Brant Construction Co. v. Metropolitan Water Reclamation District of Greater Chicago

967 F.2d 244
CourtCourt of Appeals for the Seventh Circuit
DecidedJuly 17, 1992
DocketNo. 91-1945
StatusPublished
Cited by1 cases

This text of 967 F.2d 244 (Brant Construction Co. v. Metropolitan Water Reclamation District of Greater Chicago) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brant Construction Co. v. Metropolitan Water Reclamation District of Greater Chicago, 967 F.2d 244 (7th Cir. 1992).

Opinion

CUMMINGS, Circuit Judge.

The Metropolitan Sanitary District of Greater Chicago, now known as the Metropolitan Water Reclamation District of Greater Chicago (“Reclamation District”), solicited bids for the construction of its proposed St. Michael Reservoir to be constructed in Palatine, Illinois. The project required the contractor to furnish all materials, labor and equipment necessary for the construction of a 6,000 foot-long earth dam embankment with compaction and to conduct extensive foundation removal beneath it. In conjunction with the bid solicitation, bidders were given notice of the bidding requirements and general specifications. The Reclamation District provided [246]*246the bidders with plans and specifications for the project, as well as the soil borings and soil analyses on which those plans were based. It also provided bidders with the opportunity to conduct further tests of their own.

The construction contract was awarded to the low bidder, a joint venture of Brant Construction Company, Inc. and Dyer Construction Company, Inc. (“Brant-Dyer”). Although the total value of the contract was not certain, Brant-Dyer signed a Contractor’s Bond for seven million, five hundred ninety-six thousand, four hundred sixty-four dollars and seventy-eight cents (Exhibit D at B-l). On item 9 of the Bid Proposal, one of forty-three bid items, Brant-Dyer bid $1.90 per cubic yard for “Common Excavation — Foundation and Permanent Pool.” This bid for “common excavation” was obtained by estimating the amount and cost of two types of excavation that would be required to complete the job — scraper excavation and dragline excavation. Dragline excavation is at least twice as costly as scraper excavation (Joint App. 43).

The Reclamation District originally anticipated common excavation of approximately 518,718 cubic yards of material, but later revised that estimate to 596,192 cubic yards prior to any bidding (Joint App. 60, 75). Of that amount, the Reclamation District estimated that only 18,006 cubic yards of drag-line excavation would be required. (Joint App. 46). However, after Brant-Dyer conducted excavation to the specified level set forth in the plans (the “neat lines”), the Reclamation District’s chief engineer found the soil at that level unsuitable and ordered further excavation beyond the neat lines, viz., “overexcavation.” Ultimately the contractor was required to overexcavate 67,-804 cubic yards of soil, roughly 7% more than the approximate quantity set forth in the contract. Most of that overexcavation involved unsuitable “laucustrine” soils which had to be removed by the more costly dragline method of excavation.

The parties do not dispute the Reclamation District’s responsibility to compensate Brant-Dyer for the overexcavated material. Rather, they dispute the appropriate measure of that compensation. The Reclamation District asserts that it has satisfied its financial obligation to Brant-Dyer because it has paid the basic contract price, $1.90 per cubic yard of material excavated, for the quantity of material actually excavated, including overexcavation. However, Brant-Dyer seeks an additional $187,270.02 for the actual cost of the overexcavation, which cost it estimates to be $4 per cubic yard of soil removed, more than twice the unit price provided by the contract.

The district court assumed jurisdiction over this case based upon diversity of citizenship pursuant to 28 U.S.C. § 1332(a). District Judge Zagel rejected Brant-Dyer’s claims for additional payment under Illinois law and granted the Reclamation District’s motion for summary judgment. On appeal, Brant-Dyer contests that judgment and seeks $187,270.02 for its overexcavation claim. For the reasons set forth below, we affirm the judgment of the district court.

I.

A. Extra Work

Under Illinois law, in order for a contractor to recover money for “extra work,” it must show by clear and convincing evidence that the work was 1) outside the scope of the original contract; 2) ordered at the direction of the owner; 3) agreed to be paid for by the owner either by words or by conduct; 4) not voluntarily furnished by the contractor; and 5) not rendered necessary by fault of the contractor. Chicago College of Osteopathic Medicine v. George A. Fuller Co., 776 F.2d 198 (7th Cir.1985); Berg & Assoc., Inc. v. Nelsen Steel & Wire Co., 221 Ill.App.3d 526, 162 Ill.Dec. 779, 580 N.E.2d 1198 (1st Dist.1991); Duncan v. Cannon, 204 Ill.App.3d 160, 149 Ill.Dec. 451, 452-453, 561 N.E.2d 1147, 1148-1149 (1990); Mayer Paving & Asphalt Co. v. Morse, Inc., 48 Ill.App.3d 73, 8 Ill.Dec. 122, 365 N.E.2d 360 (1st Dist.1977); Strom v. Lipschultz, 5 Ill.App.3d 308, 282 N.E.2d 257 (2d Dist.1972); Watson Lumber v. Guennewig, 79 Ill.App.2d 377, 226 N.E.2d 270 (5th Dist.1967). In this case, both parties agree that four of the [247]*247five factors have been met. However, the parties disagree with respect to the first factor — whether the work done by the contractor was outside the scope of the original contract.

Brant-Dyer asserts that the excavation it performed outside of the Reclamation District’s specified lines and grades, the “neat lines,” fell outside the scope of the contract. Some contractual language appears to support Brant-Dyer’s assertion. For example, the construction specification regarding excavation defines “scope” as follows: “[t]he work shall consist of the excavation required by the drawings and specifications and disposal of the excavated materials” (Joint App. 76). Moreover, the section of the contract regarding payment provides that when unit prices are specified, the price shall include all equipment and labor “necessary to complete the work as specified in the Detail Specifications” (Joint App. 68).

However, the contract does not end there. Instead, the contract explicitly contemplates and resolves the issue of payment for overexcavation when the soil is unsuitable, the matter at issue here. The contract provides that “Regardless of the quantities excavated, the measurement for payment will be made to the specified pay limits, except that excavation outside the specified lines and grades directed by the Engineer to remove unsuitable material will be included, but only to the extent that the unsuitable condition is not a result of the Contractor’s operations” (Joint App. 79). Thus any overexcavation “directed by the Engineer to remove unsuitable material” was contemplated within the scope of the contract.

Brant-Dyer asserts that the question of whether the material removed was actually unsuitable, and therefore within the scope of the contract, is a factual question for a jury, rather than a question to be determined at the sole discretion of the Reclamation District’s chief engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
967 F.2d 244, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brant-construction-co-v-metropolitan-water-reclamation-district-of-ca7-1992.