Peak Exteriors, LLC v. Goebel

2021 IL App (2d) 200244-U
Appellate Court of Illinois·Decided February 23, 2021·No. 2-20-0244·Unpublished·Cited by 1 cases

Opinion

No. 2-20-0244

Order filed February 23, 2021

NOTICE: This order was filed under Supreme Court Rule 23(b) and is not precedent except in the limited circumstances allowed under Rule 23(e)(l).

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT

PEAK EXTERIORS, LLC, ) Appeal from the Circuit Court ) of Boone County.

Plaintiff-Appellee, )

)

v. ) No. 17-AR-42 )

AMY GOEBEL, ) Honorable ) Ronald A. Barch,

Defendant-Appellant. ) Judge, Presiding.

JUSTICE HUDSON delivered the judgment of the court.

Presiding Justice Bridges and Justice Hutchinson concurred in the judgment.

ORDER

¶1 Held: (1) The trial court’s finding that plaintiff substantially performed its obligations under the parties’ contract in a workman-like manner was not against the manifest weight of the evidence; (2) defendant forfeited her contract-ambiguity argument by failing to raise it in the trial court or adequately developing it on appeal; (3) the trial court did not abuse its discretion in failing to exclude one of plaintiff’s witnesses from the courtroom; and (4) the trial court’s finding that plaintiff did not violate the Consumer Fraud and Deceptive Business Practices Act was not against the manifest weight of the evidence.

¶2 Plaintiff, Peak Exteriors, LLC, filed a complaint for breach of contract in the circuit court of Boone County against defendant, Amy Goebel, alleging that defendant failed to compensate it for replacing the roof on defendant’s home. Defendant filed a counter complaint which, as

amended, alleged breach of contract, breach of warranty, and violations of the Home Repair Remodeling Act (815 ILCS 513/1 et seq. (West 2016)), the Consumer Fraud and Deceptive Business Practices Act (815 ILCS 505/1 et seq. (West 2016)), and the Home Repair Fraud Act (815 ILCS 515/1 et seq. (West 2016)). The matter proceeded to arbitration, following which the arbitrators found in plaintiff’s favor on both its complaint and on defendant’s counter complaint. Defendant rejected the award of the arbitrators and a bench trial followed. After considering the evidence presented by the parties, the trial court entered judgment in plaintiff’s favor in the amount of $14,983.56 plus costs of suit on its complaint and against defendant on her counter complaint. Upon defendant’s motion to reconsider, the court reduced the award in plaintiff’s favor to $13,108.60 plus costs of suit. Defendant subsequently filed a notice of appeal. We affirm.

¶3 I. BACKGROUND

¶4 Early in September 2017, Austin Jacobsen, a field manager for plaintiff, encountered defendant while looking for homes with hail damage. Jacobsen approached defendant, and the two began a conversation. As a result of their discussion, defendant contacted her insurance company, AAA Insurance. A couple of weeks later, Jacobsen returned to meet with the insurance adjuster who was present to inspect the damage to defendant’s roof. The insurance adjuster prepared an estimate of the amount to “repair or replace the damaged items or structures noted by the adjuster at the time of the inspection.” The replacement cost value estimated by the insurance adjuster was $18,069.15.

¶5 After defendant received the estimate from her insurance company, she contacted Jacobsen. On September 28, 2017, Jacobsen and his boss, John Vecchio, met with defendant to review paperwork and sign a contract for a full roof replacement on defendant’s home. The contract, which was for a total of $17,864.02, provided that plaintiff would “tear off” the existing

shingles and underlayment and “replace” the underlayment, ice and water shield, flashings, and plumbing boots.1 The contract also provided for the installation of shingles, roof vents, and fascia. Regarding the type of shingle, the contract required plaintiff to “match existing.” As to the color of the shingle and the roof vents, the contract required plaintiff to “match.” In addition, the contract required plaintiff to obtain a building permit “if applicable.” Defendant signed the contract on her own behalf. Vecchio signed the contract as plaintiff’s representative.

¶6 The building materials were delivered in advance to defendant’s property. A few days after the delivery, plaintiff’s crew began replacing defendant’s roof. The work took two days. Defendant refused to pay plaintiff the amount due under the contract for the work performed. Accordingly, on November 13, 2017, plaintiff filed a complaint against defendant in the circuit court of Boone County for breach of contract. Defendant subsequently filed a counter complaint, which she later amended, alleging breach of contract, breach of warranty, and violations of the Home Repair Remodeling Act (815 ILCS 513/1 et seq. (West 2016)), the Consumer Fraud and Deceptive Business Practices Act (815 ILCS 505/1 et seq. (West 2016)), and the Home Repair Fraud Act (815 ILCS 515/1 et seq. (West 2016)). The matter proceeded to arbitration. The arbitrators found in plaintiff’s favor on both its complaint and on defendant’s counter complaint. Defendant rejected the award of the arbitrators, and a bench trial was held on October 28, 2019.

¶7 Before the trial began, defendant’s attorney made a motion to exclude witnesses. The following exchange then occurred:

1 The $205.13 difference between the insurance adjuster’s estimate and the contract price

was due to gutter work that was not part of the contract.

“MS. VECCHIO [Plaintiff’s attorney]: Judge, I have John Moore. He’s an owner of Peak Exteriors as well and then Austin Jacobsen; he will be our first witness.

THE COURT: Okay.

MR. CHOSTNER [Defendant’s attorney]: I thought Mr. Moore split off from Peak Exteriors Rockford and is now operating out of Peak Exteriors in the burbs.

THE COURT: I have no idea.

MS. VECCHIO: I don’t know why that matters. It’s still Peak Exteriors. He’s the owner of Peak Exteriors with my brother.

MR. CHOSTNER: If it’s a different—

THE COURT: I have a Peak Exteriors, LLC.

MS. VECCHIO: Right.

THE COURT: If that’s a party and an owner, that person will be able to stay.

MR. CHOSTNER: I understand, judge. I’m just wondering if perhaps when they split, if he formed another LLC.

THE COURT: Has there been a split, or are they still part of—

MS. VECCHIO: Peak Exteriors, LLC.

THE COURT: I can’t answer that question without representation from one party to the other as to what the current status is for Peak Exteriors. If somebody in the courtroom is an owner, then they can stay. If they’re not, they’ll have to leave.

MS. VECCHIO: Right. They’re both owners, Judge.”

The following evidence was then adduced at the trial.

¶8 Jacobsen testified that it took two days for the construction crew to replace defendant’s roof. Jacobsen was present the entire time the crew was working on the project. Jacobsen identified

a group of photos showing the old roof and the new roof. At no time during construction or upon completion did defendant approach Jacobsen to indicate that there was a problem with the color or installation of the roof. When the project was done, Jacobsen requested payment from defendant. Defendant never tendered any payment. Jacobsen acknowledged that the ice and water shield “was short just a bit” at the far back left slope of the roof. He also admitted that the insurance estimate contained line items for detaching and resetting gutters, but this was not done.

Free access — add to your briefcase to read the full text and ask questions with AI

Peak Exteriors, LLC v. Goebel, 2021 IL App (2d) 200244-U (Ill. Ct. App. 2021).

2021 IL App (2d) 200244-U (Peak Exteriors, LLC v. Goebel) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

People v. Patton
2024 IL App (5th) 200399-U (Appellate Court of Illinois, 2024)