Doornbos Heating & Air Conditioning, Inc. v. Schlenker

932 N.E.2d 1073, 403 Ill. App. 3d 468
CourtAppellate Court of Illinois
DecidedJuly 12, 2010
Docket1-09-0076
StatusPublished
Cited by35 cases

This text of 932 N.E.2d 1073 (Doornbos Heating & Air Conditioning, Inc. v. Schlenker) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Doornbos Heating & Air Conditioning, Inc. v. Schlenker, 932 N.E.2d 1073, 403 Ill. App. 3d 468 (Ill. Ct. App. 2010).

Opinion

JUSTICE PATTI

delivered the opinion of the court:

NATURE OF THE CASE AND ISSUES PRESENTED FOR REVIEW

Following a bench trial, the trial court entered judgment in favor of Doornbos Heating & Air Conditioning, Inc. (Doornbos), on the mechanic’s lien claim that Doornbos filed against defendants James Schlenker (Schlenker) and Kathleen Elizabeth Schlenker, as trustee of the Kathleen Elizabeth Schlenker Declaration of Trust Dated November 9, 1992, (Trust) (Schlenker and Trust will collectively be referred to as Owners), as well as on the breach of contract counterclaim filed by the Owners. The Owners appeal the circuit court’s judgment, arguing: (1) Doornbos’ claims are barred by section 6 of the Mechanics Lien Act (Act) (770 ILCS 60/1 et seq. (West 2006)); (2) Doornbos failed to prove that it substantially performed pursuant to the contract; (3) Doornbos failed to prove its claim for extras by clear and convincing evidence and failed to prove the amount of damages to which it was entitled; (4) the trial court erred in finding in favor of Doornbos on the Owners’ breach of contract counterclaim; and (5) the trial court erred in granting Doornbos’ motion in limine barring the Owners from presenting evidence pertaining to delay damages. For the reasons contained herein, we affirm the judgment of the circuit court.

STATEMENT OF FACTS

The Trust is the owner in fee simple of the property located at 6311 West 95th Street in Oak Lawn, Illinois, which originally consisted of a one-story medical center (hereinafter the Property). In 1997, the Trust authorized Schlenker, lessee of the Property, to commence a construction project (Project) to expand the existing medical facility located on the Property. The Project initially called for a one-story addition with a surgery center located in the basement of the facility, but was later expanded to consist of a three-story addition with a surgery center located in the lower level. Because the Project involved the construction of a surgery center, it was subject to the requirements of the Illinois Department of Public Health (IDPH), which has stringent ventilation and fire protection standards for buildings containing such amenities. Don Changnon, d/b/a Team Company (Changnon), was hired to be the general contractor of the Project, and Facilities Design, Ltd. (Facilities), was retained as the Project’s architect.

On July 15, 1998, Doornbos submitted a $75,000 budget estimate for the Project’s heating, ventilation and air conditioning (HVAC) system. On January 5, 1999, Doornbos submitted a $89,850 revised budget estimate, accounting for the provision of HVAC services for the basement-level surgery center. Finally, on May 15, 2000, Doornbos submitted a final scope-of-work estimate, which encapsulated Doornbos’ understanding of the necessary HVAC services required for the expanded scope of the Project. Doornbos’ prior scope-of-work estimates were merged into the May 15, 2000, estimate, which formed the basis for the parties’ contract. Pursuant to the May 15, 2000, written contract, Doornbos agreed to provide the necessary labor and materials to construct the HVAC system for the Project in exchange for payment of $493,208. In addition to providing labor and materials, the contract called for Doornbos to “design the complete [HVAC] system, provide drawings, submittals and schedules for approval.”

Initially, Doornbos provided the HVAC services contemplated by its contract and received timely payment therefor. Ultimately, however, problems developed between the Owners and Doornbos. Accordingly, on September 19, 2002, Doornbos recorded a mechanic’s lien claim with the Cook County recorder of deeds and filed a verified complaint to foreclose its lien in the circuit court of Cook County on October 21, 2002. In its complaint, Doornbos alleged that it “furnished all of the materials, services, labor, and equipment required” by the contract as well as additional labor and materials totaling $100,909, bringing the total value of the labor and materials that Doornbos provided to $591,117. Doornbos further alleged that it completed its work on the Project on July 17, 2002. As of that date, Doornbos had received partial payment pursuant to the contract, but was still owed $53,013.65. Accordingly, Doornbos sought to foreclose its mechanic’s lien totaling $53,013.65 and recoup the attorney fees and costs associated with the commencement of bringing its action in the circuit court.

