Cook v. Jacklitch & Sons, Inc.

315 N.W.2d 660, 1982 N.D. LEXIS 223
CourtNorth Dakota Supreme Court
DecidedFebruary 11, 1982
DocketCiv. 10030
StatusPublished
Cited by7 cases

This text of 315 N.W.2d 660 (Cook v. Jacklitch & Sons, Inc.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cook v. Jacklitch & Sons, Inc., 315 N.W.2d 660, 1982 N.D. LEXIS 223 (N.D. 1982).

Opinion

ERICKSTAD, Chief Justice.

This is an appeal by the defendants, Jack-litch & Sons, Inc. and LeRoy Jacklitch (herein referred to as Jacklitch), from a judgment of the District Court of Richland County, dated April 14, 1981, in favor of the plaintiffs, Richard and Edith Cook. We affirm.

During August, 1979, the Cooks entered a written contract to have Jacklitch build them a new home in Wahpeton. Jacklitch’s wife, Mercedes, drafted the contract and also made drawings which outlined the dimensions of the proposed home and its rooms. Construction of the house began and continued until November 12, 1979, when the Cooks ordered Jacklitch to cease construction and to leave the site. On that date the work had progressed such that the cement basement foundation had been poured, the wood sill plate, joist, and wood flooring had been placed, and part of the two-by-four framing on the main level had been constructed.

Thereafter, the Cooks filed an action against Jacklitch asserting that the completed construction on the house had been negligently performed. Jacklitch filed a counterclaim asserting that the Cooks, by wrongfully terminating construction, had breached the contract. Subsequent to trial, the Cooks amended their complaint to include a claim for breach of warranty.

The trial court determined that Jacklitch had failed to substantially perform the contract and had breached an implied warranty that the house was fit for its intended purpose. The court further determined that the Cooks were justified in rescinding the contract. In its judgment the trial court dismissed Jacklitch’s counterclaim and awarded the Cooks $2,500 as compensatory damages for the expense of removing the foundation and filling the excavation.

On appeal Jacklitch has raised the following issues:

(1) Whether or not the trial court’s finding that Jacklitch failed to substantially perform the contract is clearly erroneous;
(2) Whether or not the trial court erred in its refusal to grant Jacklitch compensation on a theory of quantum me-ruit ; and
(3) Whether or not the trial court’s finding that LeRoy Jacklitch is individually liable on the contract is clearly erroneous.

*662 A buyer has a right to rescind the contract if the contractor fails to substantially perform. Robertson Companies, Inc. v. Kenner, 311 N.W.2d 194 (N.D.1981). In City of Granville v. Kovash, Incorporated, 118 N.W.2d 354 (N.D.1962), at syllabus number 4, this Court defines substantial performance:

“4. In order that a building or construction contract shall be considered to be ‘substantially performed,’ it must appear not only that the contractor endeavored to perform the contract in good faith, but also that he has in fact done so, except as to unimportant omissions or deviations which are the result of mistake or inadvertence and which were not intentional.”

The question of whether or not a contractor has substantially performed is a question of fact, and the trial court’s finding in this regard will not be upset on appeal unless it is clearly erroneous. Rule 52(a), N.D.R. Civ.P.; Robertson Companies, Inc. v. Kenner, 311 N.W.2d 194 (N.D.1981); Dittmer v. Nokleberg, 219 N.W.2d 201 (N.D.1974).

In this case the trial court found that Jacklitch had failed to substantially perform the contract on the work completed prior to termination of the contract by the Cooks. The court based its determination on the following underlying findings of fact:

“7. After the foundation was poured and after it was covered with the wood sill plate, joists and wood flooring, various problems appeared which included the following:
(1) The concrete work was not of good quality. Forms used were old and in a state of disrepair.
(2) One or more of the walls were bowed so that the sill plate either extended over the foundation wall or the wall extended out from the plate.
(3) The tops of the foundation walls were not level nor made level by proper grouting. The sill plate, therefore, did not rest evenly on the foundation walls. One Exhibit also indicated that the joists did not rest properly on the sill plate. As a result, the floors constructed would not be level and there would be a possibility that walls would crack.
(4) One of the basement walls was improperly placed so that, if uncorrected, it would mean that the kitchen, already small, would be 8 inches smaller. This could be corrected only by removing and replacing the wall or cantilevering one side of the house.
(5) The house that the Cooks ordered, and which Jacklitch agreed to build, could not have been built on the lot selected and comply with the building codes of the City of Wahpeton. The plans called for the garage floor to be on the same level as the foyer and the family room. If the house were so constructed, either: (1) the basement would be so low that it would be below the water table, or (2) the garage and driveway would be so high that it would be in violation of the Wahpeton building codes and, in any event, aesthetically offensive to the neighborhood. The garage floor was, therefore, placed at a lower level than that called for by the original contract.”

Jacklitch asserts that there was insufficient expert testimony or other evidence to support the trial court’s finding that Jacklitch failed to substantially perform the contract. We disagree.

Robert Brungardt, Wahpeton city building official, whom the parties stipulated as an expert on the Wahpeton building code and on the construction of private, single family dwellings, testified on behalf of the Cooks, in relevant part:

“Q. Showing you Plaintiffs’ Exhibit 6, do you recognize that, and please tell us what you see.
“A. Unleveled foundation. There’s no support on the sill plate at all.
♦ * * * * *
“Q. What kind of difficulty does that present?
******
“A. Well, it would eventually — the floor would be uneven. It would settle, and you have a wavey [wavy] floor, and the walls would be the same thing.
******
*663 “Q. Had someone indicated to you pri- or to that time that that wall was in the wrong place.
“A. Yes, both the Cooks were complaining that it was in the wrong place, and Jacklitch himself visited about it and told him that that wall could be moved.
* * * * * *
“Q.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keller v. Keller
2024 ND 27 (North Dakota Supreme Court, 2024)
Flaten v. Couture
2018 ND 136 (North Dakota Supreme Court, 2018)
Habeck v. David MacDonald, M.D., P.C.
520 N.W.2d 808 (North Dakota Supreme Court, 1994)
All Seasons Water Users Ass'n v. Northern Improvement Co.
399 N.W.2d 278 (North Dakota Supreme Court, 1987)
Dodds v. North Dakota State Highway Commissioner
354 N.W.2d 165 (North Dakota Supreme Court, 1984)
Stillwell v. Cincinnati Inc.
336 N.W.2d 618 (North Dakota Supreme Court, 1983)
Gross v. Sta-Rite Industries, Inc.
336 N.W.2d 359 (North Dakota Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
315 N.W.2d 660, 1982 N.D. LEXIS 223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cook-v-jacklitch-sons-inc-nd-1982.