Christopher Glass and Aluminum, Inc v. Tishman Construction Corporation of Illinois

2020 IL App (1st) 191972-U
CourtAppellate Court of Illinois
DecidedSeptember 30, 2020
Docket1-19-1972
StatusUnpublished

This text of 2020 IL App (1st) 191972-U (Christopher Glass and Aluminum, Inc v. Tishman Construction Corporation of Illinois) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Christopher Glass and Aluminum, Inc v. Tishman Construction Corporation of Illinois, 2020 IL App (1st) 191972-U (Ill. Ct. App. 2020).

Opinion

2020 IL App (1st) 191972-U

THIRD DIVISION September 30, 2020

Nos. 1-19-1972 and 1-19-2038, Consolidated

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________

IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT ______________________________________________________________________________

CHRISTOPHER GLASS & ALUMINUM, INC., ) Appeal from the ) Circuit Court of Plaintiff-Appellee and Counterdefendant- ) Cook County. Crossappellant. ) ) v. ) No. 16 L 3919 ) TISHMAN CONSTRUCTION CORPORATION OF ) ILLINOIS, ) ) Honorable Defendant-Appellant and Counterplaintiff- ) Diane M. Shelley, Crossappellee. ) Judge Presiding. ______________________________________________________________________________

PRESIDING JUSTICE HOWSE delivered the judgment of the court. Justices McBride and Burke concurred in the judgment.

ORDER

¶1 Held: The judgment of the circuit court of Cook County is affirmed in part and vacated in part; the trial court’s judgment limiting the plaintiff’s damages to those provided by the terms in the contract is affirmed since the defendant’s breach of contract is affirmed; the trial court’s judgment failing to award damages for the defendant’s separate breach of contract based on an implied warranty of accuracy and sufficiency of its plans and specifications for the plaintiff’s work is vacated and the cause is remanded for the court to clarify its judgment on the plaintiff’s breach of contract claim and to enter an appropriate damages award.

¶2 Plaintiff, Christopher Glass and Aluminum, Inc. (CGA), contracted with defendant,

Tishman Construction Corporation of Illinois, to deliver and install the window system for a 21-

story glass mixed used building defendant was constructing as the general contractor. The 1-19-1972) 1-19-2038)Cons.

parties’ contract included plans and specifications for the window system and, additionally,

specified the window system plaintiff was to install by name and required plaintiff to use that

named system “exclusively.” It was subsequently determined the named window system would

not meet defendant’s requirements for the window system, the installation of the window system

was delayed, and eventually the defendant switched to a different window system. Defendant

terminated the contract, purportedly for cause. Plaintiff filed suit against defendant for breach of

contract and defendant filed counter-claims against plaintiff. Following a bench trial the circuit

court of Cook County entered judgment in favor of plaintiff and against defendant on all claims

in the complaint and counter-claim and awarded plaintiff damages pursuant to a limitation of

damages provision in the contract. Defendant appealed the judgment for damages to the extent

the judgment failed to charge plaintiff with construction delays attributable to the delivery and

installation of the window system. Plaintiff cross-appealed the trial court’s judgement limiting

damages pursuant to a term in the parties’ contract.

¶3 For the following reasons, we affirm in part, vacate in part, and remand with instructions.

¶4 BACKGROUND

¶5 Plaintiff, Christopher Glass and Aluminum, Inc. (CGA), filed a complaint against

defendant, Tishman Construction Corporation of Illinois (Tishman), to recover damages for

wrongful termination of a subcontract related to the construction of a building. Tishman was the

general contractor for the construction project. Tishman contracted CGA to deliver and install

the building’s exterior glass windows (referred to as the “window system” or “window wall

system”). Tishman filed a counter-complaint against CGA seeking damages for CGA’s alleged

breach of the subcontract and fraud in the inducement of the subcontract. The building was to be

-2- 1-19-1972) 1-19-2038)Cons.

a 21-story glass apartment/retail complex. The owner of the building (Owner) and the architect

for the building (hereinafter, “Gensler” or “Architect”) are not parties to this appeal.

¶6 Owner contracted Tishman as the general contractor for the construction of the building.