On February 4, 2003, the Owners filed an answer to Doornbos’ complaint to foreclose its mechanic’s lien. In pertinent part, the Owners admitted that they had not paid the amount demanded by Doornbos but denied the material allegations advanced in Doornbos’ complaint to foreclose its lien. Moreover, the Owners asserted a breach of contract counterclaim against Doornbos, contending that Doornbos breached its contract when it:

“(a) Failed to install a collecting system for the condensation from the condensor coils on the roof, causing water to pour down and damage ceiling tiles; (b) Caused the condensing unit to run in reverse, putting additional wear and tear on the unit and interfering with its efficiency; (c) Installed ductwork in violation of existing codes; (d) Installed ducts in the operating room which caused the ceiling to have too little clearance; (e) Multiple VAX boxes to not operate; (f) Fail[ed] to install the shut down alarm system; (g) Fail[ed] to install adequate heating coils in the operating room; (h) Fail[ed] to install an adequate exhaust fan in the operating room; (i) Fail[ed] to install dampers in the verticle ducts; (j) Fail[ed] to install dampers according to manufacturer’s specifications; (k) Fail[ed] to provide adequate ventilation in the computer room; [and] (1) Fail[ed] to provide control of air conditioning units.”

The Owners further alleged that as a direct and proximate cause of Doornbos’ breach of contract, they incurred damages in excess of $500,000. 1

Thereafter, the parties engaged in discovery and the cause ultimately proceeded before a bench trial. Prior to trial, Doornbos filed a motion in limine to bar the Owners from seeking delay damages because they failed to specifically allege that they suffered those damages in their breach of contract counterclaim. The circuit court granted Doornbos’ motion and trial commenced on June 4, 2007. Trial testimony revealed the following:

Robert Doornbos, Doornbos’ owner, testified that his company was in the business of providing HVAC services. Although he was not a mechanical engineer, Robert had previously designed HVAC systems, explaining that he would produce “concept drawings,” which he would turn over to the architect or engineer responsible for overseeing a given construction project. In July 1998, Schlenker requested Doornbos to provide a budget estimate of the costs associated with installing an HVAC system in his medical building. Thereafter, Schlenker requested Robert to provide an estimate for HVAC work for a basement-level surgery center. In making his request, Schlenker advised Robert that the HVAC work would need to be IDPH compliant and that Robert would need to factor in those requirements in designing the basement’s HVAC system.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PML Development LLC v. Village of Hawthorn Woods
2025 IL App (2d) 240191-U (Appellate Court of Illinois, 2025)
Edson v. Horwich
2024 IL App (1st) 221877-U (Appellate Court of Illinois, 2024)
Vanderplow v. Miller
2023 IL App (3d) 230004-U (Appellate Court of Illinois, 2023)
Van Hoekelen Greenhouses, Inc v. Work 6, Inc.
2023 IL App (1st) 220858-U (Appellate Court of Illinois, 2023)
Young v. Wilkinson
2022 IL App (4th) 220302 (Appellate Court of Illinois, 2022)
Phonco Communications, Inc v. Chicago Central Food Mart, Inc
2022 IL App (1st) 210559-U (Appellate Court of Illinois, 2022)
Baja Foods, LLC v. Spartan Surfaces, Inc.
2021 IL App (1st) 201156-U (Appellate Court of Illinois, 2021)
Nutraceuticals v. ZAC Packing, LLC
Appellate Court of Illinois, 2021
Mayster v. Santacruz
2020 IL App (2d) 190840 (Appellate Court of Illinois, 2021)
Peak Exteriors, LLC v. Goebel
2021 IL App (2d) 200244-U (Appellate Court of Illinois, 2021)
American Remodal & Construction, Inc. v. Fernandez
2020 IL App (1st) 192026-U (Appellate Court of Illinois, 2020)
Page v. Alliant Credit Union
N.D. Illinois, 2020
Union Tank Car Co. v. NuDevco Partners Holdings, LLC
2019 IL App (1st) 172858 (Appellate Court of Illinois, 2019)
LB Steel, LLC v. Carlo Steel Corp.
2018 IL App (1st) 153501 (Appellate Court of Illinois, 2018)
Archon Construction Co. Inc. v. U.S. Shelter, LLC
2017 IL App (1st) 153409 (Appellate Court of Illinois, 2017)
Pepper Construction Company v. Palmolive Tower Condominiums, LLC
2016 IL App (1st) 142754 (Appellate Court of Illinois, 2016)
Pyramid Development, LLC v. Dukane Precast, Inc.
2014 IL App (2d) 131131 (Appellate Court of Illinois, 2014)
1472 N. Milwaukee, LTD. v. Feinerman
2013 IL App (1st) 121191 (Appellate Court of Illinois, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
932 N.E.2d 1073, 403 Ill. App. 3d 468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/doornbos-heating-air-conditioning-inc-v-schlenker-illappct-2010.