Fattore Company, Inc. v. Metropolitan Sewerage Commission of the County of Milwaukee

505 F.2d 1, 1974 U.S. App. LEXIS 6335
CourtCourt of Appeals for the Seventh Circuit
DecidedOctober 25, 1974
Docket73-1660 and 73-1661
StatusPublished
Cited by26 cases

This text of 505 F.2d 1 (Fattore Company, Inc. v. Metropolitan Sewerage Commission of the County of Milwaukee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fattore Company, Inc. v. Metropolitan Sewerage Commission of the County of Milwaukee, 505 F.2d 1, 1974 U.S. App. LEXIS 6335 (7th Cir. 1974).

Opinion

LARAMORE, Senior Judge.

This case is before the court- on appeal by each party; both the plaintiff and defendant requesting review of the District Court’s findings regarding damages due and the defendant also requesting review of a finding favoring the payment of prejudgment interest. 1

*3 The main issues in this case are the amount of damages under a changed condition and equitable adjustment provision of a municipal government construction contract and prejudgment interest on such a claim. The District Court, after carefully considering the evidence in its totality, found plaintiff entitled to a “jury verdict” equitable adjustment of $1,500,000. The finding was based on this court’s reasoning in the first appeal that a broad exculpatory clause should not operate to render another clause meaningless, freeing defendant from its liability. 2 The judgment included superintendence, overhead expense, home office expense, profit and any and all other items aside from interest. Prejudgment interest was awarded at the rate of five per cent per annum from and after June 18, 1964, 3 the date all plaintiff’s accounting data necessary to compute the equitable adjustment under the changed conditions clause was complete and the retained percentage was paid.

Plaintiff presented its damages, 4 in a very detailed accounting, as the difference between the actual costs 5 incurred, adjusted downward for events unrelated 6 to the changed condition, and its bid. 7 Plaintiff argues its method for computing damages is the most reliable and is clearly supported by the evidence; therefore, the “jury” type verdict awarded is inappropriate, surpassed by plaintiff’s proof. In effect, plaintiff contends that it used reasonable costs, not total costs, because it only used items affected by the changed conditions. Accordingly, the increase in cost was directly related to the increase in time required to complete the contract due to the changed condition. 8 Plaintiff also contends that it is correct and has always been appropriate for an equitable adjustment to include a profit 9 because it would be “inequitable” for one to do two extra years work under the circumstances involved in this case, with a substantial increase in investment, for no additional return.

Defendant contends plaintiff, in effect, used the normally unacceptable total cost method of computing damages and that the total cost method is not acceptable because here there is an alternative in reasonable costs which the plaintiff failed to prove. Further, there is no right to recover the costs unreasonably incurred, when the changed geological conditions were discovered, by abandoning the shield technique for hand mining. 10 Accordingly, failure to *4 use the proper proof of damages, reasonable costs, requires dismissal of the case. It is further alleged that even if the equitable adjustment were applicable, it would be error to include profit because such an adjustment should only permit the contractor to break even on extra costs due to changed conditions. The defendant also asserts award of prejudgment interest is contrary to law because there is a genuine dispute regarding the amount due; it cannot be determined with the reasonable certainty necessary to bring it within the definition of liquidable or liquidated damages entitling it to an award of prejudgment interest.

The defendant’s argument aimed at barring correction of a wrong for failure of proof, is untenable based on the principle that a judicially recognized wrong is not a bar to recovery of damages that would be difficult to establish with precision. Given the plaintiff’s adequate proof, including the correlation between the increase in time and expense due to the changed condition, it would be unjust to only permit recovery for a recognized wz’ong by holding plaintiff to a near impossible standard of requiring him to list with mathematical precision the amount of every item of damage flowing from that wrong. See also, Dale Construction Co. v. United States, 161 Ct.Cl. 825 (1963); Luria Bros. & Co. v. United States, 369 F.2d 701, 712-713, 177 Ct.Cl. 676, 695-696 (1966); Adams v. United States, 358 F.2d 986, 993, 175 Ct.Cl. 288, 299 (1966); Specialty Assembling & Packing Co. v. United States, 355 F.2d 554, 572-573, 174 Ct.Cl. 153, 184 (1966).

It is well settled that the one liable for established and proven harm shall not escape monetary responsibility because the one harmed failed to prove his damages with mathematical precision. This view is in consonance with the Supreme Court case, Story Parchment Co. v. Paterson Parchment Paper Co., 282 U.S. 555, at 562-563, 51 S.Ct. 248 at 250, 75 L.Ed. 544 (1931), which stated:

* * The l’ule which precludes the recovery of uncertain damages applies to such as are not the certain result of the wrong, not to those damages which are definitely attributable to the wrong and only uncertain in respect of their amount. * * * it will be enough if the evidence shows the extent of the damages as a matter of just and reasonable inference, although the result be only approximate.

In addition, recognition of defendant’s argument concerning damages would have the effect of negating both the first decision in this case, Fattore Co. v. Metropolitan Sewerage Commission of Milwaukee, supra, which found plaintiff was entitled to relief, and the policy considerations upon which the changed conditions and equitable adjustment provisions az'e based. The purposes for institution and utilization of these two provisions includes eliminating the contractor’s need for placing large contingencies and unknown costs into his pricing for the gz-eat risk he may be taking by encountering adverse subsurface conditions, Kaiser Industries Corporation v. United States, 340 F.2d 322, 169 Ct.Cl. 310 (1965), and providing administrative remedies involving negotiation for what otherwise would amount to a breach of contract requiring litigation for resolution. 11 The bidder will neither enjoy windfalls nor suf *5 fer disaster. The municipal government benefits or pays according to the occurrence of adverse conditions. Foster Construction C. A. & Williams Bros. Co. v. United States, 435 F.2d 873, 887, 193 Ct.Cl. 587, 614 (1970).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Dracopoulos
N.D. California, 2023
Atwood v. Days
D. Arizona, 2023
Johnson v. United States
S.D. California, 2021
Martinez v. Hoff
E.D. California, 2019
G.M. Harston Construction Co. v. City of Chicago
371 F. Supp. 2d 949 (N.D. Illinois, 2005)
Municipality of Anchorage v. Frank Coluccio Construction Co.
826 P.2d 316 (Alaska Supreme Court, 1992)
Allen & O'hara, Inc. v. Barrett Wrecking, Inc.
898 F.2d 512 (Third Circuit, 1990)
Allen & O'Hara, Inc. v. Barrett Wrecking, Inc.
898 F.2d 512 (Seventh Circuit, 1990)
Nebraska Public Power District v. Austin Power, Inc.
773 F.2d 960 (Eighth Circuit, 1985)
New Pueblo Constructors, Inc. v. State
696 P.2d 203 (Court of Appeals of Arizona, 1984)
Highland Construction Co. v. Union Pacific Railroad
683 P.2d 1042 (Utah Supreme Court, 1984)
W. H. Lyman Construction Co. v. Village of Gurnee
403 N.E.2d 1325 (Appellate Court of Illinois, 1980)
Henricksen v. Henricksen
486 F. Supp. 622 (E.D. Wisconsin, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
505 F.2d 1, 1974 U.S. App. LEXIS 6335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fattore-company-inc-v-metropolitan-sewerage-commission-of-the-county-of-ca7-1974.