De Sombre v. Bickel

18 Wis. 2d 390
CourtWisconsin Supreme Court
DecidedJanuary 8, 1963
StatusPublished
Cited by17 cases

This text of 18 Wis. 2d 390 (De Sombre v. Bickel) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
De Sombre v. Bickel, 18 Wis. 2d 390 (Wis. 1963).

Opinion

Hallows, J.

Appellant complains of the following defects and faulty workmanship: Failure to provide slip-expansion joints on the fascia; the using of one-inch-square tubing instead of wrought-iron three-quarter-inch bars on the metal railing of the roof; failure to paint the underside of all tin and galvanized-metal work; failure to provide a gravity-type screened vent above the roof; failure to design the roof to provide sufficient ventilation to prevent condensation ; construction of a window on the first floor of the building so it did not open; designing of the building so an interior partition wall abutted the window and could be seen from the outside; failure to soundproof certain interior walls; raising the elevation of the building 11 inches higher than originally planned, and failure to complete the first floor of the building for occupancy by October 1, 1959.

Relying on Plante v. Jacobs (1960), 10 Wis. (2d) 567, 103 N. W. (2d) 296, the appellant claims the contractor did not substantially perform his contract, especially in reference to the failure to soundproof certain interior walls in accordance with the plans and specifications. In the Plante Case, we stated substantial performance as applied to the construction of a house did not mean every detail must be in strict compliance with the plans and specifications and something less than perfection was the test unless all details were made the essence of the contract. We also pointed out there may be situations in which some features or details of construction were of such special or great personal importance that if not strictly performed would prevent a finding of substantial performance of the contract. In the instant case, specifications for several interior walls called for sound *394 proofing “equal to Balsam Wool.” This required 2x4 studding to be staggered and the blanket type of acoustical insulation to be woven in and out of the studding. Instead of this, the contractor used 2x6 studs and did not stagger them. This defect was noticed by the architect on August 10th prior to the completion of the walls. The contractor completed the walls by putting a blanket of felt over the studding before putting on rock lath and plaster. At a meeting of the owner, contractor, and architect on October 20th, it was decided to fill the space between the studding of the then completed walls with a granulated insulation called “Zonolite.”

There is evidence to the effect the acoustical properties of the wall as finally constructed were the equivalent of a wall built according to the plans and specifications. The owner intended, this building to be a multipurpose building and the building was planned and constructed so it could be converted into apartments. The soundproofed wall on the first floor divided future apartments. The failure to follow the plans and specifications in view of the corrections used and the result obtained cannot be said to amount to a failure to substantially perform the contract within the rule of the Plante Case. The means of soundproofing was not as important as the end sought to be attained. Soundproofing equal to that provided by Balsam Wool was achieved. The owner received a building substantially for which he contracted and fit for the purposes and uses he expected to make of it. Much-more compliance is found in this contract than was found in the Plante Case.

It is argued that slip-expansion joints were omitted from the metal flashings. The contract provided for copper flash-ings, fascias, and copings with slip-expansion joints and for an alternative substitution of tin and galvanized iron. The appellant chose the alternative and saved some $440. There *395 is testimony copper expands one and one-half times more than galvanized iron and while expansion joints are used with copper, they are not usually provided or needed with galvanized iron flashings and fascias. The trial court was not in error in finding no breach of the contract.

The specifications required the metal railing on the roof to be wrought-iron three-fourth-inch bars welded. Instead of this, one-inch-square tubing was used. There is a dispute over the meaning of wrought iron. Assuming this to be a minor breach of the contract, no damages were proven because of the substitution.

All tin and galvanized-metal work was to be painted on the underside with iron mineral paint, which was not done. It is claimed the paint on the metal work is peeling off because there was no undercoating. Damages of $15 were proven and allowed by the trial court. The appellant claims this is not sufficient compensation but under either the cost-of-repair or the diminished-value rules there is no proof of damages in excess of $15.

