIS 200 (N.D. 1974).

Opinion

TEIGEN, Judge.

Both the plaintiffs and the defendant have appealed from a judgment of the trial court.

In their complaint the plaintiffs (Ditt-mers) seek to recover damages in the amount of $24,560 from the defendant (Nokleberg) because of Nokleberg’s breach of contract in the construction of a home on the Dittmers’ farm. It is the contention of the Dittmers that Nokleberg failed to substantially perform the contract, and that the measure of damages is the difference between the value of the house as finished by Nokleberg and what the value of the house would have been if it had been finished according to the contract.

Nokleberg has counterclaimed for a recovery of the amount due on the contract, by foreclosure of his mechanic’s lien, and for alleged extras, for a total of $6,252.

The case was tried to the court, and the court determined that the Dittmers were responsible for some of the defects but that Nokleberg was also responsible for a number of defects, and that Nokleberg had not substantially performed his contract. It allowed the Dittmers judgment against Nokleberg in the'amount of $4,077.38, and denied Nokleberg’s counterclaim.

It appears that the Dittmers and Nokle-berg entered into a verbal contract in March 1970, whereby Nokleberg was em *204 ployed by the Dittmers to furnish labor for the construction of a dwelling on their farm at an agreed consideration of $8,900. Of this sum $7,300 was allocated for labor in building the house and $1,600 for labor in constructing the basement and garage. Under the arrangement the Dittmers were to buy all materials, and Nokleberg was to do the carpenter and cement work. The Dittmers reserved to themselves the letting of contracts to other persons for excavation of the basement, electrical wiring, plumbing, brick work, plastering, and the installation of heating. The Dittmers planned to do the painting themselves.

The house was nearly completed when the parties terminated their relationship because of differences that had arisen during the construction period. The unfinished work at the time of the termination of the contract was valued at $470. Thus it appears that Nokleberg’s work was approximately 95% complete at the time of the termination of the contract on or about April 7, 1971.

During the process of the work the Ditt-mers paid Nokleberg the sum of $4,000. Nokleberg filed a mechanic’s lien for the balance of his claim, based on the contract. In addition, he claims that he performed extras in the amount of $1,525. He seeks recovery for the amount due, less the value of the unfinished work.

The claims for damages by the Dittmers are numerous. They claim that there were defects in the construction of a good portion of the exterior walls of the dwelling which resulted in the masonite siding being wavy. This was caused by the use of crooked 2 x 4s and studs in the construction of the walls. They also claim that the hip roofs and roof valleys were irregular; that the soffits were negligently constructed, causing leakage of water from the roof into the interior of the building; that the front entry concrete slab pulled away from the house; that, through carelessness, cement had splattered on a portion of the exterior walls of the building and was permitted to harden; that there were numerous defects in the interior of the house, consisting of improper installation of windows ; improper installation of sheetrock around the windows, leaving openings, and that some windows were “offsquare”; that miter cuts on inside trim did not fit; that the walls were out of plumb in some of the rooms; that the interior doorways and trim were uneven; that the sliding doors did not fit nor work; that cracks developed in the ceiling; that support posts in the basement were not properly installed; that the woodwork in the bathroom was mismatched as to grain; that the kitchen cabinets were improperly constructed and installed; and that the cement in the basement floor was developing holes and cavities.

Nokleberg contends that, pursuant to the oral contract, the Dittmers were responsible for furnishing the materials; that during the construction period the Uittmers assumed the role of general contractor, interfered with the regular process of work by changing the plans of the house several times during the construction period, interfered with the work by doing some of the work themselves, and delayed construction; that during the delay period, there were several heavy rains before the house was closed in; and that instructions were given to change the roof of the house from a gable to a hip roof. It appears that a number of differences arose between the parties during the construction period, finally resulting in the termination of the relationship.

