Mendelson v. Ben A. Borenstein & Co.

608 N.E.2d 187, 240 Ill. App. 3d 605, 181 Ill. Dec. 114, 1992 Ill. App. LEXIS 2016
CourtAppellate Court of Illinois
DecidedDecember 14, 1992
Docket1-91-0645
StatusPublished
Cited by37 cases

This text of 608 N.E.2d 187 (Mendelson v. Ben A. Borenstein & Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mendelson v. Ben A. Borenstein & Co., 608 N.E.2d 187, 240 Ill. App. 3d 605, 181 Ill. Dec. 114, 1992 Ill. App. LEXIS 2016 (Ill. Ct. App. 1992).

Opinion

PRESIDING JUSTICE BUCKLEY

delivered the opinion of the court:

Plaintiff Arthur B. Mendelson filed this suit to recover damages against defendant Ben A. Borenstein & Company based on defendant’s alleged breach of the parties’ construction contract. The circuit court of Cook County entered summary judgment against plaintiff and simultaneously denied plaintiff leave of court to file a third-amended complaint. Plaintiff filed a motion for reconsideration which the circuit court denied. Defendant thereafter filed a petition for sanctions against plaintiff pursuant to Supreme Court Rule 137 (134 Ill. 2d R. 137). Defendant’s petition was denied. Plaintiff appeals from the award of summary judgment and the court’s refusal to permit plaintiff to file a third-amended complaint. Defendant cross-appeals from the denial of his petition for sanctions. We affirm.

On March 20, 1989, plaintiff filed his initial breach of contract action against defendant relating to defendant’s construction of a strip shopping center at the corner of Madison Street and Central Avenue in Chicago. After the grant of various motions to dismiss, plaintiff filed a second-amended complaint on November 3,1989.

Plaintiff’s second-amended complaint alleges that in 1982, the property in question was improved with a building which was destroyed by fire. After the fire, the debris from the destroyed building was dropped into the previous structure’s basement. It is undisputed that both parties knew of the rubbled condition of the property.

On September 17, 1984, plaintiff entered an oral contract with defendant for the construction of a strip shopping center on the property. The parties thereafter drafted a written contract confirming the material terms of their oral agreement. The parties never signed the contract but have, according to plaintiff, governed themselves in accordance with its specifications and requirements.

Section 12.1.1 of the agreement defined a “Change Order” as “a written order to the Contractor signed by the Owner and the Architect, issued after execution of the Contract, authorizing a change in the Work or an adjustment in the Contract Sum or Contract Time.” “Work” to be performed by the contractor was defined as “the completed construction required by the Contract Documents,” which in turn consisted of, among other matters, the architect’s plans and specifications.

The specific paragraphs of plaintiff’s second-amended complaint relevant to this appeal are the following:

“6. At all times relevant ***, it was a material express term of the parties’ contract, that [defendant] would use its best skill and judgment in following the plans and specifications drawn for the project, and would cooperate with the architect in furthering the interests of [plaintiff] throughout the course of completion of the project.
7. Notwithstanding [defendant’s] express duties described above, [defendant] did materially breach such duties in unilaterally deviating from [the] Project’s] plans and specifications, as they pertained to footing and foundation excavation, without the approval of the architect as required under Paragraph *** of the General Conditions of the Contract.
8. More specifically, upon discovering the nature and extent of the poor soil conditions at the Project, [defendant] unilaterally abandoned the Project plans and specifications which *** originally specified that footings would be set at a depth of one foot, eight inches *** and instead, excavated a trench, refilled it with recycled concrete and set the Project footings upon such refilled trench.”

Discovery between the parties included the deposition of Sherwin Braun, the project’s architect, the affidavit of Alvin Frishman, defendant’s project manager, and documents identified by Braun and Frishman. These materials formed the basis of defendant’s summary judgment motion.

Braun testified that he and defendant were familiar with one another from other projects and that defendant introduced his firm to plaintiff. Braun learned that plaintiff and defendant were also very familiar with one another.

Braun testified that his firm entered a contract with plaintiff fdr Braun’s firm to perform architectural services. These services included developing specifications for the building, for which Braun hired a structural engineering firm, creating contract documents for construction, and observing the construction process, during which Braun was to advise and consult with plaintiff and served as his representative. Plaintiff never complained about the specifications as originally drawn.