Architect created drawings and specifications (specifications) for the building. Tishman used

those specifications to contract subcontractors for various elements of the work needed to

construct the building including the exterior windows. Gary Thalheimer was the executive vice-

president and regional manager for Tishman during the relevant time period. Thalheimer

testified that Tishman had no involvement in drafting the specifications. He also testified that

Tishman’s role with respect to the specifications was to “monitor them in terms of ensuring that

what we thought the cost of the project was and the schedule that we had proposed when we

were bidding the project would be adhered to as the design evolved, the plans and specs as they

developed further.”

¶7 The building specifications the architect created regarding the window system are

relevant to the issues on appeal. The relevant section of the specifications is titled “Glazed

Aluminum Curtain Walls.” That section states that it “includes glazed aluminum curtain wall

assemblies for the entire project” and that the “aluminum curtain wall assemblies work includes

*** [g]lass and glazing for the windows, window walls, curtain walls, entrances and storefronts”

and “installations.” The specifications included, but were not limited to, thermal performance

requirements, condensation resistance conditions, and thermal break construction specifications.

Stephen Miller, an employee of Architect and an architect himself, testified that the glass work

was “not a design build project.”

¶8 Tishman sent the specifications to potential subcontractors including potential

subcontractors for the glass work on the building. During a second round of bidding CGA -3- 1-19-1972) 1-19-2038)Cons.

attended a meeting with Architect. Owner and Tishman were present for the meeting, as was

U.S. Aluminum (USA). USA is CGA’s window system vendor. USA is not a party to this

appeal. At this meeting USA proposed using USA’s structurally glazed (4500) system (USA

4500 window system). When asked, “Who first suggested the US Aluminum system?” the lead

architect on the project, Stephen Miller, responded, “Tishman would have.” George Heflin, the

vice-president of sales for USA testified via evidence deposition that at this meeting he

“suggested the use of the 4500T SSG system, which was another unitized window wall system.”

Heflin testified he began “conversing back and forth regarding the merits and the attributes of the

4500T SSG” with Architect’s consultant who was present and the meeting and the consultant

“thought it was an ideal, a system that would be ideally suited for the use in this particular

application.” Ultimately CGA bid on the subcontract. CGA’s bid states it was “pleased to

submit our proposal to furnish materials and labor for the [building] based upon the [‘Glazed

Aluminum Curtain Walls’]” specification Architect prepared (which CGA referred to by number

from the specifications). Thalheimer testified CGA’s bid stated that CGA was “proposing to

furnish and install window wall openings CRL/United States Aluminum CW4500 thermal

window wall system.” Thalheimer testified he interpreted that language to mean “they were

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kellogg Bridge Co. v. Hamilton
110 U.S. 108 (Supreme Court, 1884)
Hollerbach v. United States
233 U.S. 165 (Supreme Court, 1914)
United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
The Austin Company v. The United States
314 F.2d 518 (Court of Claims, 1963)
United States v. Wegematic Corporation
360 F.2d 674 (Second Circuit, 1966)
Economy Fuse & Mfg. Co. v. Raymond Concrete Pile Co.
111 F.2d 875 (Seventh Circuit, 1940)
Brian Properties, Inc. v. Burley
662 N.E.2d 522 (Appellate Court of Illinois, 1996)
Schwehr v. Badalamenti
143 N.E.2d 558 (Appellate Court of Illinois, 1957)
M. I. G. Investments, Inc. v. Marsala
414 N.E.2d 1381 (Appellate Court of Illinois, 1981)
La Salle National Bank v. City of Park Ridge
393 N.E.2d 623 (Appellate Court of Illinois, 1979)
Mitchell v. Jewel Food Stores
568 N.E.2d 827 (Illinois Supreme Court, 1990)
Mendelson v. Ben A. Borenstein & Co.
608 N.E.2d 187 (Appellate Court of Illinois, 1992)
Lopez v. Northwestern Memorial Hospital
873 N.E.2d 420 (Appellate Court of Illinois, 2007)
Fieldcrest Builders, Inc. v. Antonucci
724 N.E.2d 49 (Appellate Court of Illinois, 1999)
W. H. Lyman Construction Co. v. Village of Gurnee
403 N.E.2d 1325 (Appellate Court of Illinois, 1980)
Air Safety, Inc. v. Teachers Realty Corp.
706 N.E.2d 882 (Illinois Supreme Court, 1999)
Galesburg Clinic Ass'n v. West
706 N.E.2d 1035 (Appellate Court of Illinois, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2020 IL App (1st) 191972-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/christopher-glass-and-aluminum-inc-v-tishman-construction-corporation-of-illappct-2020.