Dahl v. Housing Authority of the City of Madison

194 N.W.2d 618, 54 Wis. 2d 22, 1972 Wisc. LEXIS 1048
Wisconsin Supreme Court·Decided February 29, 1972·No. 160·Published·Cited by 12 cases

Opinion

Robert W. Hansen, J.

Two issues, and two issues only, are raised on this appeal. The first relates to the contractor’s claim to $12,120 for removal of peat and backfill with sand under certain footings in the construction project. The second involves the right of the contractor to interest on sums ordered paid in the judgment. Each will be taken up in turn.

Removal and backfill claim.

At construction site “C,” one of four covered by the contract, a construction problem was presented by the presence of peat soil under the footings of the proposed construction. This fact was known to the Housing Au *25 thority and to its architect. 1 While the architect’s plan drawings show the footings of the foundation at site “C” to be two to five feet above the layer of peat, no provision for meeting the problem presented was made on the plans. However, Division 2 (10) of the specifications sets forth:

“. . . On Site ‘C,’ soil investigation indicates a layer of peat. Where footings and foundations occur in this material or immediately above, remove the peat to its full depth and fill with granular material and compact to 95 °/o compaction . . . .”

No additional compensation to the contractor is suggested or provided for such removal and backfilling operation. Another section of the specifications, Division 3(7), provides:

“. . . All footings to rest on undisturbed soil. If necessary, foundations may be required to greater depths than shown. If work is ordered by Local Authority, its cost will be determined on basis of unit prices established in the Special Conditions.”

Additionally, there is in the specifications General Condition 10 (g) providing:

“g. During the progress of the work, if the Contractor encounters at the site (1) subsurface or latent physical conditions differing materially from those indicated in the Contract or (2) unknown physical conditions differing materially from those inhering in work of the character provided for in this Contract, he shall promptly, and before such conditions are disturbed, notify the Contracting Officer in writing. . . . The Contracting Officer shall thereupon promptly investigate such conditions and if he finds that they do materially differ he shall cause such changes to be made in the Specifications *26 and Drawings as he may deem necessary, if any, and shall make such equitable adjustment in the contract price or time as is justified . . . .”

Shortly after the awarding of the contract, the digging of a utility trench at site “C” revealed that the soil, due to the layer of peat, would not bear the footings. Treating this situation as an . . unknown physical condition differing materially from those inhering in work of the character provided for in this Contract, . . .” the contractor wrote a letter to the Housing Authority outlining the problem and requesting determination by the Authority as to the procedure to be followed. The Housing Authority responded that Division 2 (10) of the specifications required the removal of the peat under the footing and backfilling with sand by the contractor without additional compensation. At a meeting of contractor, Authority and architect, the contractor was directed to remove the peat and backfill with compacted sand. On the day of the meeting, the contractor sent the Housing Authority a formal notice of dispute, contending that the removal and backfill was beyond the scope of the contract and specifications, and demanding additional compensation. 2

So, very early in the ball game, not only the fact of dispute but the exact position of each disputant became clear. At the first meeting on the dispute, as later before the trial court and now before us, the contractor contends that the peat at site “C” was an “unknown physical condition” governed by General Condition 10 (g) of the specifications for the removal of which he is entitled to extra compensation. Now, as then, the Housing Authori *27 ty contends that the peat layer under the footings was a condition covered by the contract and governed by Division 2 (10) of the specifications, and no additional payment due for its removal and the backfilling. The trial court agreed with the Authority finding that the removal and backfilling was “. . . work which plaintiff was required to do under the terms of the contract.”

The conclusion of law reached by the trial court necessarily rests upon a finding of fact that the footings two or more feet above the layer of peat were “immediately above” such footings or foundation. Urging a “nothing intervenes” definition of the term, “immediately above,” the contractor cites a case defining “immediately” to mean that “ ‘it forbids the existence of intervening space.’ ” 3 The Housing Authority urges a broader definition of the word “immediately,” citing a case holding it to mean only “ ‘Being near at hand; not far apart or distant.’ ” 4 One accepted dictionary defines “immediate” to mean: “. . . 4: characterized by contiguity: existing without intervening space or substance . . . broadly: being near at hand: not far apart or distant . . .” 5 However, we do not view the reference here to “immediately above” as a matter of choosing between dictionary or judicial definitions. 6 An airplane a few hundred feet over an airport may well be “immediately above” the landing place. Whether footings two feet above a peat layer are “immediately above” it is to be *28 answered in the light of the specific situation, specific circumstances and specific reference in the specifications. The term is ambiguous and evidence of the surrounding circumstances can be considered in construing the term or determining its applicability. 7 Since the language used in the specifications is reasonably susceptible to different constructions, the sense in which the words are therein used becomes a question of fact. 8

Free access — add to your briefcase to read the full text and ask questions with AI

Dahl v. Housing Authority of the City of Madison, 194 N.W.2d 618, 54 Wis. 2d 22, 1972 Wisc. LEXIS 1048 (Wis. 1972).

194 N.W.2d 618 (Dahl v. Housing Authority of the City of Madison) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Teff v. Unity Health Plans Ins. Corp.
2003 WI App 115 (Court of Appeals of Wisconsin, 2003)
Little v. Roundy's, Inc.
449 N.W.2d 78 (Court of Appeals of Wisconsin, 1989)
Amoco Oil Co. v. Capitol Indemnity Corp.
291 N.W.2d 883 (Court of Appeals of Wisconsin, 1980)
Klug & Smith Co. v. Sommer
265 N.W.2d 269 (Wisconsin Supreme Court, 1978)
Olguin v. Allstate Insurance
237 N.W.2d 694 (Wisconsin Supreme Court, 1976)
Kilgust Heating Division of Wolff, Kubly & Hirsig, Inc. v. Kemp
235 N.W.2d 292 (Wisconsin Supreme Court, 1975)
State Ex Rel. Schilling & Klingler v. Baird
222 N.W.2d 666 (Wisconsin Supreme Court, 1974)
Stevens Construction Corp. v. Carolina Corp.
217 N.W.2d 291 (Wisconsin Supreme Court, 1974)