Wyandotte Chemicals Corp. v. Royal Electric Manufacturing Company, Inc.

225 N.W.2d 648, 66 Wis. 2d 577, 1975 Wisc. LEXIS 1681
CourtWisconsin Supreme Court
DecidedFebruary 4, 1975
Docket277
StatusPublished
Cited by56 cases

This text of 225 N.W.2d 648 (Wyandotte Chemicals Corp. v. Royal Electric Manufacturing Company, Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wyandotte Chemicals Corp. v. Royal Electric Manufacturing Company, Inc., 225 N.W.2d 648, 66 Wis. 2d 577, 1975 Wisc. LEXIS 1681 (Wis. 1975).

Opinion

Connor T. Hansen, J.

The principal issue on this appeal relates to that portion of the judgment which denied the plaintiffs’ demand for preverdict interest. There is no dispute as to the amount of the actual damages. The damage question in the special verdict was answered by the trial court pursuant to stipulation of the parties. Also, no issue is raised as to the rights of any insurer.

The damage to the property occurred on May 17, 1967. After a five-day jury trial, the jury returned their special *581 verdict on December 8, 1972. Royal and Thomas were subcontractors engaged in the installation of some equipment fabricated by Schuler. The damage to plaintiffs’ property arose during the installation of this equipment.

The action was originally commenced against Royal and Thomas. Schuler was subsequently impleaded as a third-party defendant by Royal. Approximately one month before the trial, on motion of the plaintiffs, the court ordered that Schuler be made a principal defendant. The plaintiffs alleged the three respondents were jointly and severally liable. Royal, Thomas and Schuler denied liability.

The jury found each of the three respondents causally negligent, and attributed 25 percent of the causal negligence to Royal, 25 percent to Thomas, and 50 percent to Schuler.

Following entry of the judgment on April 9, 1973, the defendants paid the amount due to the clerk of courts. Pursuant to an Order Correcting Clerical Omission In Judgment, the judgment was amended on May 7, 1973, to specifically reflect the denial of preverdict interest. The clerk then applied the defendants’ payments to the judgment, satisfying the same on May 30,1973.

The plaintiffs claim that the actual amount of the damages became liquidable, certain, and capable of determination on November 16, 1967, and that appropriate demand for payment was made on that date. There does not appear to be a material dispute as to these facts, especially as to Royal and Thomas. In this case, however, the dispute goes to the question of the respective liability of the three respondents and the apportionment of causal negligence, if any, among them.

The recent decision of Dahl v. Housing Authority of the City of Madison (1972), 54 Wis. 2d 22, 194 N. W. 2d 618, considered the question of preverdict interest and cited Laycock v. Parker (1899), 103 Wis. 161, 79 N. W. 327.

*582 In Laycock v. Parker, supra, this court, after review of prior case authority, set forth the basic rules governing the recovery of preverdict interest. In Laycock it was noted that originally interest was recoverable only as a penalty or punishment for the wrongdoer’s refusal to pay liquidated damages which were legally due. Laycock, supra, page 179: It was recognized, however, that more recent legal authorities had come to regard interest not just as a penalty but as an element of compensation necessary to make the injured party whole. This trend in the law paralleled the growing acceptance in the commercial world of interest as a measure of the time value of money. Laycock, supra, pages 179-181. Thus, it was determined by this court that the awarding of interest should not be strictly limited to the instance of liquidated damages, but should also extend to those cases where the amount of damages is determinable, i.e., where “there be a reasonably certain standard of measurement by the correct application of which one can ascertain the amount he owes . . . .” Laycock, supra, page 186. Applying that rule to the facts in Laycock, this court awarded prejudgment interest where the items of damage claimed involved the costs of materials and labor necessary to complete a building.

While this standard was an extension of the rule as theretofore applied, the rule was a compromise between the two conflicting theories of interest recovery. The idea that interest was recoverable only in the instance where the money was wrongfully withheld from the injured party was not totally abandoned. Rather, in accommodating the view that interest was recoverable as an element of compensation, this court expanded the notion of what conduct was wrongful by placing on the withholding party the duty of ascertaining the value of the damages where an adequate standard of measurement was available reasonably permitting him to do so. The fact that this court still considered the rights of the withholding party as *583 being important was specifically noted when it was stated in Laycock, supra, pages 186, 187:

“. . . If one having a commodity to purchase or certain services to hire can by inquiry among those familiar with the subject learn approximately the current prices which he would have to pay therefor, a market value can well be said to exist, so that no serious inequity will result from the application of the foregoing rule to those who desire to act justly; especially in view of the other rule of law that a debtor can always stop interest by making and keeping good an unconditional tender, thus giving him a substantial advantage over a creditor, who has no such option.”

