Chicago College of Osteopathic Medicine v. George A. Fuller Co.

776 F.2d 198
CourtCourt of Appeals for the Seventh Circuit
DecidedNovember 4, 1985
DocketNos. 84-2933, 84-2994
StatusPublished
Cited by33 cases

This text of 776 F.2d 198 (Chicago College of Osteopathic Medicine v. George A. Fuller Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago College of Osteopathic Medicine v. George A. Fuller Co., 776 F.2d 198 (7th Cir. 1985).

Opinion

HARLINGTON WOOD, Jr., Circuit Judge.

The appeal in this diversity jurisdiction case concerns a small portion of a much larger dispute arising over the construction of an out-patient clinic at the Chicago College of Osteopathic Medicine in Hyde Park, Chicago. This court resolved most of the dispute in Chicago College of Osteopathic Medicine v. George A. Fuller Co., 719 F.2d 1335 (7th Cir.1983); however, on the issue whether Ed Hoffman Excavating, Inc. (“Hoffman”), the subcontractor excavator on the project, is entitled to any delay damages from George A. Fuller Co. (“Fuller”), the general contractor, we remanded for additional findings.

In its first decision the district court granted relief to Hoffman for costs incurred consequent to a nine-month delay in excavation of the site, holding that a clause in the subcontract expressly waiving Hoffman’s rights to collect for damages caused by delays (the “Delay Waiver Clause”) did not apply to the extraordinary delays involved in this case. On appeal we reversed, holding that Illinois law did not permit such a narrow construction of the Delay Waiver Clause, and remanded for the district court to consider three other theories upon which relief might be granted to Hoffman: (1) that Fuller waived its rights under the Delay Waiver Clause, (2) that Hoffman met the five-prong test for obtaining payment for extra work, and (3) that the parties orally modified the written contract. Id. at 1340-41. On remand the district court, relying on all three legal theories, held that Fuller was liable to Hoffman in the amount of $180,189. Fuller appeals the finding of liability and the damages determination; Hoffman cross-appeals seeking additional damages.

I. Facts

In 1973 Fuller and Hoffman entered into an agreement (the “Subcontract”) for Hoffman to perform the excavation and backfill work for an out-patient clinic at Chicago College of Osteopathic Medicine. The Subcontract price was $210,000.

Originally, Hoffman was to commence work on November 9, 1973. Because of delays caused by the owner, Chicago College of Osteopathic Medicine (“CCOM”), and the architect, Schmidt, Garden & Erickson (“SGE”), Hoffman did not actually begin work until January 25, 1974. For the next seven months through no fault of its own Hoffman proceeded with the excavation in a sporadic, unorthodox, and more expensive manner. For example, it began work on January 25 by clearing the site, which took about a week. Hoffman then halted work until March 9, 1974, when it began excavation, but only to a depth of five feet in limited areas of the site. Hoffman performed this partial excavation work in eight to ten days. About a month later Hoffman was directed to recommence the excavation; this time Hoffman encountered uncharted sewer lines which halted excavation. Hoffman returned to the site on May 9 only to discover existing fire lines which forced another delay. Delays of this sort continued to plague the excavation project for several more months until August 7, 1984, nine months after excavation was originally scheduled to begin; on that date Hoffman finally began uninterrupted mass excavation, completing the job in three and one-half months.

During the delay period Hoffman wrote to and had several conversations with Full[201]*201er about the delays and the problems the delays were causing Hoffman. In a January 2, 1974 letter Hoffman complained about the delay and asked Fuller to either release Hoffman from its “contractual obligation” or pay the additional charges sought. Fuller orally asked Hoffman “to hang on in good faith” and promised Hoffman that it would be paid for the additional costs that it was incurring as a result of the delays. Tr. 2988. On February 8, 1974, Hoffman wrote to Fuller advising that Hoffman would be seeking additional remuneration because of the delays. In a February, 1974 meeting Fuller assured Hoffman that Article XI, the Delay Waiver Clause,1 which allocated the risk of delay to Hoffman, Fuller, 719 F.2d at 1339-40, did not apply to the extraordinary delays that had occurred, that Fuller would pay for the additional costs that Hoffman was incurring, and that Fuller would attempt to pass on such costs to SGE and CCOM. Tr. 54-59 & 29.