The evidence is contradictory in a number of respects, although both parties agree that the Dittmers were responsible for purchasing the materials. The Dittmers contend that Nokleberg had the responsibility of approving the materials and chose the lumber company from which the materials were to be purchased. The Dittmers testified that their agreement with the lumber company was that the lumber was to be 80% of construction quality and 20% of standard grade, whereas the lumber furnished was only 50% of construction quali *205 ty. It appears that this caused a delay in the work of about three weeks. During this time the dwelling was only partially constructed and had not been closed in against the weather, and that during this period it rained. Nokleberg contends that he attempted to cull out the defective materials, and that he was not responsible for the quality of the materials.

The trial court, having heard the testimony and observed the witnesses as they testified, determined that Nokleberg must be held responsible for the lack of good workmanship and that the Dittmers must be held responsible for the defects in materials. It also determined that the defects or omissions which were not remediable without tearing down that portion of the building which had incorporated in it the wavy walls and other defects caused by poor materials were the fault of the Ditt-mers, and that the remaining defects were remediable or repairable. Although the trial court found that the defects in workmanship were substantial, that reference in its findings was limited to the interior of the house. The record establishes that subsequent to the termination of the contract between the parties the Dittmers engaged other workmen to repair or remedy these defects, as well as to complete some of the work which remained unfinished.

In its memorandum decision the trial court found that the necessary repairs had been made at a cost to the Dittmers of $3,557.38, plus repairs yet to be made on the basement floor estimated at $50, and allowed damages for uncompleted work in the amount of $470, for a total of $4,077.38 as damages allowable to the Dittmers against Nokleberg. It denied Nokleberg’s claim for the balance of the contract and for the claimed extras on the basis that there had not been substantial performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shafer v. Scarborough
2022 ND 233 (North Dakota Supreme Court, 2022)
Coulier v. United Airlines, Inc.
110 F. Supp. 3d 730 (S.D. Texas, 2015)
Pegg v. Kohn
2015 ND 79 (North Dakota Supreme Court, 2015)
Curtis Construction Co. v. American Steel Span, Inc.
2005 ND 218 (North Dakota Supreme Court, 2005)
Towne v. Dinius
1998 ND 162 (North Dakota Supreme Court, 1998)
Circle B Enterprises, Inc. v. Steinke
1998 ND 164 (North Dakota Supreme Court, 1998)
All Seasons Water Users Ass'n v. Northern Improvement Co.
399 N.W.2d 278 (North Dakota Supreme Court, 1987)
Winterton v. Elverson
389 N.W.2d 633 (South Dakota Supreme Court, 1986)
Hogg v. First National Bank of Aberdeen
386 N.W.2d 921 (South Dakota Supreme Court, 1986)
Precon, Inc. v. JRS Realty Trust
47 B.R. 432 (D. Maine, 1985)
Bismarck Realty Co. v. Folden
354 N.W.2d 636 (North Dakota Supreme Court, 1984)
Gross v. Sta-Rite Industries, Inc.
336 N.W.2d 359 (North Dakota Supreme Court, 1983)
Merrill Iron & Steel, Inc. v. Minn-Dak Seeds, Ltd.
334 N.W.2d 652 (North Dakota Supreme Court, 1983)
Storebo v. Foss
325 N.W.2d 223 (North Dakota Supreme Court, 1982)
Kulseth v. Rotenberger
320 N.W.2d 920 (North Dakota Supreme Court, 1982)
Koland, Inc. v. Hanggi
320 N.W.2d 502 (North Dakota Supreme Court, 1982)
Reif v. Smith
319 N.W.2d 815 (South Dakota Supreme Court, 1982)
Cook v. Jacklitch & Sons, Inc.
315 N.W.2d 660 (North Dakota Supreme Court, 1982)
Robertson Companies, Inc. v. Kenner
311 N.W.2d 194 (North Dakota Supreme Court, 1981)
Carlson Homes, Inc. v. Messmer
307 N.W.2d 564 (North Dakota Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
219 N.W.2d 201, 1974 N.D. LEXIS 200, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dittmer-v-nokleberg-nd-1974.