The appellant claims the ventilator on the roof above the dry-cleaning unit was not an approved-type gravity ventilator, but rather a cap on a ventilator with no screen. There is dispute in the evidence whether the ventilator supplied complied with the plans and specifications. The cost of replacing this ventilator with one acceptable to the appellant was not proven.

The trial court held there was no delay in the completion of the first floor of the building by October 1st for which the contractor was responsible and time was not of the essence of the contract. The contract provided the construction work should be substantially completed by October 1st and “the first floor to be finished first and must be fully ready for occupancy by October 1, 1959.” The appellant could not occupy the first floor until the end of November and suffered damages of $250 because of the delay. It is *396 claimed one week’s delay was caused by a sewer problem, one month because a boiler was not delivered, and two weeks by summer storms. We can agree that time was not of the essence of the contract. The mere stating of a date for performance is not sufficient to make time of the essence. Buntrock v. Hoffman (1922), 178 Wis. 5, 189 N. W. 572; Rottman v. Endejan (1959), 6 Wis. (2d) 221, 94 N. W. (2d) 596. That is immaterial since the appellant is not attempting to rescind the contract. When time is made of the essence of the contract, either by its terms or by the conduct of the parties, late performance does not fulfil the requirements of the contract and gives rise to a right in the innocent party to rescind the contract or relieves him from performance. Here the doctrine of substantial performance is applicable. A promisor may be liable in damages for late performance amounting to substantial performance even though the promisee has no right to avoid his own obligation on the contract. 9 Am. Jur., Building & Construction Contracts, p. 36, sec. 48; 12 Am. Jur., Contracts, p. 912, sec. 349.

A delay which is not the fault of the promisor does not necessarily relieve him from liability for damages. Parties may contract with reference to supervening difficulties. The wording of this contract in the light of accompanying circumstances manifests an intention the first floor of the building would be fully completed and ready for occupancy on October 1st although the building as a whole might not be substantially completed. We are unable to read into this contract an implied condition qualifying the contractor’s promise of performance because of matters beyond his fault or control.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jacob v. West Bend Mutual Insurance
553 N.W.2d 800 (Court of Appeals of Wisconsin, 1996)
Production Credit Asso. of Madison v. Nowatzski
280 N.W.2d 118 (Wisconsin Supreme Court, 1979)
Kuhlman, Inc. v. G. Heileman Brew. Co., Inc.
266 N.W.2d 382 (Wisconsin Supreme Court, 1978)
Klug & Smith Co. v. Sommer
265 N.W.2d 269 (Wisconsin Supreme Court, 1978)
McKenzie v. Warmka
260 N.W.2d 752 (Wisconsin Supreme Court, 1978)
Pleasure Time, Inc. v. Kuss
254 N.W.2d 463 (Wisconsin Supreme Court, 1977)
Tri-State Home Improvement Co. v. Mansavage
253 N.W.2d 474 (Wisconsin Supreme Court, 1977)
Kraemer Bros. v. Prepakt Concrete Co.
432 F. Supp. 462 (W.D. Wisconsin, 1977)
Gonis v. New York Life Insurance
236 N.W.2d 273 (Wisconsin Supreme Court, 1975)
Laska v. Steinpreis
231 N.W.2d 196 (Wisconsin Supreme Court, 1975)
Stevens Construction Corp. v. Carolina Corp.
217 N.W.2d 291 (Wisconsin Supreme Court, 1974)
Carter v. Sherburne Corporation
315 A.2d 870 (Supreme Court of Vermont, 1974)
Wisconsin Brick and Block Corp. v. Vogel
195 N.W.2d 664 (Wisconsin Supreme Court, 1972)
Kreyer v. Driscoll
159 N.W.2d 680 (Wisconsin Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
18 Wis. 2d 390, Counsel Stack Legal Research, https://law.counselstack.com/opinion/de-sombre-v-bickel-wis-1963.