Delta Construction, Inc. v. Dressler

381 N.E.2d 1023, 64 Ill. App. 3d 867, 21 Ill. Dec. 576, 1978 Ill. App. LEXIS 3358
CourtAppellate Court of Illinois
DecidedOctober 18, 1978
Docket78-13
StatusPublished
Cited by13 cases

This text of 381 N.E.2d 1023 (Delta Construction, Inc. v. Dressler) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Delta Construction, Inc. v. Dressler, 381 N.E.2d 1023, 64 Ill. App. 3d 867, 21 Ill. Dec. 576, 1978 Ill. App. LEXIS 3358 (Ill. Ct. App. 1978).

Opinion

Mr. JUSTICE ALLOY

delivered the opinion of the court:

Plaintiff Delta Construction, Inc. (hereinafter called Delta), appeals from an order of the Circuit Court of Will County granting defendant’s motion for judgment at the close of the plaintiff’s case.

From the record it is shown that Delta instituted an action against Phil Dressier, individually, and d/b/a Phil Dressier & Associates (hereinafter called Dressier), and, also, against Lockport Township Park District to recover moneys due it under a contract for the asphalt paving of tennis courts and a parking lot at the park district’s racquet club.

Count I of the complaint alleged a contract with Dressier, the general contractor, in the amount of *53,824.19, which sum included moneys due on account of various items of extra work which were allegedly performed by Delta at Dressler’s request. A second count of the complaint, against the park district and Dressier, was dismissed pursuant to section 48 of the Civil Practice Act (Ill. Rev. Stat. 1977, ch. 110, par. 48) by reason of Delta’s failure to bring the action within the period prescribed by statute. The park district was dismissed at that time from the proceeding and no appeal has been taken from the dismissal of that count.

A bench trial was held on count I and, after presentation of Delta’s case, defendant Dressier moved, pursuant to section 64(3) (Ill. Rev. Stat. 1977, ch. 110, par. 64(3)), for a judgment at the close of plaintiff’s evidence. The trial court granted the motion and dismissed the cause, stating that plaintiff had failed to prove a prima facie case. Appeal is taken from the order granting the motion and the consequent dismissal of the action instituted by Delta.

On appeal in this court, Delta contends that its evidence was sufficient to establish a prima facie case for the amount due on the contract and for the extras, and that the trial court’s decision is contrary to the manifest weight of the evidence. We recognize, on the basis of established precedents, that section 64(3) of the Civil Practice Act provides that in ruling on the motion, the trial court shall weigh the evidence. As regards the duties of the trial court on a section 64(3) motion, the Illinois Supreme Court stated in City of Evanston v. Ridgeview House, Inc. (1976), 64 Ill. 2d 40, 57-58, 349 N.E.2d 399:

“In ruling on the defendant’s motion for judgment, therefore, the judge had the duty to pass on the credibility of the witnesses and consider the weight and quality of the evidence. In weighing the evidence, the court had the responsibility to consider all the evidence, including any favorable to the defendant.”

Therefore, it is customary to state that a decision of a trial court on a motion such as the one with which we are concerned normally would not be disturbed unless it is contrary to the manifest weight of the evidence. (City of Evanston v. Ridgeview House, Inc. (1976), 64 Ill. 2d 40, 58.) A reviewing court, however, must re-examine the evidence to determine whether the trial court, after weighing the evidence, erred in deciding that there was a failure to make a prima facie case. Jackson v. Navik (2d Dist. 1976), 37 Ill. App. 3d 88, 346 N.E.2d 116.