Cases decided subsequent to Laycock, while expressly relying on the theory that interest can be recovered as an item of compensatory damages, have followed a middle ground between the two conflicting policies.

In Necedah Mfg. Corp. v. Juneau County (1932), 206 Wis. 316, 237 N. W. 277, 240 N. W. 405, this court permitted recovery of preverdict interest in a negligence case where the damages claimed involved items of property destroyed by fire for which there was a reasonably certain standard for valuation available to the defendant before trial. The items had been assigned tax values which were essentially the same as the values ultimately found by the jury. So too, in Maslow Cooperage Corp. v. Weeks Pickle Co. (1955), 270 Wis. 179, 70 N. W. 2d 577, and Giffen v. Tigerton Lumber Co. (1965), 26 Wis. 2d 327, 132 N. W. 2d 572, this court permitted the recovery of prejudgment interest where in each case it was shown that there was some available means by which the withholding party could determine the amount owed so that that amount could be tendered and interest halted. Moreover, in De Toro v. DI-LA-CH, Inc. (1966), 31 Wis. 2d 29, 142 N. W. 2d 192, it was recognized that interest was recoverable on an otherwise liquidable claim despite the existence of an unliquidated setoff, counterclaim or cross-claim. Essential to De Toro is the notion that an inde *584 pendent claim in the form of a setoff, counterclaim or cross-claim does not in itself affect the value of the damages being withheld from the injured party but merely results in the mathematical crediting of one independent claim against a competing independent claim after each has been fully established to the satisfaction of the court.

On the other hand, a claim of prejudgment or pre-verdict interest has been denied in cases where the value of the amount withheld was “determinable” under the standard Laycock

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Catherine F. Conway v. Douglas H. Frazer
Court of Appeals of Wisconsin, 2026
V.K. v. D. J. F.
Court of Appeals of Wisconsin, 2025
Yim C. Hear v. Superior Restaurant Company, LLC
Court of Appeals of Wisconsin, 2020
Waukesha County v. H.M.B.
Court of Appeals of Wisconsin, 2020
Shockley v. Comm'r
2016 T.C. Memo. 8 (U.S. Tax Court, 2016)
Christopher T. Beidel v. Sideline Software, Inc.
2013 WI 56 (Wisconsin Supreme Court, 2013)
Trease v. Tri-State Adjustments, Inc.
934 F. Supp. 2d 1016 (E.D. Wisconsin, 2013)
Northern Air Services, Inc. v. Link
2011 WI 75 (Wisconsin Supreme Court, 2011)
Davis v. Countrywide Home Loans, Inc.
683 N.W.2d 93 (Court of Appeals of Wisconsin, 2004)
DeWitt Ross & Stevens, S.C. v. Galaxy Gaming & Racing Ltd. Partnership
2003 WI App 190 (Court of Appeals of Wisconsin, 2003)
Teff v. Unity Health Plans Ins. Corp.
2003 WI App 115 (Court of Appeals of Wisconsin, 2003)
Totsky v. Riteway Bus Service, Inc.
2000 WI 29 (Wisconsin Supreme Court, 2000)
GMAC Mortgage Corp. v. Gisvold
572 N.W.2d 466 (Wisconsin Supreme Court, 1998)
Riley v. Lawson
565 N.W.2d 266 (Court of Appeals of Wisconsin, 1997)
Wisconsin Alumni Research Foundation v. General Electric Co.
880 F. Supp. 1266 (E.D. Wisconsin, 1995)
Beacon Bowl, Inc. v. Wisconsin Electric Power Co.
501 N.W.2d 788 (Wisconsin Supreme Court, 1993)
R.S. Deering Mechanical Contractors v. Livesey Co.
468 N.W.2d 758 (Court of Appeals of Wisconsin, 1991)
Gertsch v. International Equity Research
463 N.W.2d 853 (Court of Appeals of Wisconsin, 1990)
In Matter of Estate of Katze-Miller
463 N.W.2d 853 (Court of Appeals of Wisconsin, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
225 N.W.2d 648, 66 Wis. 2d 577, 1975 Wisc. LEXIS 1681, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wyandotte-chemicals-corp-v-royal-electric-manufacturing-company-inc-wis-1975.