Tri-State Home Improvement Co. v. Mansavage

253 N.W.2d 474, 77 Wis. 2d 648, 1977 Wisc. LEXIS 1324
CourtWisconsin Supreme Court
DecidedMay 17, 1977
Docket75-230
StatusPublished
Cited by15 cases

This text of 253 N.W.2d 474 (Tri-State Home Improvement Co. v. Mansavage) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri-State Home Improvement Co. v. Mansavage, 253 N.W.2d 474, 77 Wis. 2d 648, 1977 Wisc. LEXIS 1324 (Wis. 1977).

Opinion

BEILFUSS, C. J.

Three basic issues are presented: (1) Did the plaintiff substantially perform the contract?

(2) Was it an abuse of discretion to deny the plaintiff’s motion to amend its complaint so as to state a cause of action for quantum meruit?

(3) Did the proof establish violations of the provisions of Ch. Ag 110, 1 Wis. Adm. Code, dealing with unfair practices in home improvement contracts ?

*654 On April 29, 1972, the defendants-respondents, Dennis and Bridget Mansavage entered into a written home improvement contract with the plaintiff-appellant, TriState Home Improvement Company, Inc., through its agent, David Kahn. The contract price was $2,500. Included in the contract provisions was the following:

“SPECIFICATIONS
“Reside outer wall with Genuine U. S. aluminum color white use in g’abels classic Jade. Recover overhangs and peaks and on the side trim, check all sills & casings, replace where ever needed, caulk & seal around windows and doors, install aluminum door. This job is guaranteed for labor and material.”

After one outer side of the defendants’ home had been sided, a dispute arose over the type of aluminum siding used. The siding put on was hollow. The plaintiff, TriState, claimed the hollow siding complied with the contract, but to avoid the dispute it removed the hollow siding and replaced it with insulated backer board siding.

Another dispute developed concerning the overhangs, peaks and side trim, the replacement of sills and casings and the caulking and sealing around the doors and windows. This dispute was unresolved. Tri-State’s position was that it had completed the contract as of May 30,1972. The Mansavages maintained the contract had not been completed and relied on the contract provision that payment was not due until thirty days after the completion of the contract. Tri-State demanded payment. Man-savages refused to make any payment at all.

The contract contained a notice of lien rights provision. In September of 1972, Tri-State filed its Notice of Lien, commenced this action in November of 1972, and filed a Notice of Lis Pendens. An amended complaint was filed in December of 1972. The Mansavages filed an answer and counterclaim in March of 1973. Subsequently they *655 retained different counsel and amended their answer and counterclaim. The amended answer affirmatively alleged the contract had not been performed and listed the deficiencies set forth above. The counterclaim alleged violations of the Administrative Code by Tri-State in representations made to induce the contract and deficiencies of the contract. The matter was tried to the court without a jury in October of 1974. A judgment dismissing Tri-State’s complaint upon its merits was entered April 4, 1975; and a judgment dismissing the counterclaim of the Mansavages was entered July 3, 1975.

Tri-State argues that it fully complied with all terms of the contract and is entitled to lien foreclosure judgment. On review, this court will sustain findings of fact unless they are against the great weight and clear preponderance of the evidence. 1 “ ‘ “A trial court’s finding of fact made on conflicting evidence should not be set aside if a judicial mind could, on due consideration of the evidence as a whole, reasonably have reached that conclusion. . . .” ’ ” Precision Service Co. v. Schill, 60 Wis.2d 346, 348, 210 N.W.2d 706 (1973). The court found that Tri-State unjustifiably refused to complete the contract with respect to the uncovered overhang. It also found that work on a third floor windowsill was not in conformity with the contract, and that all the windows were not caulked properly. Testimony that windows were not properly repaired and that overhangs were not covered was offered. This testimony supports the finding that Tri-State did not fully comply with the contract. The findings were not against the great weight and clear preponderance of the evidence and must be upheld.

*656 The court found the damages for the failure to perform the contract were $508.75. Tri-State contends that this figure is not supported by the record. This figure was supplied by David Kahn, a Tri-State employee. It was Kahn who originally estimated the $2,500 contract cost of siding and repairing the Mansavage residence. He stated that $508.75 would be the 1972 cost of covering or repairing those items that the Mansavages contended should have been covered or repaired pursuant to the contract. The court found that the contract provided the disputed items were to be covered or repaired.

“The general principle regarding the measure of damages for defects and omissions in the performance of building contracts is simply that the party is entitled to have what he contracts for or its equivalent. . . [T]he equivalent is sometimes held to be the cost of making the work conform to the contract.” De Sombre v. Bickel, 18 Wis.2d 390, 398, 118 N.W.2d 868 (1963).

A finding that $508.75 was the amount necessary complete the repairs that should have been made under the contract, but were not, is not against the great weight and clear preponderance of the evidence.

Tri-State further contends that it is entitled to recover under the doctrine of substantial performance.

“The doctrine of substantial performance is an equitable doctrine and constitutes an exception in building contracts to the general rule requiring complete performance of the contract. . . . [T]he contractor must make a good faith effort to perform and substantially perform his agreement ....

“[Substantial performance should be granted in cases of incompleteness only when such details are inconsider *657 able and not the fault of the contractor.” Kreyer v. Driscoll, 39 Wis.2d 540, 544-45, 159 N.W.2d 680 (1968).

The trial court made no specific finding concerning whether Tri-State substantially performed the contract. However, implicit in a finding that Tri-State did not perform the contract is a finding that it did not substantially perform. We presume the trial court was aware that if Tri-State had substantially performed it was entitled to recover on the contract.

Reviewing the record, it would be difficult to conclude that those areas not covered by siding or repaired were inconsiderable details. Moreover, the failure to perform was the fault of the contractor. The cost of the additional repairs was $508.75, one-fifth of the total contract price. We cannot hold as a matter of law that performing four-fifths of the contract was substantial compliance. The plaintiff’s defaults were not inconsiderable. We agree that the contract was not substantially performed. Without substantial performance of the contract it follows that judgment of foreclosure of the lien could not be granted and the complaint was properly dismissed as to that cause of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bich v. WW3 LLC
E.D. Wisconsin, 2022
Wisconsin Manufacturers and Commerce v. Tony Evers
2022 WI 38 (Wisconsin Supreme Court, 2022)
Jim Olson Motors, Inc. v. Michael Cole
Court of Appeals of Wisconsin, 2020
Lindquist Ford, Inc. v. Middleton Motors, Inc.
557 F.3d 469 (Seventh Circuit, 2009)
MacH v. Allison
2003 WI App 11 (Court of Appeals of Wisconsin, 2002)
Webb v. B.C. Rogers Poultry, Inc.
174 F.3d 697 (Fifth Circuit, 1999)
Jacob v. West Bend Mutual Insurance
553 N.W.2d 800 (Court of Appeals of Wisconsin, 1996)
Green Spring Farms v. Spring Green Farms Associates Ltd. Partnership
492 N.W.2d 392 (Court of Appeals of Wisconsin, 1992)
Stuart v. Stuart
410 N.W.2d 632 (Court of Appeals of Wisconsin, 1987)
State v. Excel Management Services, Inc.
331 N.W.2d 312 (Wisconsin Supreme Court, 1983)
Cook v. Jacklitch & Sons, Inc.
315 N.W.2d 660 (North Dakota Supreme Court, 1982)
Goebel v. National Exchangors, Inc.
277 N.W.2d 755 (Wisconsin Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
253 N.W.2d 474, 77 Wis. 2d 648, 1977 Wisc. LEXIS 1324, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-state-home-improvement-co-v-mansavage-wis-1977.