In analyzing the cause before us, we note that the record shows that Delta and Dressier entered into a written contract on August 18, 1975, by the terms of which Delta agreed to provide a stone base and an asphalt surface for indoor tennis courts at the racquet club, and to also provide a stone base and asphalt surface for the adjacent outdoor parking lot. The contract provided for lump sum payments of *35,358 and *13,230, respectively, upon completion of the paving. Construction on the tennis courts and parking lot began shortly after Dressier had accepted the contract on August 18, 1975. From the record, it is apparent that the first modification of the contract occurred shortly thereafter, according to James Lavan, Delta’s estimator and chief negotiator with Dressier on the paving job. The original contract called for Delta to prepare the stone base for the tennis courts, but when Delta began work it found that a stone base had already been laid by another party. As a result, Lavan and Phil Dressier met to negotiate an appropriate adjustment to the contract. They agreed upon a lump sum credit to Dressier, in the amount of *9,500, by reason of Delta being relieved of providing the stone base as specified in the written contract. In conjunction with the credit agreed upon, Dressier agreed to an extra charge, on a time and materials basis, for necessary work by Delta in preparing the existing stone base for the asphalt covering. On the basis of the record as submitted, all negotiations for this and subsequent modifications of the contract were conducted orally, although, according to Lavan’s testimony, Dressier would sign all time sheets which reflected the extra work agreed upon by the parties. An invoice covering the modification concerning the stone base as well as the extra work involved in preparing the base was submitted by Delta to Dressier on August 29, 1976, and it was paid promptly.

Lavan further testified in the trial court, that, as work progressed on the job, other modifications in the contract were orally agreed upon between Delta and Dressier. Lavan stated that after Delta had completed its surfacing of the tennis courts, Dressier requested that Delta have its men help in the laying of the carpeting on the tennis courts, a job and work outside the original contract. Again, as stated by Lavan, Dressier agreed to pay on a time and material basis, as per original contract rates, for the extra work requested. Lavan testified to two other occasions when Dressier requested Delta to do work outside the contract on a time and material basis. Delta was requested to perform extra work in installing some culverts and backfilling some curbing which was not part of the original contract. Delta also worked with cleaning up some oil spillage on the tennis courts occasioned by the electrical subcontractor on the job, which it was requested to do by Dressier. Lavan stated that Dressier directed Delta to do the cleanup work, again on a time and material basis, since it was also outside the original scope of the contract between the parties. Lavan also testified that after each of the extra jobs were completed, Delta would have Dressier sign the time sheets on the extra work that had been done by Delta’s crews. Lavan’s testimony, concerning Dressier’s request for work outside the contract and Dressier’s agreement to pay on a time and material basis, stands uncontradicted in the record on appeal in this cause at this stage of the proceedings. The total amount alleged to be due, under the original contract, as modified to include the credit for the existing stone base, as well as the liabilities for the extras requested, was $53,824.19. Delta concedes that Dressier has paid $15,474.32 of that amount.

Plaintiff Delta finished its work on the job on October 21,1975, and on October 27, 1975, it submitted its invoices to Dressier for the remainder claimed to be due under the contract and for the extras performed. The invoices concerning the extras were based, according to Lavan, on the time sheets signed by Dressier.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peak Exteriors, LLC v. Goebel
2021 IL App (2d) 200244-U (Appellate Court of Illinois, 2021)
Warden v. McGraw-Hill Companies, Inc.
98 F. Supp. 2d 971 (N.D. Illinois, 2000)
Evans and Associates, Inc. v. Dyer
615 N.E.2d 770 (Appellate Court of Illinois, 1993)
Mendelson v. Ben A. Borenstein & Co.
608 N.E.2d 187 (Appellate Court of Illinois, 1992)
National Wrecking Co. v. Midwest Terminal Corp.
601 N.E.2d 999 (Appellate Court of Illinois, 1992)
National Wrecking Co. v. MIDWEST TERM. CORP.
601 N.E.2d 999 (Appellate Court of Illinois, 1992)
Berg & Associates, Inc. v. Nelsen Steel & Wire Co.
580 N.E.2d 1198 (Appellate Court of Illinois, 1991)
Folk v. Central National Bank & Trust Co.
567 N.E.2d 1 (Appellate Court of Illinois, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
381 N.E.2d 1023, 64 Ill. App. 3d 867, 21 Ill. Dec. 576, 1978 Ill. App. LEXIS 3358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/delta-construction-inc-v-dressler-illappct-1978.