All parties knew of the rubbled condition of the property. Prior to construction, the parties contemplated that the footings may have to be changed because the extent of the rubble was unknown. The construction plans were drawn with the footings at a standard four feet below “zero zero.” During the construction process, it became clear to all parties that the footings could not be placed as specified in the initial plans. A meeting was accordingly held at defendant’s offices. Plaintiff, Braun, defendant and a soil engineer attended the meeting. The parties discussed various options, including removing the rubble, compacting all the rubble, lowering the footings to virgin soil, and installing compacted fill where the footings were to be placed. All of these options, however, were determined to be prohibitively expensive.

The soil engineer recommended excavating a five-foot trench down to virgin soil, filling it with recycled concrete, and placing the footings on the concrete. Braun contacted his structural engineer, who approved the solution. Braun considered this option to be the appropriate solution and would have recommended another course of action if he thought otherwise. Defendant proceeded with the placement of the footings in accordance with the meeting.

Frishman’s affidavit corroborates Braun’s testimony in all material respects. All parties knew that the rubbled condition would have to be treated during the construction process. At the meeting held to address the problem, options were discussed, and one was selected: A five-foot-wide trench would be dug to virgin soil, with the trench being filled with recycled concrete. The footings would be placed on the concrete. Plaintiff, Braun and the structural engineer specifically approved this method.

On October 11, 1984, Frishman sent a letter to plaintiff confirming this agreement, and he sent a copy of the letter to the architect. Defendant then carried out the agreed solution. Plaintiff and his architect observed the work in progress. The architect issued a “Certificate of Substantial Completion” on January 16, 1986.

In response to defendant’s motion, plaintiff submitted his own affidavit wherein he states that he was familiar with defendant from prior dealings and introduced to the architect by defendant. During the construction process, plaintiff learned from defendant that the foundations could not be set as originally specified in the written contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. The Department of Agriculture
2024 IL App (4th) 230537-U (Appellate Court of Illinois, 2024)
The Ridgeland Corp v. Stonedry, LLC
2022 IL App (1st) 200259-U (Appellate Court of Illinois, 2022)
Christopher Glass and Aluminum, Inc v. Tishman Construction Corporation of Illinois
2020 IL App (1st) 191972-U (Appellate Court of Illinois, 2020)
Boffa Surgical Group LLC v. Managed Healthcare Associates Ltd.
2015 IL App (1st) 142984 (Appellate Court of Illinois, 2015)
Affordable Housing Preservation Foundation v. Wiiams
872 N.E.2d 562 (Appellate Court of Illinois, 2007)
Hartzog v. Martinez
Appellate Court of Illinois, 2007
Beahringer v. Roberts
776 N.E.2d 247 (Appellate Court of Illinois, 2002)
Berg v. Allied Security, Inc.
737 N.E.2d 160 (Illinois Supreme Court, 2000)
Town of Sugarloaf v. IEPA
Appellate Court of Illinois, 1999
Town of Sugar Loaf v. Environmental Protection Agency
712 N.E.2d 393 (Appellate Court of Illinois, 1999)
Hoisington v. ZT-Winston-Salem Associates
516 S.E.2d 176 (Court of Appeals of North Carolina, 1999)
Robertson v. Winnebago County Forest Preserve District
301 Ill. App. 3d 520 (Appellate Court of Illinois, 1998)
Robertson v. WINNEBAGO CTY. FOREST PRESERVE DIST.
703 N.E.2d 606 (Appellate Court of Illinois, 1998)
Berg v. Allied Security, Inc.
Appellate Court of Illinois, 1998
Berg v. ALLIED SEC., INC., CHICAGO
697 N.E.2d 769 (Appellate Court of Illinois, 1998)
Zabel v. Cohn
670 N.E.2d 877 (Appellate Court of Illinois, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
608 N.E.2d 187, 240 Ill. App. 3d 605, 181 Ill. Dec. 114, 1992 Ill. App. LEXIS 2016, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mendelson-v-ben-a-borenstein-co-illappct-1992.