On July 1, 1974, Hoffman wrote a letter to Fuller detailing the problems that had arisen consequent to the delays and asked Fuller to “notify [Hoffman] in writing to cease and desist the excavating work immediately” if Fuller would “not accept or process the additional charges over and above the contract amount which is forth coming (sic).” Fuller never responded in writing but continued to promise orally that it would pay Hoffman for its additional costs. Tr. 2988.

Although delay problems ended on August 25, in their stead arose problems over the storage of excavated material Hoffman hoped to use as backfill material. Under the terms of the Subcontract Hoffman was responsible for providing “materials ... necessary for the proper completion of the ... Backfill work.” Article I. The Subcontract specifications provided, however, that Hoffman could use material excavated from the lowermost layer of the excavation as backfill material provided it met specifications.2 Paragraphs 54 and 55 Exhibit A to the Subcontract allowed Hoffman to stockpile the excavated backfill material on the job site provided space was available and imposed on it any expense of relocation of the sand.3

Initially space was available at the job site for stockpiling the backfill material and Hoffman took advantage of it. In September, 1974, however, the stockpiled material began to create a safety hazard and Fuller told Hoffman to remove the material. Hoffman refused to remove the sand until Fuller had agreed to pay for extra costs incurred and provided Hoffman an alternative storage site a block away. Later, Fuller directed Hoffman to remove the material from the alternative storage site. Hoffman again refused to remove the material until Fuller promised additional compensation. This time, rather than move the sand to another location, Hoffman sold it for about $9,000. When it came time to backfill the CCOM job Hoffman replaced the sand it had sold with sand it had excavated at the Brain Research project, another excavation project in the area that Hoffman was working on.

On these facts Judge Leighton held (1) that Fuller waived its right under Article [202]*202XXXIV to insist that all waivers and modification be in writing,4 its right under Article XI, the Delay Waiver Clause, to be free from liability for costs of delay incurred by Hoffman, and its right under paragraphs 10 and 35 of Exhibit A to insist that Hoffman bear the costs occasioned by being forced to perform the work out of sequence or in an otherwise unorthodox fashion;5 (2) that Fuller and Hoffman orally modified the terms of the subcontract;6 and (3) that Hoffman met the five-prong test for obtaining extra pay for providing replacement sand for backfill. Judge Leighton awarded Hoffman $180,189, $85,539 to cover the cost of doing the excavation work and $94,650 for providing the replacement backfill sand.

II. Liability for Delay Damages

We first review Judge Leighton’s finding that Fuller waived its rights under the Subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GW 3800 Milwaukee, LLC v. Bloom Bounce, LLC
2025 IL App (1st) 241461-U (Appellate Court of Illinois, 2025)
Wisconsin Electric Power Co. v. Union Pacific Railroad
557 F.3d 504 (Seventh Circuit, 2009)
City of Philadelphia v. One Reading Center Associates
143 F. Supp. 2d 508 (E.D. Pennsylvania, 2001)
Doyle v. Holy Cross Hospital
708 N.E.2d 1140 (Illinois Supreme Court, 1999)
Gupta v. Freixenet, USA, Inc.
908 F. Supp. 557 (N.D. Illinois, 1995)
Hindin/Owen/Engelke, Inc. v. GRM Industries, Inc.
869 F. Supp. 539 (N.D. Illinois, 1994)
Joe Cooper & Assoc. v. Central Life
614 So. 2d 982 (Supreme Court of Alabama, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
776 F.2d 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-college-of-osteopathic-medicine-v-george-a-fuller-co-ca7-1985.