Klug & Smith Co. v. Sommer

265 N.W.2d 269, 83 Wis. 2d 378, 1978 Wisc. LEXIS 996
CourtWisconsin Supreme Court
DecidedMay 2, 1978
Docket75-840
StatusPublished
Cited by28 cases

This text of 265 N.W.2d 269 (Klug & Smith Co. v. Sommer) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Klug & Smith Co. v. Sommer, 265 N.W.2d 269, 83 Wis. 2d 378, 1978 Wisc. LEXIS 996 (Wis. 1978).

Opinion

*381 CALLOW, J.

The only issue on this appeal is whether the trial court erred in permitting the prevailing party, the plaintiff in this breach of contract action, to recover prejudgment interest. The plaintiff is Klug & Smith Company (K & S), a Wisconsin corporation; and the defendants are two partners, William Sommer and Richard Gebhardt, d/b/a Fair Park Ice Arena (the Arena). 1 In June, 1973, K & S agreed to erect a building to house a skating rink at State Fair Park in West Allis, Wisconsin. The contract price agreed upon was approximately $208,000. By mutual agreement of the parties certain “extras” were added to the contract price in the amount of approximately $20,000, for a total contract price of approximately $228,000.

K & S erected the structure, but the Arena held back approximately $102,000 for the reason that K & S had not substantially completed the contract. In an agreement executed on March 26, 1974, the parties attempted to resolve their dispute over completion on or before July 1, 1974. This agreement provided that upon execution the Arena remit all but $67,555.32 of the amount due on the principal contract including extras and that on or before July 1, 1974, the Arena remit the $67,555.32, less the costs of repair of defects and the diminished value of any unrepaired or unrepairable defects as of July 1, 1974. The agreement also provided that the amount due on July 1 would bear interest from the date of the agreement until paid.

Despite the March 26 agreement, the parties could not resolve the dispute by July 1 or any other date. As a result, K & S commenced this suit against the Arena to recover moneys due under the contract in the amount of $67,555.32, the amount withheld pursuant to the March *382 26 agreement. In its answer the Arena alleged that the sums withheld “are equal to or less than the sums necessary to eliminate, correct or complete the contracts.” The Arena further alleged as a setoff that K & S were negligent in the performance of the contract and that the negligence damaged the Arena in an amount equal to or greater than the amount withheld.

The case was tried to a jury. The jury found that K & S did not perform its contract according to the plans and specifications in a proper and workmanlike manner and that the amount of money which would reasonably and fairly compensate the plaintiff for the construction work done for which it has not been paid was $50,500. K & S moved for judgment on the verdict, including prejudgment interest as provided for in the agreement, while the Arena moved for a judgment on the verdict without prejudgment interest. The trial court ruled that K & S was entitled to prejudgment interest in the amount of $4,739.85. The Arena has appealed.

In a proper case prejudgment interest 2 can be recovered as an element of compensatory damages. Wyandotte Chemicals Corp. v. Royal Electric Mfg., 66 Wis.2d 577, 582, 225 N.W.2d 648 (1975); Laycock v. Parker, 103 Wis. 161, 179-181, 79 N.W. 327 (1899). In addition, when the parties explicitly agree, either in their principal contract or in a supplementary stipulation or agreement, that damages will or will not include prejudgment interest, the parties will be held to that agreement, whether or not interest would be proper without such an agreement. See, e.g., Kleinschmidt v. Aluminum & Bronze Foundry, 274 Wis. 231, 79 N.W.2d 802 (1956); Wyandotte Chemicals Corp. v. Royal Electric Mfg., supra.

*383 The provisions concerning interest in the March 26 agreement are as follows:

“7. That the sums due and owing from Arena to K & S on July 1,197k shall bear interest at the legal rate from the date of this Agreement until paid; that it is understood and agreed by and between the parties that the amount being withheld on the principal contract represents the following estimated contract costs:
1. Building minus structural steel frame and inner liner panels $28,123.69;
2. Insulation $ 4,512.28;
3. Erection of remaining portion of building $13,200.00;
4. Cost of tear down $13,200.00;
5. Cost of removal of inner liner panels $ 1,900.00;
6. Erection of inner liner panels $ 1,900.00
Total tt $62,835.97;
“9. That it is further understood that in the event the parties can mutually agree on the existence of substantial completion prior to July 1, 197k, such sums as are due and owing from Arena to K & S in accordance with the foregoing provisions of this Agreement shall be immediately payable and which sums shall bear interest at the legal rate from the date of this Agreement until paid.” (Emphasis supplied.)

The trial court interpreted these provisions, by which the Arena agreed that “ [all] sums as are due and owing . . . shall bear interest . . . until paid,” to provide for the payment of prejudgment interest. The Arena, however, contends that the trial court’s interpretation of the agreement is wrong. It argues that the parties intended to provide for the payment of interest only if the dispute was solved on or before July 1, 1974, and that the agreement was not intended to establish the conduct of the parties in the event the dispute remained unsolved. We can suggest a third and equally plausible interpretation: *384 that the parties never foresaw that they might fail to settle the dispute pursuant to the agreement and that the dispute would be litigated.

There was no hearing on the issue of prejudgment interest. Except for the agreement itself, the only evidence before the trial court of the intent of the parties was the conflicting declarations of the parties themselves. Further, the Arena did not include the trial transcript in the appeal record, and any evidence in the transcript bearing upon the parties’ intention in executing the March 26 agreement is not before this court.

We think the trial court’s interpretation of the agreement is a reasonable one, and the record provides little basis for setting it aside. However, the proper interpretation of the agreement is irrelevant in this case because, even if we accept the Arena’s interpfeation, i.e., that the parties did not agree to pay interest if the dispute remained unsolved after July 1, 1974, the award of prejudgment interest was proper. If the question of prejudgment interest is not governed by the agreement, then it is governed by our rules for the recovery of prejudgment interest; and those rules permit the award of prejudgment interest in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M & D Truck & Equipment Sales LLC v. Daniel Amarei
Court of Appeals of Wisconsin, 2026
Krizan v. Krizan
W.D. Wisconsin, 2021
Yim C. Hear v. Superior Restaurant Company, LLC
Court of Appeals of Wisconsin, 2020
State v. Ryan M. Muth
2020 WI 65 (Wisconsin Supreme Court, 2020)
Estate of Kevin L. Payette v. David E. Marx
2020 WI App 2 (Court of Appeals of Wisconsin, 2019)
W. Jerome Frautschi v. Ecolab, Inc.
Court of Chancery of Delaware, 2018
Winston v. Guelzow
2014 WI App 96 (Court of Appeals of Wisconsin, 2014)
Staver v. Milwaukee County
2006 WI App 33 (Court of Appeals of Wisconsin, 2006)
DeWitt Ross & Stevens, S.C. v. Galaxy Gaming & Racing Ltd. Partnership
2003 WI App 190 (Court of Appeals of Wisconsin, 2003)
Wisconsin Alumni Research Foundation v. General Electric Co.
880 F. Supp. 1266 (E.D. Wisconsin, 1995)
United States Fire Insurance v. Good Humor Corp.
496 N.W.2d 730 (Court of Appeals of Wisconsin, 1993)
Nankin v. Beverly Enterprises Wisconsin, Inc.
774 F. Supp. 540 (E.D. Wisconsin, 1991)
D'Huyvetter v. A.O. Smith Harvestore Products
475 N.W.2d 587 (Court of Appeals of Wisconsin, 1991)
Tony Spychalla Farms, Inc. v. Hopkins Agricultural Chemical Co.
444 N.W.2d 743 (Court of Appeals of Wisconsin, 1989)
Holy Family Catholic Congregation v. Stubenrauch Associates, Inc.
402 N.W.2d 382 (Court of Appeals of Wisconsin, 1987)
Production Credit Ass'n v. Jacobson
388 N.W.2d 655 (Court of Appeals of Wisconsin, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
265 N.W.2d 269, 83 Wis. 2d 378, 1978 Wisc. LEXIS 996, Counsel Stack Legal Research, https://law.counselstack.com/opinion/klug-smith-co-v-sommer-wis-1978.